F Environmental Specification - Air.pdf
PDF 412 KB Posted
- Solicitation number
- NFU2-7623
- Issued by
-
Department of Energy
About this file
This specification outlines requirements for construction services related to the National Energy Research Scientific Computing Center Facility Upgrade II project. Key details include conducting work in accordance with environmental regulations and Lawrence Berkeley National Laboratory policies to protect air quality, including obtaining permits from the Bay Area Air Quality Management District for generators, fueling stations, boilers, and other equipment producing air emissions. Contractors must comply with standards from the California Air Resources Board for onsite vehicles and off-road diesel equipment, and the specification provides qualifications for contractor staff including training, licensing, and certification requirements. The document also specifies submittals the contractor must provide, such as plans for regulatory compliance, records management, unexpected environmental releases, and quality assurance, for review and approval by the Laboratory's Environmental Services Group to ensure standards are met before work begins.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 | P a g e
ENVIRONMENTAL SPECIFICATION – AIR
PART 1 – GENERAL
1.1 SUMMARY
A. This specification section describes Subcontractor requirements that apply to those portions of projects at
Lawrence Berkeley National Laboratory (LBNL) that include environmental protection and environmental restoration activities involving air emissions.
B. All activities must be planned and conducted with full regard to protecting site workers, the public, and the environment, as well as complying with all applicable environmental laws and regulations.
C. The Environmental Services Group (ESG) must review proposed documented work products, including but not limited to work packages, instructions, sampling and quality assurance plans, permit applications, and associated reports to determine if they are consistent with LBNL policies and comply with regulatory requirements.
D. The Subcontractor must provide, in the performance of LBNL environmental activities, labor, materials, equipment, services, and supervision required to conduct work in accordance with all applicable federal, state, and local environmental laws and regulations, and LBNL policies protective of public health and the environment as specified in this section.
PART 2 – PRODUCTS – Not Used
PART 3 – EXECUTION
3.1 OVERVIEW OF RELEVANT ENVIRONMENTAL REGULATIONS, LBNL DOCUMENTS, AND
SPECIFICATIONS
A. This section provides a list of potentially relevant environmental regulations, LBNL documents and procedures, and specifications pertaining to ambient air and stack emissions, vehicle emissions, air sampling, and associated reporting requirements. LBNL documents can be downloaded from the LBNL website and can also be provided in electronic format upon request.
3.2 ENVIRONMENTAL REGULATIONS
Potentially relevant laws and regulations that must be met during the course of a project commonly include, but are not limited to, the following:
A. Bay Area Air Quality Management District (BAAQMD) Rules and Regulations – the regulations listed below cover the requirements associated with permits related to generators, fueling stations, paint spray booths, sand blast booths, boilers, soil vapor extraction systems, and construction work associated with concrete demolition, asbestos demolition, excavations, ambient air and stack emissions monitoring, and building indoor air sampling that must be met during the course of a project.
1. Regulation 2, Rule 2 – New Source Review;
2. Regulation 6, Rule 6 – Prohibition of Trackout;
3. Regulation 8, Rule 4 – General Solvent and Surface Coating Operations;
4. Regulation 8, Rule 7 – Gasoline Dispensing Facilities;
5. Regulation 8, Rule 16 – Solvent Cleaning Operations;
6. Regulation 8, Rule 40 – Aeration of Contaminated Soil and Removal of Underground Storage Tanks
(USTs);
7. Regulation 8, Rule 47 – Air Stripping and Soil Vapor Extraction Operations;
8. Regulation 8, Rule 51 – Adhesive and Sealant Products;
9. Regulation 9, Rule 7 – Nitrogen Oxides and Carbon Monoxide from Industrial, Institutional, and
Commercial Boilers, Steam Generators, and Process Heaters;
10. Regulation 10 – Standards of Performance for New Stationary Sources;
11. Regulation 11, Rule 1 – Lead;
12. Regulation 11, Rule 2 – Asbestos Demolition, Renovation and Manufacturing;
13. Regulation 11, Rule 14 – Asbestos-Containing Serpentine; and
2 | P a g e
14. Regulation 12, Rule 4 – Sandblasting.
B. National Emission Standards for Hazardous Air Pollutants (NESHAP) – this regulation pertains to stack radiological effluent and asbestos measurements and sampling in association with NESHAP compliance.
1. Title 40, Part 61, Subpart H – NESHAP – National Emission Standards for Emissions of Radionuclides
Other Than Radon from Department of Energy (DOE) Facilities
2. Title 40, Part 61, Subpart M of the Code of Federal Regulations including Asbestos NESHAP Revision;
Final Rule, Federal Register– Guidelines for Asbestos NESHAP Demolition and Renovation Inspection
Procedures.
C. California Air Resources Board (CARB) – Contractors must comply with the most current California CARB requirements for all equipment, trucks, offsite vehicles and offsite construction equipment (construction equipment) when performing work for LBNL. All construction equipment will be maintained, and usage hours recorded, and reported, in accordance with CARB requirements.
1. Title 13, Section 2485 – regulates emissions for in-use off-road diesel-fueled vehicles (e.g., tractors), heavy duty vehicles, and off-road large spark-ignition engines (e.g., fork-lifts).
D. Senate Bill 656, Chapter 738 (SB 656, Sher, 2003) – This measure pertains to control measures that can be employed to reduce PM10 and PM2.5, applies to stationary, area-wide, and mobile sources, and designates
CARB as the agency charged with coordinating efforts to attain and maintain ambient air quality standards.
E. CARB, Title 17, Division 3, Chapter 1, Subchapter 10, Article 4 – Pertains to the reduction of Greenhouse
Gas Emissions, including the annual reporting requirements associated with the Sulfur Hexafluoride (SF6)
Emissions Report for Gas Insulated Switchgear.
1. Section 95356 – Annual Reporting Requirements.
F. California Code of Regulations (CCR), Title 8, Division 1 – Occupational Safety – Pertains to permitting, reporting, and requirements associated with demolition work impacting asbestos and/or lead containing materials.
1. Section 5208, Asbestos in General Industry.
2. Section 1529, Asbestos in Construction Industry.
3. Section 3204, Medical and Environmental Records.
4. Section 341, Registration and Permits.
5. Section 1532.1, Contractors State License Board – Lead Standard.
G. California Department of Toxics Control (DTSC) – Promotes state-wide standard practice and consistency for screening buildings for vapor intrusion and to establish appropriate sampling to protect building occupants from vapors off-gassing from contaminated sources.
1. Vapor Intrusion Guidance, 2011.
2. Vapor Intrusion Mitigation Advisory, 2011.
3. Supplemental Guidance: Screening and Evaluating Vapor Intrusion, draft for public comment, February
2020.
H. Code of Federal Regulations (CFR).
1. Title 40, Part 61: Subpart A – General Provisions of the CFR.
2. Title 40, Parts 260 to 265 – Hazardous Waste Management.
3. Title 29, Part 1910 – Occupational Safety and Health Standards – Hazardous Waste Operations and
Emergency Response (HAZWOPER).
I. Department of Energy (DOE).
1. Order 231.1b – Environment, Safety, and Health Reporting
2. Order 243.1 – Records Management Program:
a. Includes a Contractor Requirements Document (CRD) that applies to "contractors that create, receive, use, maintain, disseminate, and/or dispose of DOE records in connection with the performance of DOE-funded tasks or activities.”
3. Order 414.1D – Quality Assurance and the Environmental Restoration Quality Assurance Program Plan
(QAPrP).
4. Order 436.1 – Departmental Sustainability and ISO 14001:2015 – Environmental Management Systems
5. Order 458.1 – Radiation Protection of the Public and the Environment
J. San Francisco Bay Regional Water Quality Control Board.
1. Interim Framework for Assessment of Vapor Intrusion at TCE-Contaminated Sites in the San Francisco
Bay Region, 2014 K. U.S. Environmental Protection Agency (US EPA).
1. Technical Guidance for Assessing and Mitigating the Vapor Intrusion Pathway from Subsurface Vapor
Sources to Indoor Air, 2015.
3 | P a g e
3.3 LBNL ENVIRONMENTAL DOCUMENTS
A. The most current version of the following documents will be provided to the Subcontractor upon request to
LBNL:
1. LBNL Environmental, Health and Safety Manual, PUB-3000 – last updated on March 16, 2017.
2. Annual Site Environmental Report.
3. Environmental Management System Plan.
4. Environmental Restoration Program Annual Progress Report.
5. Quality Assurance Program Plan (QAPrP) for the Environmental Restoration Program.
6. Quality Assurance Program Plan for NESHAP Compliance.
7. NESHAP Stack Effluent Flow Rate Measurement and Sampling System Inspection Report – TP5033.
8. NESHAP Real-Time Stack Flow Calibration Annual Report – TP5032.
9. NESHAP Annual Report.
10. Records Management Plan for the Environmental Service Group Environmental Radiological Protection and Environmental Restoration Programs.
3.4 ENVIRONMENTAL SERVICES GROUP (ESG) PROCEDURES
A. Environmental Document Preparation – Procedure 200.
B. Sample Processing, Packaging, and Transport – Procedure 254.
C. Environmental Sample Tracking and Data Management – Procedure 268.
D. Sitewide Air Sampling – Procedure 280.
E. Air Sampling Equipment Maintenance – Procedure 286.
F. Stack Air Flow Rate Measurement and Calibration – Procedure 287.
G. ESG Built Air Sampling System Manual.
3.5 POTENTIALLY RELEVANT LBNL SPECIFICATIONS
A. This section provides a list of relevant LBNL specifications pertaining to activities that involve environmental air emissions requiring controls, monitoring and/or reporting. These include, but are not limited to:
1. DIVISION 01 – GENERAL REQUIREMENTS:
a. Section 010000 – General Requirements
b. Section 013500 – Special Procedures
c. Section 013529 – Environmental Safety and Health Procedures
d. Section 017419 – Construction Waste Management
2. DIVISION 02 – EXISTING CONDITIONS:
a. Section 024116 – Structure Demo
b. Section 024119 – Selective Structure Demo
c. Section 028200 – Asbestos Abatement
d. Section 028300 – Lead Abatement
3. DIVISION 23 – HEATING, VENTILATION, AND AIR CONDITIONING (HVAC):
a. Section 230111.13 – Testing and Maintenance of HVAC.
b. Section 235223 – Cast Iron Boilers
c. Section 235233 – Water Tube Boilers
d. Section 235239 – Fire Tube Boilers
4. DIVISION 26 – ELECTRICAL:
a. Section 261323 – SF6 Gas Insulated Switches
b. Section 263213 – Stationary Package Engine Generator
c. Section 263213.13 – Mobile Engine Generator
5. DIVISION 31 – EARTHWORK:
a. Section 311000 – Site Clearing
b. Section 312213 – Rough Grading
c. Section 312316 – Excavation
d. Section 312316.13 – Trenching
e. Section 312323 – Backfilling
4 | P a g e
f. Section 315000 – Excavation Support and Protection
6. RADIOLOGICAL PROTECTION SPECIFICATION (rev 4/26/2018)
7. HAZARDOUS, MIXED, AND RADIOACTIVE WASTE MANAGEMENT SPECIFICATION (rev
4/26/2018)
3.6 REQUIRED CONTRACTOR SUBMITTALS
A. The following is a list of documents that may be required to be submitted by the Subcontractor, depending on the specific project’s needs. The documents must be consistent with the LBNL policies listed above and comply with all applicable regulatory requirements.
B. The documents will be reviewed by ESG and will be revised by the Subcontractor in accordance with LBNL comments.
C. If regulatory agency review is required, the Subcontractor will prepare responses to regulatory agency comments and revise the document in accordance with regulatory-agency-approved responses and as directed by LBNL. All responses to regulatory agency comments and revised versions of the documents will be submitted to ESG for review and approval prior to submission to the regulatory agency by LBNL.
D. Any deviations from the LBNL-approved documents must be justified in writing and approved by ESG prior to implementation.
E. The LBNL PM and EHS Environmental Project Coordinator must approve any written communication with regulatory agencies and an LBNL representative must be present for any verbal communication.
F. The minimum requirements for each document, if required, are specified below. Each required document must be comprehensive to comply with the most recent environmental regulations and LBNL policies listed above.
G. Potential document submittals and minimum requirements.
1. Regulatory Agency Compliance Plan
a. If requested by ESG, the Subcontractor will be required to prepare a Regulatory Agency
Compliance Plan. The Regulatory Agency Compliance Plan will describe interactions, including notification and reporting requirements, with regulatory agencies with oversight authority for the project. All environmental-related communications between the project and the regulatory agency, and all documents and other correspondence, must be provided to an LBNL Environmental Project
Coordinator unless otherwise specified by LBNL.
b. The Plan must include, but will not be limited to, the following information:
1. All project-specific regulatory agency compliance requirements;
2. Applicable state and federal laws, their implementing regulations, and applicable regulatory agency guidance documents;
3. Permits and approvals;
4. Names, positions, and contact information for all regulatory agencies;
5. Release notification requirements and actions;
6. Required plans and reports and other deliverables, as applicable;
7. Contingency plans for non-compliance conditions;
8. Certification requirements;
9. Site access;
10. Dispute resolution as it pertains to a remedial action, Record of Decision, or other regulatory-approved project plans; and
11. Subcontractor personnel responsible for regulatory agency compliance.
2. Regulatory Agency Compliance Agreement
a. If requested by a regulatory agency, the Subcontractor will be required to prepare the Regulatory
Agency Compliance Agreement.
b. A compliance agreement with a regulatory agency such as the US EPA Region 9, California
Department of Toxic Substances Control (DTSC), BAAQMD, CARB, and/or the San Francisco Bay
Area Regional Water Quality Control Board may be necessary for environmental investigation and cleanup activities that will specify the regulatory processes that must be followed, including how environmental activities will be conducted and the regulatory agency interactions that will be required.
c. In coordination with LBNL and DOE, the content of the agreement will be based on lead agency requirements.
3. Records/Data Management Plan
5 | P a g e
a. The Records/Data Management Plan provides the requirements, responsibilities, and procedures for managing records/data, including storage and transfer to LBNL, and archiving and retention time. The Plan specifies the requirements for documentation be in accordance with:
1. DOE O 243.1, Records Management Program, which includes a Contractor Requirements
Document (CRD) that applies to "contractors that create, receive, use, maintain, disseminate, and/or dispose of DOE records in connection with the performance of DOE-funded tasks or activities."
2. DOE Order 458.1 requires that environmental radiation protection records be retained until final disposition is authorized by the DOE.
b. LBNL’s Requirements and Policies Manual, which describes LBNL’s institutional records management program, and which is consistent with all applicable laws and DOE requirements.
Records/data to be managed under this Plan include, but are not limited to:
1. Work plans and reports;
2. Technical studies;
3. Risk evaluations;
4. Results of air sampling and chain-of-custody forms;
5. Project documents such as Quality Assurance Plans, Health and Safety Plans, and Sampling
Analysis Plans;
6. Community relations/public participation documents;
7. Comments and responses;
8. Regulatory agency approvals and decision documents; and
9. Files, photographs, sampling and monitoring data, and laboratory analytical reports including hard copies and Electronic Data Deliverables (EDDs).
c. Laboratory analysis EDDs must be in the format required by Specifications for Transmitting
Analytical and Quality Assurance/Quality Control (QA/QC) Data from a Subcontract Analytical
Laboratory to Environment, Health and Safety Division, LBNL, April 26, 2012 (with updates).
4. Environmental Release Report
a. During the course of conducting work under this specification, should an unexpected environmental condition be encountered or an unexpected environmental release occur, an Environmental
Release Report must be prepared by the Subcontractor.
b. Reports submitted to regulatory agencies must be signed by a qualified professional approved by
ESG.
c. If an unexpected release occurs, the report must include the following, as applicable:
1. A summary of the environmental release, including the location, the material released, and the quantity of material released;
2. A description of potential or known impacts to human and environmental receptors;
3. Corrective actions taken to contain the release and media that were impacted by the release;
4. If additional investigation is required to evaluate the extent of the release;
5. Documentation of required regulatory notifications; and
6. All sampling and analytical data.
d. If the unexpected release or condition encountered results in additional investigation, the report must also include the following, as applicable:
1. A summary of investigation results (include tables and figures that summarize sample locations analytical results);
2. A description of the investigation, including methods and procedures and all data necessary to understand the investigation in its entirety;
3. A discussion of key decisions resolved during the investigation; and
4. A discussion of any field or laboratory condition(s) that occurred that may influence the results with summary tables documenting the condition(s) and identifying the sample(s) that may be impacted.
5. Annual Environmental Report Attachments
a. The Subcontractor must provide LBNL an annual report prepared by a qualified professional approved by ESG to be included as an attachment to LBNL’s Site Environmental Report and/or
Environmental Restoration Program Annual Progress Report, if applicable. The report must include, at a minimum:
1. All actions taken to achieve compliance with regulatory agency requirements;
2. A summary of all findings;
3. All problems or potential problems encountered and solutions;
6 | P a g e
4. All projected work for the next fiscal year;
5. A discussion of any changes in personnel that occurred during the reporting period;
6. Summaries of all contacts with representatives of regulatory agencies, the press, local community, or public interest groups;
7. The results of any sampling tests and/or other data generated, including maps showing sample locations and tables of analytical results; and
8. A discussion of any deviation from approved plan requirements, with reasons for the deviation.
6. Quality Assurance Project Plan
a. The Quality Assurance Project Plan (QAPP) provides the project quality assurance requirements for collecting and analyzing project specific environmental data involving the investigation and cleanup if required for ambient air and stack emissions monitoring and building indoor air sampling.
The QAPP may be a component of the Sampling and Analysis Plan.
b. The QAPP must comply with EPA Region 9 Guidance for Quality Assurance Project Plans and meet the requirements of DOE Order 414.1D Quality Assurance and the ESG Environmental
Restoration Program QAPrP.
c. The QAPP must contain, but is not limited to, the following four main elements:
1. Program Management: Addresses program objectives, roles, and responsibilities.
2. Data Generation and Acquisition: Addresses all aspects of program data generation and describes procedures to ensure that appropriate methods for data collection or sampling;
measurement, analysis, and data generation; data handling; and QC activities are employed and properly documented. This includes development of Data Quality Objectives (DQOs).
3. Assessment and Oversight: Addresses the activities to assess the effectiveness of the implementation of the program and associated QA and QC activities.
4. Data Review and Usability: Addresses the QA activities that occur after the data collection or generation phase.
7. Sampling and Analysis Plan
a. The Sampling and Analysis Plan (SAP) establishes the requirements for collecting environmental data for investigation and monitoring of indoor air, if required.
b. Guidance for preparing a SAP is provided in EPA Region 9 Sampling and Analysis Plan Guidance and Template Version 4, General Projects R9QA/009, 1 May 2014.
c. Air sampling specific sampling guidance is provided in the DTSC Guidance for the Evaluation and
Mitigation of Subsurface Vapor Intrusion to Indoor Air (Vapor Intrusion Guidance).
d. The SAPs must be prepared by a qualified professional approved by ESG and approved by the
Subcontractor PM, and submitted to and approved by ESG before any samples are collected.
e. Sample analysis must comply with LBNL’s policies and procedures. Contracted laboratories must provide EDDs that are compatible with LBNL’s ESM database.
f. Subcontractors must use analytical laboratories with existing contracts with LBNL. Potential exceptions require pre-approval by ESG.
g. At a minimum, the SAP must establish DQOs and include, but will not be limited to, the following for all sampling, monitoring, and analytical activities:
1. A description of the activities that require sampling and analysis;
2. Identification of the contaminants of potential concern (COPCs);
3. Sampling design, including specification of the number, locations, and depths where samples will be collected. The sampling design should in most cases include a conceptual site model that incorporates existing data and provides a basis for the sampling design;
4. Sampling and analysis approach, including description of the sampling equipment and requirements for collecting, labeling, storing, and transporting samples to the laboratory;
5. Sample analysis requirements, the analytical methods to be used, holding times, and the required reporting limits;
6. The names, addresses, and telephone numbers of the analytical laboratories; and
7. The SAP must be submitted as a stand-alone document and as such will reference relevant elements contained in the QAPP.
8. Project-Specific Memoranda
a. Site Environmental Report for Project Activities:
1. The annual report is prepared by ESG and is due to the DOE at the end of each September. It is the Subcontractor’s responsibility to provide details pertaining to project-related tasks involving ambient air and stack emissions monitoring, heavy duty truck and off-road diesel
7 | P a g e vehicle emissions, and indoor air sampling for the previous calendar year by August 1st so that they can be included in the report.
2. The information must meet the reporting requirements of DOE Order 231.1b, Environment, Safety, and Health Reporting.
b. Environmental Restoration Program Annual Progress Report for Project Activities:
1. The Annual Progress Report is prepared by ESG and is due to the DTSC annually by the end of February. It is the Subcontractor’s responsibility to provide a project-specific memorandum including details pertaining to activities involving air by December 31st so that they can be included in the report. The memorandum must describe activities involving air, including, but not limited to, tables and figures summarizing sampling and analysis results, and regulatory agency actions.
2. If work conducted is a corrective action, the information must meet the reporting requirements of LBNL’s approved RCRA Corrective Action Program.
3.7 SUBCONTRACTOR QUALIFICATION, TRAINING AND CERTIFICATION REQUIREMENTS
A. Qualifications of the assigned Subcontractor and personnel include, but are not limited to:
1. Knowledge of federal, State of California, and local environmental regulations and their applicability
(Part 3.2 above);
2. Professional registration or applicable certification as required by the regulations;
3. All diesel fueled off-road vehicles (tractors) used onsite must be registered in CARB’s In-Use Off-Road
Diesel-Fueled Fleets Regulation having CARB’s red and white equipment identification number (EIN) number clearly visible on each side of the vehicle. All heavy duty trucks (>10,000 pounds) will conform to CARB regulations;
4. The Subcontractor must be properly licensed as required by the State of California. Specialty licenses may be required (e.g. C-57 drilling license).
B. Training requirements of the assigned Subcontractor and personnel include, but are not limited to:
1. If the project involves hazardous substance removal or other activities that expose or potentially expose personnel to hazardous substances and health hazards, those personnel must possess a current 40-hour HAZWOPER training certificate and have received a minimum of three days field experience under the direct supervision of a trained experienced supervisor as required under 40 CFR 1910.120.
2. Workers that are onsite only occasionally for a specific limited task (such as, but not limited to land surveying or geophysical surveying) and who are unlikely to be exposed over permissible exposure limits (PELs) must possess a current 24-hour occasional site worker HAZWOPER certificate and one day of field experience under the direct supervision of a trained, experienced supervisor.
3. The Supervisor of HAZWOPER personnel must have 8-hour HAZWOPER Supervisor training in addition to the 40-hour training.
4. All 40 and 24-hour HAZWOPER-certified personnel must also possess a current (within the last year) 8-hour HAZWOPER refresher training certification.
C. Certifications required of the assigned Subcontractor and personnel include, but are not limited to:
1. Environmental investigation and sampling work associated with building indoor air and ambient air and stack emissions monitoring must be performed under the supervision of a licensed professional approved by ESG with requisite training and experience in conducting environmental investigations.
2. NESHAP-required air monitoring of radiological emissions requires a Certified Health Physicist (CHP) to supervise radiological work and to maintain authorizations, permit, and authorization database.
3. Sample locations must be surveyed either by a licensed surveyor or LBNL approved personnel with appropriate training in surveying and mapping.
4. Chemical and radiological analyses must be performed by a laboratory that is certified by both the
California State Water Resources Control Board and the Environmental Laboratory Accreditation
Program and is accredited by a third party overseen by the Department of Energy.
8 | P a g e
3.8 CONTRACTOR ROLES AND RESPONSIBILITIES
A. The Subcontractor is responsible for project oversight and execution of the work; verifying that work is conducted in a safe manner and meets all regulatory requirements; submitting to ESG required documents for review and approval; and preparing permit applications and/or draft notices to regulatory agencies (Part
3.10). Subcontractor must provide qualified personnel to fulfill the following roles. Depending on the size of the project, one or more of the roles may be assigned to one on-site person:
1. Subcontractor Project Manager (PM) – The PM has responsibility for project oversight of the work plan development and implementation processes for environmental protection and restoration activities associated with ambient air, stack emissions monitoring, and building indoor air sampling.
2. Environmental Professional (EP) – The EP will oversee the field activities, verify that all documentation is maintained, and provide input regarding field conditions that may require changes to the work plan or notification to agencies.
3.9 DOCUMENT APPROVAL PROCESS
A. All documents, whether new or adopted, must be approved by LBNL.
B. Subcontractor-prepared documents will be submitted to the LBNL Technical Representative identified by the
Contract, who will distribute documents to their selected LBNL review team.
C. Internal draft, draft, and final versions of documents are required. A response to comments table may be required for large deliverables as stipulated by LBNL.
D. Subcontractor should assume complete high-quality documents will require 10 working days for review by
LBNL; inadequate or incomplete documents will require longer review, multiple review cycles, or result in document rejection.
3.10 REQUIRED PERMITTING
Unless otherwise specified, permits will be prepared by the Subcontractor and submitted to the applicable agency by the LBNL Project Manager or ESG representative. Required permits may include, but are not limited to, the following:
A. BAAQMD:
1. Stand by generators
2. Fueling Stations
3. Boilers
4. Asbestos demolition/ Asbestos containing structural concrete demolition – Submit proof of notification made to the BAAQMD, 10 working days prior to asbestos demolition or renovation activities, as required by BAAQMD Regulation 11, Rule 2;
5. UST removal – BAAQMD regulates pollutant emissions from soil contaminated by organic or petroleum chemical leaks or spills, and from USTs when they are removed or replaced. Prior to beginning UST removals or associated soil excavation, Tank Removal Excavation of Contaminated Soil Notification must be completed and submitted to BAAQMD.
File details come from the government source that posted it. Updated .