This file contains a price proposal form and related federal contract opportunity for construction services for the National Energy Research Scientific Computing Center Facility Upgrade II project. The price proposal form requests lump sum pricing for the base scope of work and six independent options, including replacing/upgrading variable frequency drives, upgrading motors, adding platform extensions and air handling units, and installing an electrical switch station, duct bank and feeds. Offerors must submit pricing using the standardized Excel template by the specified due date. The related federal contract opportunity is a solicitation from the Department of Energy and Lawrence Berkeley National Laboratory seeking proposals for the construction of the NERSC Facility Upgrade II project. A mandatory pre-proposal conference and on-site inspection will be held on February 21, 2024. Offerors should email the point of contact to register attendance at least 72 hours in advance to allow for site access.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1-Instructions
| PRICE PROPOSAL FOR LUMP SUM CONSTRUCTION SUBCONTRACTS |
| RFP No. NFU2-7623 |
| PROJECT NFU2 (NERSC Facility Upgrade II) |
| OFFEROR / FIRM NAME |
| SUBMITTED BY: |
| OFFEROR / FIRM COMPANY NAME |
| CONTACT PERSON |
| TELEPHONE NO. |
| EMAIL ADDRESS |
| DATE SUBMITTED |
| The price proposal submitted by the Offeror is submitted on this Excel Sheet. Fill in each tab as applicable. | |
| Sheet 1 | Instructions |
| Sheet 2 | Price Summary |
| Sheet 3 | Base Scope of Work |
| Sheet 4 | Indep. Option 1 - Replace/upgrade VFD for CWGP-1 and CWGP-2 |
| Sheet 5 | Indep. Option 2 - Upgrade motor for CT-1, CT-2 and CT-4 |
| Sheet 6 | Indep. Option 3 - Replace/upgrade VFD for TWGP-1 and TWGP-2 |
| Sheet 7 | Indep. Option 4 - Add first platform extension to accommodate six (6) total ACHE Fan Array Bays; add one (1) ACHE fan unit for a total of four (4) ACHE |
| Sheet 8 | Indep. Option 5 - Add second platform extension to accommodate nine (9) total ACHE Fan Array Bays; add two (2) ACHE fan unit for a total of six (6) ACHE |
| Sheet 9 | Indep. Option 6 - Add electrical switch station A8, duct bank, feeds to substations in North Electrical Room |
| Offeror acknowledges that it is the Offeror’s responsibility to ascertain whether any RFP Addenda have been issued and if so, to obtain copies of such Addenda from the University Procurement Representative. Offeror agrees to be bound by all Addenda that have been issued for this RFP, and acknowledges that all Addenda that have been issued for this RFP have been fully contemplated in the price(s) listed in this offer. Failure to acknowledge receipt of all RFP Addenda may render an offer non-responsive. Offeror acknowledges the receipt of the following addenda to the RFP (please list all that the offeror has received prior to submitting this offer): | |
| Addendum Number | Dated |
Add rows as needed
| Contractor and Lower-Tier Subcontractor Licenses - Offeror certifies it is properly licensed to perform the type of work described in the RFP, by the California Contractors State License Board, and has the following active license(s): | ||
| License Type * | License Number | Expiration Date |
* add a separate page if needed
2 - Price Summary
| Instructions: | All fields are filled from other tabs. Do not edit this tab. | |
| PROPOSED PRICE | ||
| Lump Sum Fixed Price for Base Scope and Independent Option(s) | ||
| Total Price: | $ - 0 | |
| Base Scope: | $ - 0 | |
| Independent Option 1: | $ - 0 | |
| Independent Option 2: | $ - 0 | |
| Independent Option 3: | $ - 0 | |
| Independent Option 4: | $ - 0 | |
| Independent Option 5: | $ - 0 | |
| Independent Option 6: | $ - 0 |
3 - Base Scope of Work
| Instructions | Fill in every field, if you have no price in a section fill in $0 | ||
| PROPOSED PRICE | |||
| Level 1 | Level 2 | Level 3 | Individual Cost Element |
| Major Group Elements | Group Elements | Individual Elements | |
| A. SUPERSTRUCTURE | A10 - Foundations | ||
| A1010 - Standard Foundations | $ - 0 | ||
| A1020 - Special Foundations | $ - 0 | ||
| A1030 – Slab on Grade | $ - 0 | ||
| A20 - Basement Construction | |||
| A2010 - Basement Excavation | $ - 0 | ||
| A2020 - Basement Walls | $ - 0 | ||
| Subtotal | $ - 0 | ||
| B. SHELL | B10 - Superstructure | ||
| B1010 - Floor Construction | $ - 0 | ||
| B1020 - Roof Construction | $ - 0 | ||
| B20 - Exterior Closure | |||
| B2010 - Exterior Walls | $ - 0 | ||
| B2020 - Exterior Windows | $ - 0 | ||
| B2030 – Exterior Doors | $ - 0 | ||
| B30 - Roofing | |||
| B3010 - Roof Coverings | $ - 0 | ||
| B3020 - Roof Openings | $ - 0 | ||
| Subtotal | $ - 0 | ||
| C. INTERIORS | C10 - Interior Construction | ||
| C1010 - Partitions | $ - 0 | ||
| C1020 - Interior Doors | $ - 0 | ||
| C30 - Interior Finishes | |||
| C3010 - Wall Finishes | $ - 0 | ||
| Subtotal | $ - 0 | ||
| D. SERVICES | D20 - Plumbing | ||
| D2010 - Plumbing Fixtures | $ - 0 | ||
| D2020 - Domestic Water Distribution | $ - 0 | ||
| D2030 - Sanitary Waste | $ - 0 | ||
| D2040 - Rain Water Drainage | $ - 0 | ||
| D30 - HVAC | |||
| D3020 - Heat Generating Systems | $ - 0 | ||
| D3030 - Cooling Generating Systems | $ - 0 | ||
| D3040 - Distribution Systems | $ - 0 | ||
| D3050 - Terminal & Package Units | $ - 0 | ||
| D3060 - Controls & Instrumentation | $ - 0 | ||
| D3070 - Special HVAC Systems & Equipment | $ - 0 | ||
| D3080 - Systems Testing & Balancing | $ - 0 | ||
| D40 - Fire Protection | |||
| D4010 - Fire Protection Sprinkler Systems | $ - 0 | ||
| D4030 - Fire Protection Specialties | $ - 0 | ||
| D4040 - Special Electrical Systems | $ - 0 | ||
| D50 - Electrical | |||
| D5010 - Electrical Service & Distribution | $ - 0 | ||
| D5020 - Lighting & Branch Wiring | $ - 0 | ||
| D5030 - Communication & Security Systems | $ - 0 | ||
| D5040 - Special Electrical Systems | $ - 0 | ||
| Subtotal | $ - 0 | ||
| E - REMOVED | |||
| F. SPECIAL CONSTRUCTION & DEMOLITION | F10 - Special Construction | ||
| F1010 - Special Structures | $ - 0 | ||
| F1020 - Integrated Construction | $ - 0 | ||
| F1030 - Special Construction Systems | $ - 0 | ||
| F20 - Selective Building Demolition | |||
| F2010 - Building Elements Demolition | $ - 0 | ||
| Subtotal | $ - 0 | ||
| G. BUILDING SITEWORK | G10 - Site Preparation | ||
| G1010 - Site Clearing | $ - 0 | ||
| G1020 - Site Demolition & Relocations | $ - 0 | ||
| G1030 - Site Earthwork | $ - 0 | ||
| G20 - Site Improvements | |||
| G2020 - Parking Lots | $ - 0 | ||
| G2030 - Pedestrian Paving | $ - 0 | ||
| G2040 - Site Development | $ - 0 | ||
| G2050 - Landscaping | $ - 0 | ||
| G30 - Site Civil/Mechanical Utilities | |||
| G3010 - Water Supply & Distribution Systems | $ - 0 | ||
| G3020 - Sanitary Sewer Systems | $ - 0 | ||
| G3030 - Storm Sewer Systems | $ - 0 | ||
| G40 - Site Electrical Utilities | |||
| G4010 - Electrical Distribution | $ - 0 | ||
| G4020 - Exterior Lighting | $ - 0 | ||
| G50 - Other Site Construction | |||
| G4020 - Other Site Systems & Equipment | $ - 0 | ||
| Subtotal | $ - 0 | ||
| Subtotal of Level 3 Costs | $ - 0 | ||
| OVERHEAD, PROFIT, INSURANCE & BOND PREMIUMS | |||
| Bottom-Line Costs | Overhead | $ - 0 | |
| Profit | $ - 0 | ||
| Insurance Premium | $ - 0 | ||
| Bond Premium | $ - 0 | ||
| Subtotal of Overhead, Profit, Insurance & Bonds Premiums | $ - 0 | ||
| TOTAL PROPOSED PROJECT PRICE | |||
| TOTAL PROPOSED BASE PRICE | Subtotal of Level 3 Individual Element Costs | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bond Cost Elements | $ - 0 | ||
| TOTAL PROPOSED BASE PRICE | $ - 0 |
4 - Option 1
| Instructions | Fill in every field, if you have no price in a section fill in $0 | |
| Indep. Option 1 - | Replace/upgrade VFD for CWGP-1 and CWGP-2 | |
| Level 1 | Level 2 | Individual Cost Element |
| Group Elements | Individual Elements | |
| A10 - Foundations | ||
| A1010 - Standard Foundations | $ - 0 | |
| A1020 - Special Foundations | $ - 0 | |
| A1030 – Slab on Grade | $ - 0 | |
| A20 - Basement Construction | ||
| A2010 - Basement Excavation | $ - 0 | |
| A2020 - Basement Walls | $ - 0 | |
| Subtotal | $ - 0 | |
| B10 - Superstructure | ||
| B1010 - Floor Construction | $ - 0 | |
| B1020 - Roof Construction | $ - 0 | |
| B20 - Exterior Closure | ||
| B2010 - Exterior Walls | $ - 0 | |
| B2020 - Exterior Windows/Doors | $ - 0 | |
| B30 - Roofing | ||
| B3010 - Roof Coverings | $ - 0 | |
| B3020 - Roof Openings | $ - 0 | |
| Subtotal | $ - 0 | |
| C10 - Interior Construction | ||
| C1010 - Partitions | $ - 0 | |
| C1020 - Interior Doors | $ - 0 | |
| C1030 - Specialties | $ - 0 | |
| C20 - Staircases | ||
| C2010 - Stair Construction | $ - 0 | |
| C2020 - Stair Finishes | $ - 0 | |
| C30 - Interior Finishes | ||
| C3010 - Wall Finishes | $ - 0 | |
| C3020 - Floor Finishes | $ - 0 | |
| C3030 - Ceiling Finishes | $ - 0 | |
| Subtotal | $ - 0 | |
| D10 - Conveying Systems | ||
| D1010 - Elevators | $ - 0 | |
| D1020 - Escalators & Moving Walks | $ - 0 | |
| D1030 - Material Handling Systems | $ - 0 | |
| D20 - Plumbing | ||
| D2010 - Plumbing Fixtures | $ - 0 | |
| D2020 - Domestic Water Distribution | $ - 0 | |
| D2030 - Sanitary Waste | $ - 0 | |
| D2040 - Rain Water Drainage | $ - 0 | |
| D2050 - Special Plumbing Systems | $ - 0 | |
| D30 - HVAC | ||
| D3010 - Energy Supply | $ - 0 | |
| D3020 - Heat Generating Systems | $ - 0 | |
| D3030 - Cooling Generating Systems | $ - 0 | |
| D3040 - Distribution Systems | $ - 0 | |
| D3050 - Terminal & Package Units | $ - 0 | |
| D3060 - Controls & Instrumentation | $ - 0 | |
| D3070 - Special HVAC Systems & Equm't | $ - 0 | |
| D3080 - Systems Testing & Balancing | $ - 0 | |
| D40 - Fire Protection | ||
| D4010 - Fire Protection Sprinkler Systems | $ - 0 | |
| D4020 - Stand-Pipe & Hose Systems | $ - 0 | |
| D4030 - Fire Protection Specialties | $ - 0 | |
| D4040 - Special Electrical Systems | $ - 0 | |
| D50 - Electrical | ||
| D5010 - Electrical Service & Distribution | $ - 0 | |
| D5020 - Lighting & Branch Wiring | $ - 0 | |
| D5030 - Communication & Security Sys | $ - 0 | |
| D5040 - Special Electrical Systems | $ - 0 | |
| Subtotal | $ - 0 | |
| E10 - Equipment | ||
| E1010 - Commercial Equipment | $ - 0 | |
| E1020 - Institutional Equipment | $ - 0 | |
| E1030 - Vehicular Equipment | $ - 0 | |
| E1040 - Other Equipment | $ - 0 | |
| E20 - Furnishings | ||
| E2010 - Fixed Furnishings | $ - 0 | |
| E2020 - Movable Furnishings | $ - 0 | |
| Subtotal | $ - 0 | |
| F10 - Special Construction | ||
| F1010 - Special Structures | $ - 0 | |
| F1020 - Integrated Construction | $ - 0 | |
| F1030 - Special Construction Systems | $ - 0 | |
| F1040 - Special Facilities | $ - 0 | |
| F1050 - Special Controls & Instrumentation | $ - 0 | |
| F20 - Selective Building Demolition | ||
| F2010 - Building Elements Demolition | $ - 0 | |
| F2020 - Hazardous Components Abatement | $ - 0 | |
| Subtotal | $ - 0 | |
| G10 - Site Preparation | ||
| G1010 - Site Clearing | $ - 0 | |
| G1020 - Site Demolition & Relocations | $ - 0 | |
| G1030 - Site Earthwork | $ - 0 | |
| G1040 - Hazardous Waste Remediation | $ - 0 | |
| G20 - Site Improvements | ||
| G2010 - Roadways | $ - 0 | |
| G2020 - Parking Lots | $ - 0 | |
| G2030 - Pedestrian Paving | $ - 0 | |
| G2040 - Site Development | $ - 0 | |
| G2050 - Landscaping | $ - 0 | |
| G30 - Site Civil/Mechanical Utilities | ||
| G3010 - Water Supply & Distribution Sys | $ - 0 | |
| G3020 - Sanitary Sewer Systems | $ - 0 | |
| G3030 - Storm Sewer Systems | $ - 0 | |
| G3040 - Heating Distribution | $ - 0 | |
| G3050 - Cooling Distribution | $ - 0 | |
| G3060 - Fuel Distribution | $ - 0 | |
| G3070 - Other Civil/Mechanical Utilities | $ - 0 | |
| G40 - Site Electrical Utilities | ||
| G4010 - Electrical Distribution | $ - 0 | |
| G4020 - Exterior Lighting | $ - 0 | |
| G4030 - Exterior Comm's & Security | $ - 0 | |
| G4040 - Other Electrical Utilities | $ - 0 | |
| G50 - Other Site Construction | ||
| G4010 - Service Tunnels | $ - 0 | |
| G4020 - Other Site Systems & Equipment | $ - 0 | |
| Subtotal | $ - 0 | |
| SUBTOTAL Level 3 Individual Element Costs | $ - 0 | |
| OVERHEAD, PROFIT, INSURANCE & BOND PREMIUMS | ||
| Overhead | $ - 0 | |
| Profit | $ - 0 | |
| Insurance Premium | $ - 0 | |
| Bond Premium | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bonds Premiums | $ - 0 | |
| TOTAL PROPOSED PROJECT PRICE | ||
| Subtotal of Level 3 Individual Element Costs | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bond Cost Elements | $ - 0 | |
| Indep. Option 1 - TOTAL PROPOSED PROJECT PRICE | $ - 0 |
5 - Option 2
| Instructions | Fill in every field, if you have no price in a section fill in $0 | |
| Indep. Option 2 - | Upgrade motor for CT-1, CT-2, and CT-4 | |
| Level 1 | Level 2 | Individual Cost Element |
| Group Elements | Individual Elements | |
| A10 - Foundations | ||
| A1010 - Standard Foundations | $ - 0 | |
| A1020 - Special Foundations | $ - 0 | |
| A1030 – Slab on Grade | $ - 0 | |
| A20 - Basement Construction | ||
| A2010 - Basement Excavation | $ - 0 | |
| A2020 - Basement Walls | $ - 0 | |
| Subtotal | $ - 0 | |
| B10 - Superstructure | ||
| B1010 - Floor Construction | $ - 0 | |
| B1020 - Roof Construction | $ - 0 | |
| B20 - Exterior Closure | ||
| B2010 - Exterior Walls | $ - 0 | |
| B2020 - Exterior Windows/Doors | $ - 0 | |
| B30 - Roofing | ||
| B3010 - Roof Coverings | $ - 0 | |
| B3020 - Roof Openings | $ - 0 | |
| Subtotal | $ - 0 | |
| C10 - Interior Construction | ||
| C1010 - Partitions | $ - 0 | |
| C1020 - Interior Doors | $ - 0 | |
| C1030 - Specialties | $ - 0 | |
| C20 - Staircases | ||
| C2010 - Stair Construction | $ - 0 | |
| C2020 - Stair Finishes | $ - 0 | |
| C30 - Interior Finishes | ||
| C3010 - Wall Finishes | $ - 0 | |
| C3020 - Floor Finishes | $ - 0 | |
| C3030 - Ceiling Finishes | $ - 0 | |
| Subtotal | $ - 0 | |
| D10 - Conveying Systems | ||
| D1010 - Elevators | $ - 0 | |
| D1020 - Escalators & Moving Walks | $ - 0 | |
| D1030 - Material Handling Systems | $ - 0 | |
| D20 - Plumbing | ||
| D2010 - Plumbing Fixtures | $ - 0 | |
| D2020 - Domestic Water Distribution | $ - 0 | |
| D2030 - Sanitary Waste | $ - 0 | |
| D2040 - Rain Water Drainage | $ - 0 | |
| D2050 - Special Plumbing Systems | $ - 0 | |
| D30 - HVAC | ||
| D3010 - Energy Supply | $ - 0 | |
| D3020 - Heat Generating Systems | $ - 0 | |
| D3030 - Cooling Generating Systems | $ - 0 | |
| D3040 - Distribution Systems | $ - 0 | |
| D3050 - Terminal & Package Units | $ - 0 | |
| D3060 - Controls & Instrumentation | $ - 0 | |
| D3070 - Special HVAC Systems & Equm't | $ - 0 | |
| D3080 - Systems Testing & Balancing | $ - 0 | |
| D40 - Fire Protection | ||
| D4010 - Fire Protection Sprinkler Systems | $ - 0 | |
| D4020 - Stand-Pipe & Hose Systems | $ - 0 | |
| D4030 - Fire Protection Specialties | $ - 0 | |
| D4040 - Special Electrical Systems | $ - 0 | |
| D50 - Electrical | ||
| D5010 - Electrical Service & Distribution | $ - 0 | |
| D5020 - Lighting & Branch Wiring | $ - 0 | |
| D5030 - Communication & Security Sys | $ - 0 | |
| D5040 - Special Electrical Systems | $ - 0 | |
| Subtotal | $ - 0 | |
| E10 - Equipment | ||
| E1010 - Commercial Equipment | $ - 0 | |
| E1020 - Institutional Equipment | $ - 0 | |
| E1030 - Vehicular Equipment | $ - 0 | |
| E1040 - Other Equipment | $ - 0 | |
| E20 - Furnishings | ||
| E2010 - Fixed Furnishings | $ - 0 | |
| E2020 - Movable Furnishings | $ - 0 | |
| Subtotal | $ - 0 | |
| F10 - Special Construction | ||
| F1010 - Special Structures | $ - 0 | |
| F1020 - Integrated Construction | $ - 0 | |
| F1030 - Special Construction Systems | $ - 0 | |
| F1040 - Special Facilities | $ - 0 | |
| F1050 - Special Controls & Instrumentation | $ - 0 | |
| F20 - Selective Building Demolition | ||
| F2010 - Building Elements Demolition | $ - 0 | |
| F2020 - Hazardous Components Abatement | $ - 0 | |
| Subtotal | $ - 0 | |
| G10 - Site Preparation | ||
| G1010 - Site Clearing | $ - 0 | |
| G1020 - Site Demolition & Relocations | $ - 0 | |
| G1030 - Site Earthwork | $ - 0 | |
| G1040 - Hazardous Waste Remediation | $ - 0 | |
| G20 - Site Improvements | ||
| G2010 - Roadways | $ - 0 | |
| G2020 - Parking Lots | $ - 0 | |
| G2030 - Pedestrian Paving | $ - 0 | |
| G2040 - Site Development | $ - 0 | |
| G2050 - Landscaping | $ - 0 | |
| G30 - Site Civil/Mechanical Utilities | ||
| G3010 - Water Supply & Distribution Sys | $ - 0 | |
| G3020 - Sanitary Sewer Systems | $ - 0 | |
| G3030 - Storm Sewer Systems | $ - 0 | |
| G3040 - Heating Distribution | $ - 0 | |
| G3050 - Cooling Distribution | $ - 0 | |
| G3060 - Fuel Distribution | $ - 0 | |
| G3070 - Other Civil/Mechanical Utilities | $ - 0 | |
| G40 - Site Electrical Utilities | ||
| G4010 - Electrical Distribution | $ - 0 | |
| G4020 - Exterior Lighting | $ - 0 | |
| G4030 - Exterior Comm's & Security | $ - 0 | |
| G4040 - Other Electrical Utilities | $ - 0 | |
| G50 - Other Site Construction | ||
| G4010 - Service Tunnels | $ - 0 | |
| G4020 - Other Site Systems & Equipment | $ - 0 | |
| Subtotal | $ - 0 | |
| SUBTOTAL Level 3 Individual Element Costs | $ - 0 | |
| OVERHEAD, PROFIT, INSURANCE & BOND PREMIUMS | ||
| Overhead | $ - 0 | |
| Profit | $ - 0 | |
| Insurance Premium | $ - 0 | |
| Bond Premium | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bonds Premiums | $ - 0 | |
| TOTAL PROPOSED PROJECT PRICE | ||
| Subtotal of Level 3 Individual Element Costs | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bond Cost Elements | $ - 0 | |
| Indep. Option 2 - TOTAL PROPOSED PROJECT PRICE | $ - 0 |
6 - Option 3
| Instructions | Fill in every field, if you have no price in a section fill in $0 | |
| Indep. Option 3 - | Replace/upgrade VFD for TWGP-1 and TWGP-2 | |
| Level 1 | Level 2 | Individual Cost Element |
| Group Elements | Individual Elements | |
| A10 - Foundations | ||
| A1010 - Standard Foundations | $ - 0 | |
| A1020 - Special Foundations | $ - 0 | |
| A1030 – Slab on Grade | $ - 0 | |
| A20 - Basement Construction | ||
| A2010 - Basement Excavation | $ - 0 | |
| A2020 - Basement Walls | $ - 0 | |
| Subtotal | $ - 0 | |
| B10 - Superstructure | ||
| B1010 - Floor Construction | $ - 0 | |
| B1020 - Roof Construction | $ - 0 | |
| B20 - Exterior Closure | ||
| B2010 - Exterior Walls | $ - 0 | |
| B2020 - Exterior Windows/Doors | $ - 0 | |
| B30 - Roofing | ||
| B3010 - Roof Coverings | $ - 0 | |
| B3020 - Roof Openings | $ - 0 | |
| Subtotal | $ - 0 | |
| C10 - Interior Construction | ||
| C1010 - Partitions | $ - 0 | |
| C1020 - Interior Doors | $ - 0 | |
| C1030 - Specialties | $ - 0 | |
| C20 - Staircases | ||
| C2010 - Stair Construction | $ - 0 | |
| C2020 - Stair Finishes | $ - 0 | |
| C30 - Interior Finishes | ||
| C3010 - Wall Finishes | $ - 0 | |
| C3020 - Floor Finishes | $ - 0 | |
| C3030 - Ceiling Finishes | $ - 0 | |
| Subtotal | $ - 0 | |
| D10 - Conveying Systems | ||
| D1010 - Elevators | $ - 0 | |
| D1020 - Escalators & Moving Walks | $ - 0 | |
| D1030 - Material Handling Systems | $ - 0 | |
| D20 - Plumbing | ||
| D2010 - Plumbing Fixtures | $ - 0 | |
| D2020 - Domestic Water Distribution | $ - 0 | |
| D2030 - Sanitary Waste | $ - 0 | |
| D2040 - Rain Water Drainage | $ - 0 | |
| D2050 - Special Plumbing Systems | $ - 0 | |
| D30 - HVAC | ||
| D3010 - Energy Supply | $ - 0 | |
| D3020 - Heat Generating Systems | $ - 0 | |
| D3030 - Cooling Generating Systems | $ - 0 | |
| D3040 - Distribution Systems | $ - 0 | |
| D3050 - Terminal & Package Units | $ - 0 | |
| D3060 - Controls & Instrumentation | $ - 0 | |
| D3070 - Special HVAC Systems & Equm't | $ - 0 | |
| D3080 - Systems Testing & Balancing | $ - 0 | |
| D40 - Fire Protection | ||
| D4010 - Fire Protection Sprinkler Systems | $ - 0 | |
| D4020 - Stand-Pipe & Hose Systems | $ - 0 | |
| D4030 - Fire Protection Specialties | $ - 0 | |
| D4040 - Special Electrical Systems | $ - 0 | |
| D50 - Electrical | ||
| D5010 - Electrical Service & Distribution | $ - 0 | |
| D5020 - Lighting & Branch Wiring | $ - 0 | |
| D5030 - Communication & Security Sys | $ - 0 | |
| D5040 - Special Electrical Systems | $ - 0 | |
| Subtotal | $ - 0 | |
| E10 - Equipment | ||
| E1010 - Commercial Equipment | $ - 0 | |
| E1020 - Institutional Equipment | $ - 0 | |
| E1030 - Vehicular Equipment | $ - 0 | |
| E1040 - Other Equipment | $ - 0 | |
| E20 - Furnishings | ||
| E2010 - Fixed Furnishings | $ - 0 | |
| E2020 - Movable Furnishings | $ - 0 | |
| Subtotal | $ - 0 | |
| F10 - Special Construction | ||
| F1010 - Special Structures | $ - 0 | |
| F1020 - Integrated Construction | $ - 0 | |
| F1030 - Special Construction Systems | $ - 0 | |
| F1040 - Special Facilities | $ - 0 | |
| F1050 - Special Controls & Instrumentation | $ - 0 | |
| F20 - Selective Building Demolition | ||
| F2010 - Building Elements Demolition | $ - 0 | |
| F2020 - Hazardous Components Abatement | $ - 0 | |
| Subtotal | $ - 0 | |
| G10 - Site Preparation | ||
| G1010 - Site Clearing | $ - 0 | |
| G1020 - Site Demolition & Relocations | $ - 0 | |
| G1030 - Site Earthwork | $ - 0 | |
| G1040 - Hazardous Waste Remediation | $ - 0 | |
| G20 - Site Improvements | ||
| G2010 - Roadways | $ - 0 | |
| G2020 - Parking Lots | $ - 0 | |
| G2030 - Pedestrian Paving | $ - 0 | |
| G2040 - Site Development | $ - 0 | |
| G2050 - Landscaping | $ - 0 | |
| G30 - Site Civil/Mechanical Utilities | ||
| G3010 - Water Supply & Distribution Sys | $ - 0 | |
| G3020 - Sanitary Sewer Systems | $ - 0 | |
| G3030 - Storm Sewer Systems | $ - 0 | |
| G3040 - Heating Distribution | $ - 0 | |
| G3050 - Cooling Distribution | $ - 0 | |
| G3060 - Fuel Distribution | $ - 0 | |
| G3070 - Other Civil/Mechanical Utilities | $ - 0 | |
| G40 - Site Electrical Utilities | ||
| G4010 - Electrical Distribution | $ - 0 | |
| G4020 - Exterior Lighting | $ - 0 | |
| G4030 - Exterior Comm's & Security | $ - 0 | |
| G4040 - Other Electrical Utilities | $ - 0 | |
| G50 - Other Site Construction | ||
| G4010 - Service Tunnels | $ - 0 | |
| G4020 - Other Site Systems & Equipment | $ - 0 | |
| Subtotal | $ - 0 | |
| SUBTOTAL Level 3 Individual Element Costs | $ - 0 | |
| OVERHEAD, PROFIT, INSURANCE & BOND PREMIUMS | ||
| Overhead | $ - 0 | |
| Profit | $ - 0 | |
| Insurance Premium | $ - 0 | |
| Bond Premium | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bonds Premiums | $ - 0 | |
| TOTAL PROPOSED PROJECT PRICE | ||
| Subtotal of Level 3 Individual Element Costs | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bond Cost Elements | $ - 0 | |
| Indep. Option 3 - TOTAL PROPOSED PROJECT PRICE | $ - 0 |
7 - Option 4
| Instructions | Fill in every field, if you have no price in a section fill in $0 | |
| Indep. Option 4 - | Add first platform extension to accommodate six (6) total ACHE Fan Array Bays; add one (1) ACHE fan unit for a total of four (4) ACHE | |
| Level 1 | Level 2 | Individual Cost Element |
| Group Elements | Individual Elements | |
| A10 - Foundations | ||
| A1010 - Standard Foundations | $ - 0 | |
| A1020 - Special Foundations | $ - 0 | |
| A1030 – Slab on Grade | $ - 0 | |
| A20 - Basement Construction | ||
| A2010 - Basement Excavation | $ - 0 | |
| A2020 - Basement Walls | $ - 0 | |
| Subtotal | $ - 0 | |
| B10 - Superstructure | ||
| B1010 - Floor Construction | $ - 0 | |
| B1020 - Roof Construction | $ - 0 | |
| B20 - Exterior Closure | ||
| B2010 - Exterior Walls | $ - 0 | |
| B2020 - Exterior Windows/Doors | $ - 0 | |
| B30 - Roofing | ||
| B3010 - Roof Coverings | $ - 0 | |
| B3020 - Roof Openings | $ - 0 | |
| Subtotal | $ - 0 | |
| C10 - Interior Construction | ||
| C1010 - Partitions | $ - 0 | |
| C1020 - Interior Doors | $ - 0 | |
| C1030 - Specialties | $ - 0 | |
| C20 - Staircases | ||
| C2010 - Stair Construction | $ - 0 | |
| C2020 - Stair Finishes | $ - 0 | |
| C30 - Interior Finishes | ||
| C3010 - Wall Finishes | $ - 0 | |
| C3020 - Floor Finishes | $ - 0 | |
| C3030 - Ceiling Finishes | $ - 0 | |
| Subtotal | $ - 0 | |
| D10 - Conveying Systems | ||
| D1010 - Elevators | $ - 0 | |
| D1020 - Escalators & Moving Walks | $ - 0 | |
| D1030 - Material Handling Systems | $ - 0 | |
| D20 - Plumbing | ||
| D2010 - Plumbing Fixtures | $ - 0 | |
| D2020 - Domestic Water Distribution | $ - 0 | |
| D2030 - Sanitary Waste | $ - 0 | |
| D2040 - Rain Water Drainage | $ - 0 | |
| D2050 - Special Plumbing Systems | $ - 0 | |
| D30 - HVAC | ||
| D3010 - Energy Supply | $ - 0 | |
| D3020 - Heat Generating Systems | $ - 0 | |
| D3030 - Cooling Generating Systems | $ - 0 | |
| D3040 - Distribution Systems | $ - 0 | |
| D3050 - Terminal & Package Units | $ - 0 | |
| D3060 - Controls & Instrumentation | $ - 0 | |
| D3070 - Special HVAC Systems & Equm't | $ - 0 | |
| D3080 - Systems Testing & Balancing | $ - 0 | |
| D40 - Fire Protection | ||
| D4010 - Fire Protection Sprinkler Systems | $ - 0 | |
| D4020 - Stand-Pipe & Hose Systems | $ - 0 | |
| D4030 - Fire Protection Specialties | $ - 0 | |
| D4040 - Special Electrical Systems | $ - 0 | |
| D50 - Electrical | ||
| D5010 - Electrical Service & Distribution | $ - 0 | |
| D5020 - Lighting & Branch Wiring | $ - 0 | |
| D5030 - Communication & Security Sys | $ - 0 | |
| D5040 - Special Electrical Systems | $ - 0 | |
| Subtotal | $ - 0 | |
| E10 - Equipment | ||
| E1010 - Commercial Equipment | $ - 0 | |
| E1020 - Institutional Equipment | $ - 0 | |
| E1030 - Vehicular Equipment | $ - 0 | |
| E1040 - Other Equipment | $ - 0 | |
| E20 - Furnishings | ||
| E2010 - Fixed Furnishings | $ - 0 | |
| E2020 - Movable Furnishings | $ - 0 | |
| Subtotal | $ - 0 | |
| F10 - Special Construction | ||
| F1010 - Special Structures | $ - 0 | |
| F1020 - Integrated Construction | $ - 0 | |
| F1030 - Special Construction Systems | $ - 0 | |
| F1040 - Special Facilities | $ - 0 | |
| F1050 - Special Controls & Instrumentation | $ - 0 | |
| F20 - Selective Building Demolition | ||
| F2010 - Building Elements Demolition | $ - 0 | |
| F2020 - Hazardous Components Abatement | $ - 0 | |
| Subtotal | $ - 0 | |
| G10 - Site Preparation | ||
| G1010 - Site Clearing | $ - 0 | |
| G1020 - Site Demolition & Relocations | $ - 0 | |
| G1030 - Site Earthwork | $ - 0 | |
| G1040 - Hazardous Waste Remediation | $ - 0 | |
| G20 - Site Improvements | ||
| G2010 - Roadways | $ - 0 | |
| G2020 - Parking Lots | $ - 0 | |
| G2030 - Pedestrian Paving | $ - 0 | |
| G2040 - Site Development | $ - 0 | |
| G2050 - Landscaping | $ - 0 | |
| G30 - Site Civil/Mechanical Utilities | ||
| G3010 - Water Supply & Distribution Sys | $ - 0 | |
| G3020 - Sanitary Sewer Systems | $ - 0 | |
| G3030 - Storm Sewer Systems | $ - 0 | |
| G3040 - Heating Distribution | $ - 0 | |
| G3050 - Cooling Distribution | $ - 0 | |
| G3060 - Fuel Distribution | $ - 0 | |
| G3070 - Other Civil/Mechanical Utilities | $ - 0 | |
| G40 - Site Electrical Utilities | ||
| G4010 - Electrical Distribution | $ - 0 | |
| G4020 - Exterior Lighting | $ - 0 | |
| G4030 - Exterior Comm's & Security | $ - 0 | |
| G4040 - Other Electrical Utilities | $ - 0 | |
| G50 - Other Site Construction | ||
| G4010 - Service Tunnels | $ - 0 | |
| G4020 - Other Site Systems & Equipment | $ - 0 | |
| Subtotal | $ - 0 | |
| SUBTOTAL Level 3 Individual Element Costs | $ - 0 | |
| OVERHEAD, PROFIT, INSURANCE & BOND PREMIUMS | ||
| Overhead | $ - 0 | |
| Profit | $ - 0 | |
| Insurance Premium | $ - 0 | |
| Bond Premium | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bonds Premiums | $ - 0 | |
| TOTAL PROPOSED PROJECT PRICE | ||
| Subtotal of Level 3 Individual Element Costs | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bond Cost Elements | $ - 0 | |
| Indep. Option 4 - TOTAL PROPOSED PROJECT PRICE | $ - 0 |
8 - Option 5
| Instructions | Fill in every field, if you have no price in a section fill in $0 | |
| Indep. Option 5 - | Add second platform extension to accommodate nine (9) total ACHE Fan Array Bays; add two (2) ACHE fan unit for a total of six (6) ACHE | |
| Level 1 | Level 2 | Individual Cost Element |
| Group Elements | Individual Elements | |
| A10 - Foundations | ||
| A1010 - Standard Foundations | $ - 0 | |
| A1020 - Special Foundations | $ - 0 | |
| A1030 – Slab on Grade | $ - 0 | |
| A20 - Basement Construction | ||
| A2010 - Basement Excavation | $ - 0 | |
| A2020 - Basement Walls | $ - 0 | |
| Subtotal | $ - 0 | |
| B10 - Superstructure | ||
| B1010 - Floor Construction | $ - 0 | |
| B1020 - Roof Construction | $ - 0 | |
| B20 - Exterior Closure | ||
| B2010 - Exterior Walls | $ - 0 | |
| B2020 - Exterior Windows/Doors | $ - 0 | |
| B30 - Roofing | ||
| B3010 - Roof Coverings | $ - 0 | |
| B3020 - Roof Openings | $ - 0 | |
| Subtotal | $ - 0 | |
| C10 - Interior Construction | ||
| C1010 - Partitions | $ - 0 | |
| C1020 - Interior Doors | $ - 0 | |
| C1030 - Specialties | $ - 0 | |
| C20 - Staircases | ||
| C2010 - Stair Construction | $ - 0 | |
| C2020 - Stair Finishes | $ - 0 | |
| C30 - Interior Finishes | ||
| C3010 - Wall Finishes | $ - 0 | |
| C3020 - Floor Finishes | $ - 0 | |
| C3030 - Ceiling Finishes | $ - 0 | |
| Subtotal | $ - 0 | |
| D10 - Conveying Systems | ||
| D1010 - Elevators | $ - 0 | |
| D1020 - Escalators & Moving Walks | $ - 0 | |
| D1030 - Material Handling Systems | $ - 0 | |
| D20 - Plumbing | ||
| D2010 - Plumbing Fixtures | $ - 0 | |
| D2020 - Domestic Water Distribution | $ - 0 | |
| D2030 - Sanitary Waste | $ - 0 | |
| D2040 - Rain Water Drainage | $ - 0 | |
| D2050 - Special Plumbing Systems | $ - 0 | |
| D30 - HVAC | ||
| D3010 - Energy Supply | $ - 0 | |
| D3020 - Heat Generating Systems | $ - 0 | |
| D3030 - Cooling Generating Systems | $ - 0 | |
| D3040 - Distribution Systems | $ - 0 | |
| D3050 - Terminal & Package Units | $ - 0 | |
| D3060 - Controls & Instrumentation | $ - 0 | |
| D3070 - Special HVAC Systems & Equm't | $ - 0 | |
| D3080 - Systems Testing & Balancing | $ - 0 | |
| D40 - Fire Protection | ||
| D4010 - Fire Protection Sprinkler Systems | $ - 0 | |
| D4020 - Stand-Pipe & Hose Systems | $ - 0 | |
| D4030 - Fire Protection Specialties | $ - 0 | |
| D4040 - Special Electrical Systems | $ - 0 | |
| D50 - Electrical | ||
| D5010 - Electrical Service & Distribution | $ - 0 | |
| D5020 - Lighting & Branch Wiring | $ - 0 | |
| D5030 - Communication & Security Sys | $ - 0 | |
| D5040 - Special Electrical Systems | $ - 0 | |
| Subtotal | $ - 0 | |
| E10 - Equipment | ||
| E1010 - Commercial Equipment | $ - 0 | |
| E1020 - Institutional Equipment | $ - 0 | |
| E1030 - Vehicular Equipment | $ - 0 | |
| E1040 - Other Equipment | $ - 0 | |
| E20 - Furnishings | ||
| E2010 - Fixed Furnishings | $ - 0 | |
| E2020 - Movable Furnishings | $ - 0 | |
| Subtotal | $ - 0 | |
| F10 - Special Construction | ||
| F1010 - Special Structures | $ - 0 | |
| F1020 - Integrated Construction | $ - 0 | |
| F1030 - Special Construction Systems | $ - 0 | |
| F1040 - Special Facilities | $ - 0 | |
| F1050 - Special Controls & Instrumentation | $ - 0 | |
| F20 - Selective Building Demolition | ||
| F2010 - Building Elements Demolition | $ - 0 | |
| F2020 - Hazardous Components Abatement | $ - 0 | |
| Subtotal | $ - 0 | |
| G10 - Site Preparation | ||
| G1010 - Site Clearing | $ - 0 | |
| G1020 - Site Demolition & Relocations | $ - 0 | |
| G1030 - Site Earthwork | $ - 0 | |
| G1040 - Hazardous Waste Remediation | $ - 0 | |
| G20 - Site Improvements | ||
| G2010 - Roadways | $ - 0 | |
| G2020 - Parking Lots | $ - 0 | |
| G2030 - Pedestrian Paving | $ - 0 | |
| G2040 - Site Development | $ - 0 | |
| G2050 - Landscaping | $ - 0 | |
| G30 - Site Civil/Mechanical Utilities | ||
| G3010 - Water Supply & Distribution Sys | $ - 0 | |
| G3020 - Sanitary Sewer Systems | $ - 0 | |
| G3030 - Storm Sewer Systems | $ - 0 | |
| G3040 - Heating Distribution | $ - 0 | |
| G3050 - Cooling Distribution | $ - 0 | |
| G3060 - Fuel Distribution | $ - 0 | |
| G3070 - Other Civil/Mechanical Utilities | $ - 0 | |
| G40 - Site Electrical Utilities | ||
| G4010 - Electrical Distribution | $ - 0 | |
| G4020 - Exterior Lighting | $ - 0 | |
| G4030 - Exterior Comm's & Security | $ - 0 | |
| G4040 - Other Electrical Utilities | $ - 0 | |
| G50 - Other Site Construction | ||
| G4010 - Service Tunnels | $ - 0 | |
| G4020 - Other Site Systems & Equipment | $ - 0 | |
| Subtotal | $ - 0 | |
| SUBTOTAL Level 3 Individual Element Costs | $ - 0 | |
| OVERHEAD, PROFIT, INSURANCE & BOND PREMIUMS | ||
| Overhead | $ - 0 | |
| Profit | $ - 0 | |
| Insurance Premium | $ - 0 | |
| Bond Premium | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bonds Premiums | $ - 0 | |
| TOTAL PROPOSED PROJECT PRICE | ||
| Subtotal of Level 3 Individual Element Costs | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bond Cost Elements | $ - 0 | |
| Indep. Option 5 - TOTAL PROPOSED PROJECT PRICE | $ - 0 |
9 - Option 6
| Instructions | Fill in every field, if you have no price in a section fill in $0 | |
| Indep. Option 6 - | Add electrical switch station A8, duct bank, feeds to substations in North Electrical Room | |
| Level 1 | Level 2 | Individual Cost Element |
| Group Elements | Individual Elements | |
| A10 - Foundations | ||
| A1010 - Standard Foundations | $ - 0 | |
| A1020 - Special Foundations | $ - 0 | |
| A1030 – Slab on Grade | $ - 0 | |
| A20 - Basement Construction | ||
| A2010 - Basement Excavation | $ - 0 | |
| A2020 - Basement Walls | $ - 0 | |
| Subtotal | $ - 0 | |
| B10 - Superstructure | ||
| B1010 - Floor Construction | $ - 0 | |
| B1020 - Roof Construction | $ - 0 | |
| B20 - Exterior Closure | ||
| B2010 - Exterior Walls | $ - 0 | |
| B2020 - Exterior Windows/Doors | $ - 0 | |
| B30 - Roofing | ||
| B3010 - Roof Coverings | $ - 0 | |
| B3020 - Roof Openings | $ - 0 | |
| Subtotal | $ - 0 | |
| C10 - Interior Construction | ||
| C1010 - Partitions | $ - 0 | |
| C1020 - Interior Doors | $ - 0 | |
| C1030 - Specialties | $ - 0 | |
| C20 - Staircases | ||
| C2010 - Stair Construction | $ - 0 | |
| C2020 - Stair Finishes | $ - 0 | |
| C30 - Interior Finishes | ||
| C3010 - Wall Finishes | $ - 0 | |
| C3020 - Floor Finishes | $ - 0 | |
| C3030 - Ceiling Finishes | $ - 0 | |
| Subtotal | $ - 0 | |
| D10 - Conveying Systems | ||
| D1010 - Elevators | $ - 0 | |
| D1020 - Escalators & Moving Walks | $ - 0 | |
| D1030 - Material Handling Systems | $ - 0 | |
| D20 - Plumbing | ||
| D2010 - Plumbing Fixtures | $ - 0 | |
| D2020 - Domestic Water Distribution | $ - 0 | |
| D2030 - Sanitary Waste | $ - 0 | |
| D2040 - Rain Water Drainage | $ - 0 | |
| D2050 - Special Plumbing Systems | $ - 0 | |
| D30 - HVAC | ||
| D3010 - Energy Supply | $ - 0 | |
| D3020 - Heat Generating Systems | $ - 0 | |
| D3030 - Cooling Generating Systems | $ - 0 | |
| D3040 - Distribution Systems | $ - 0 | |
| D3050 - Terminal & Package Units | $ - 0 | |
| D3060 - Controls & Instrumentation | $ - 0 | |
| D3070 - Special HVAC Systems & Equm't | $ - 0 | |
| D3080 - Systems Testing & Balancing | $ - 0 | |
| D40 - Fire Protection | ||
| D4010 - Fire Protection Sprinkler Systems | $ - 0 | |
| D4020 - Stand-Pipe & Hose Systems | $ - 0 | |
| D4030 - Fire Protection Specialties | $ - 0 | |
| D4040 - Special Electrical Systems | $ - 0 | |
| D50 - Electrical | ||
| D5010 - Electrical Service & Distribution | $ - 0 | |
| D5020 - Lighting & Branch Wiring | $ - 0 | |
| D5030 - Communication & Security Sys | $ - 0 | |
| D5040 - Special Electrical Systems | $ - 0 | |
| Subtotal | $ - 0 | |
| E10 - Equipment | ||
| E1010 - Commercial Equipment | $ - 0 | |
| E1020 - Institutional Equipment | $ - 0 | |
| E1030 - Vehicular Equipment | $ - 0 | |
| E1040 - Other Equipment | $ - 0 | |
| E20 - Furnishings | ||
| E2010 - Fixed Furnishings | $ - 0 | |
| E2020 - Movable Furnishings | $ - 0 | |
| Subtotal | $ - 0 | |
| F10 - Special Construction | ||
| F1010 - Special Structures | $ - 0 | |
| F1020 - Integrated Construction | $ - 0 | |
| F1030 - Special Construction Systems | $ - 0 | |
| F1040 - Special Facilities | $ - 0 | |
| F1050 - Special Controls & Instrumentation | $ - 0 | |
| F20 - Selective Building Demolition | ||
| F2010 - Building Elements Demolition | $ - 0 | |
| F2020 - Hazardous Components Abatement | $ - 0 | |
| Subtotal | $ - 0 | |
| G10 - Site Preparation | ||
| G1010 - Site Clearing | $ - 0 | |
| G1020 - Site Demolition & Relocations | $ - 0 | |
| G1030 - Site Earthwork | $ - 0 | |
| G1040 - Hazardous Waste Remediation | $ - 0 | |
| G20 - Site Improvements | ||
| G2010 - Roadways | $ - 0 | |
| G2020 - Parking Lots | $ - 0 | |
| G2030 - Pedestrian Paving | $ - 0 | |
| G2040 - Site Development | $ - 0 | |
| G2050 - Landscaping | $ - 0 | |
| G30 - Site Civil/Mechanical Utilities | ||
| G3010 - Water Supply & Distribution Sys | $ - 0 | |
| G3020 - Sanitary Sewer Systems | $ - 0 | |
| G3030 - Storm Sewer Systems | $ - 0 | |
| G3040 - Heating Distribution | $ - 0 | |
| G3050 - Cooling Distribution | $ - 0 | |
| G3060 - Fuel Distribution | $ - 0 | |
| G3070 - Other Civil/Mechanical Utilities | $ - 0 | |
| G40 - Site Electrical Utilities | ||
| G4010 - Electrical Distribution | $ - 0 | |
| G4020 - Exterior Lighting | $ - 0 | |
| G4030 - Exterior Comm's & Security | $ - 0 | |
| G4040 - Other Electrical Utilities | $ - 0 | |
| G50 - Other Site Construction | ||
| G4010 - Service Tunnels | $ - 0 | |
| G4020 - Other Site Systems & Equipment | $ - 0 | |
| Subtotal | $ - 0 | |
| SUBTOTAL Level 3 Individual Element Costs | $ - 0 | |
| OVERHEAD, PROFIT, INSURANCE & BOND PREMIUMS | ||
| Overhead | $ - 0 | |
| Profit | $ - 0 | |
| Insurance Premium | $ - 0 | |
| Bond Premium | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bonds Premiums | $ - 0 | |
| TOTAL PROPOSED PROJECT PRICE | ||
| Subtotal of Level 3 Individual Element Costs | $ - 0 | |
| Subtotal of Overhead, Profit, Insurance & Bond Cost Elements | $ - 0 | |
| Indep. Option 6 - TOTAL PROPOSED PROJECT PRICE | $ - 0 |