NAVMWR-25-R-0008-0004.pdf

PDF 884 KB Posted

Attached to
NAS Corpus Christi Splash Pad
Solicitation number
NAVMWR-25-R-0008
Issued by

About this file

This document is an Amendment (0004) to Solicitation NAVMWR-25-R-0008 for the NAS Corpus Christi Splash Pad project. The amendment provides clarifications and changes to the original solicitation, including key details about the project requirements and submission process. Significant clarifications include: the two wooden pavilions in the main pool area are to be removed, the dividing fence will only separate the main pool and splash pad, and the proposal due date is extended to 30 April 2025.

The amendment addresses multiple contractor questions, providing specifics on project requirements such as key personnel experience levels (10 years for Chief of Contractor Quality Control, 5 years for On-site Superintendent), confirmation that the Site Safety Health Officer cannot be the same person as the CQC Chief, and removal of previous Dun & Bradstreet reporting requirements. Additionally, the government confirmed this is a Full and Open Competition, allowed RFIs to be submitted up to 7 days prior to the proposal due date, and agreed to accept electronic test files before the final proposal submission.

View the file

Other files

File Type Posted
NAVMWR-25-R-0008-0006.pdf PDF
NAVMWR-25-R-0008 Amendment 0005.pdf PDF
NAVMWR-25-R-0008-0003.pdf PDF
NAVMWR-25-R-0008-0002 Corpus Christi Splash Pad.pdf PDF
NAVMWR-25-R-0008-0001.pdf PDF
NAVMWR-25-R-0008.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

7. ADMINISTERED BY (If other than Item 6) CODE

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

FACILITY CODE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED (SEE ITEM 13)

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15C. DATE SIGNED

15A. NAME AND TITLE OF SIGNER (Type or print)

16C. DATE SIGNED

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

PAGE OF PAGES

6. ISSUED BY CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)

CODE

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

Previous edition unusable

1 4

0004 15 Apr 2025 R21-22 R21-22 N944

CNIC Facilities and Construction Contracting Alanna Young, Contracting Officer 5720 Integrity Drive, Lassen Building 457 Millington, TN 38055 901-574-0848 / alanna.g.young.naf@us.navy.mil

Nika Maldonado, Contract Specialist 901-930-7728 nika.n.maldonado.naf@us.navy.mil

NAVMWR-25-R-0008

18 February 2025

Corpus Christi Splash Pad NAS Corpus Christi, TX

Continued on page 2.

Alanna Young, Contracting Officer

Block 14 Continued:

A. Changes:

1. Delete Section L-19-4.D. in its entirety.

B. Clarifications:

Q-23. There are two wooden pavilions in the main pool area but near the kiddie pool.

Are these to remain in the main pool area or be removed?

A-23. The two (2) wooden pavilions are to be removed.

Q-24. Is it intended that the dividing fence separates the main pool and splash pad only or is it supposed to surround the splash pad?

A-24. The dividing fence will only separate the main pool and the splash pad.

Q-25. Is there a height requirement for the fence?

A-25. Per IBC, UFC-FC

Q-26. When demoing the kiddie pool are we to include removal of associated pump and filtration equipment?

A-26. No, depending on the design but the filtration system is the same as the pool.

Q-27. Are dry or wet chemicals currently being used for the pool? We would assume it is preferable for chemicals needed for the splash pad are the same.

A-27. The filtration system is the same as the pool.

Q-28. Assuming access for equipment will be through the back gate which will damage the grass from the entry point at the parking lot to the gate. Will we be responsible for returning the grass area outside the gate to existing condition?

A-28. Yes, the contractor is responsible for the repair and restoration of any area to its pre-use condition.

Q-29. Will the main power needed for new pump house be brought to the building or is that our responsibility?

A-29. That is the responsibility of the design/build contractor.

Q-30. Can the Government confirm the only permitting necessary would be with the base and NOT the City of Corpus Christi?

A-30. No known permitting is necessary by City of Corpus Christi for this project.

Q-31. During the Pre-Proposal Conference it was mentioned that we could submit our electronic proposals on the due date with hard copy to follow. Is this still acceptable for the hard copy to be received by NAFI May 1 via Commercial Courier (UPS/FedEx?)

NAVMWR-25-R-0008 Corpus Christi Splash Pad NAS Corpus Christi, TX

Amendment 0004 Page 2 of 4

A-31. No, incorrect. Reference Amendment 0002, A. Changes 1. Proposals are now due 30 April 25.

Q-32. Reference Question & Answer #14 from amendment 0002 Regarding Page Count

Exclusions and Answer No Page Count for this solicitation. There is a discrepancy with Section

L -19, Paragraph A wherein the sentence states “Volume I shall not exceed 100 pages”…. Please confirm there is no longer a page count.

A-32. There is no discrepancy, the KO has changed the page count by way of

Amendment 0002.

Q-33. The Pre-Proposal Conference Minutes 2. Request for quote (RFP) Acquisition

Process Overview, A. Request for Proposal See SF 18. There is no SF18 but an SF33. Please confirm. SF 18 is also referenced in Section J. Instructions, Conditions, and Notices to Offerors and Respondents. We only have SF33 and SF30 (Amendment).

A-33. Reference Amendment 0002, Pre-Proposal Conference Minutes, Section

2.J.2. Remove SF 18 and replace with SF 33

Q-34. From the Pre-Proposal Conference Minutes, section 2, H, 6) Key Personnel (H-

28) the Published experience levels minimum mandatory lists 5 years minimum, yet the RFP, Section H-26 identifies the Chief of Contractor Quality Control must have at least 10 years of experience as a General Construction Superintendent on similar type projects or be a licensed professional engineer or architect. Please clarify if the minimum required years of experience is

5 or 10.

A-34. Minimum required years of experience for this project is 10 years.

Q-35. From the Pre-Proposal Conference Minutes, section 2, H, 6) Key Personnel (H-

28) the Published experience levels minimum mandatory lists 5 years minimum, yet the RFP, Section H-28, Paragraph B, 5. On-site Superintendent states “Superintendent should have a minimum of 10 years of Similar project experience.” Please confirm if 5 years of experience on similar type projects is acceptable or if the government requires 10.

A-35. Minimum required years of experience for this project is 5 years.

Q-36. Can the CQC Chief also serve as the Site Safety Health Officer (SSHO)? This position was not listed in the Pre-Proposal Conference Minutes as a Key Position, but is found in

Paragraph H-28 and Section L, Paragraph A.

A-36. CQC Chief and Site Safety Health Officer (SSHO) SHALL NOT dual be dual hatted, serve in the same role for this project.

Q-37. Since the Proposal has been extended to April 30, can we assume any RFIs can be submitted up to 7 days prior (April 23), in lieu of the stated April 15, 2025?

A-37. That is correct.

Q-38. I have never used this method of uploading a proposal and would like to send a trial email. Would the government be amenable to receiving an electronic test file?

A-38. The NAFI agrees to a test email before submitting electronically. All test emails shall be sent on 22 April 2025 with the KO and KS copied.

NAVMWR-25-R-0008 Corpus Christi Splash Pad

Amendment 0004 Page 3 of 4

Q-39. In reference to Section L-19-4, D. A Dun & Bradstreet Comprehensive report on the prime contractor dated within 30 days of the RFP Closing Date – Please note that Dun and

Bradstreet no longer offers a Comprehensive Report, as such, would the government please remove this requirement from the RFP?

A-39. Reference above changes.

Q-40. Sam.Gov has removed the use of Dun & Bradstreet from its registration requirements and reporting and contractors now are issued a Unique Identifier. The majority of

Federal Government contracting no longer requires Dun & Bradstreet reporting, but for us to provide the SAM Unique Identifier that enables contracting to access and review contractor records. Would the Government please remove the Dun & Bradstreet requirement from the

RFP?

A-40. Reference A-39.

Q-41. From the Pre-Proposal Conference Minutes, Section 1. Introductions, D.

Administrative bullet 4) – “This project is NOT advertised in beta.sam.gov.” We received this solicitation directly from the government, yet it is on Sam.Gov. Was this published through a select bidders list or is this Full and Open Competition?

A-41. Reference Amendment 0002, Pre-Proposal Conference Minutes Section

1.D.4), Remove “NOT”. RFP Solicitation is Full and Open Competition.

NAVMWR-25-R-0008 Corpus Christi Splash Pad

Amendment 0004 Page 4 of 4