This is Addendum No. 3 to the contract documents for the Massachusetts Department of Transportation (MassDOT) regarding the Boden Lane Bridge Replacement project in Natick (Federal Aid Project No. HIP(NGB)-003S(965)X, N-03-012). The addendum addresses questions and responses from Commonwealth Scaffold regarding temporary shielding requirements for the bridge replacement work over CSX/MBTA railroad infrastructure. The proposal opening date is Tuesday, October 27, 2026, at 2:00 p.m. Bidders must acknowledge Addendum No. 3 in their Expedite Proposal file prior to bid submission. The addendum clarifies that shield extent and design loads shall comply with MBTA requirements and project Special Provisions to protect the railroad from debris during construction, with support locations to be determined by the Contractor on the Shielding System plan. The shielding design must maintain existing vertical clearance under the bridge and required horizontal clearance as determined by the MBTA for abutment demolition and construction activities.

The addendum specifies that shielding installation work windows, flagging requirements, foundation restrictions, and reset phases are subject to MBTA approval through a Railroad Access Agreement to be obtained by the Contractor. Shielding design shall be prepared by the Contractor and submitted to MassDOT for review and approval by the MBTA, Keolis, the Engineer, and MassDOT. The overall project is valued at $12.898 million and is a federally-assisted project subject to prevailing wage rates, Title VI Civil Rights Act compliance, and Executive Order 11246 minority and female participation goals. A Proposal Guaranty equal to 5% of the bid value is required. The contract includes price adjustment provisions for hot mix asphalt, Portland cement, diesel fuel, gasoline, and structural steel.

View the file

Other files

File Type Posted
A00844-607420.pdf PDF
A00811-607420.pdf PDF
A00825-607420.pdf PDF
607420 - Bid Tabulations.pdf PDF
A00814-607420.pdf PDF
607420 Bid Items List.txt TXT text file
A00812-607420.pdf PDF
NATICK-607420-136650-A-1.pdf PDF
A00875-607420.pdf PDF
607420 - Plan Holders List 10-26-2026.pdf PDF
A00810-607420.pdf PDF
A00813-607420.pdf PDF
A00802-607420.pdf PDF
607420 - Notice to Contractors.pdf PDF
A00801-607420.pdf PDF
Link to Bid Opening 10-27-2026~1.pdf PDF
A00807-607420.pdf PDF
BIDS OPENED - Tuesday - October 27-2026~3.pdf PDF
A00820-607420.pdf PDF
A00815-607420.pdf PDF
607420 - Plan Holders List 10-13-2026.pdf PDF
NATICK-607420-136650-A-2.pdf PDF
A00808-607420.pdf PDF
Show all 23

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ten Park Plaza, Suite 4160, Boston, MA 02116 Tel: 857-368-4636, TTY: 857-368-0655 mass.gov/massdot

October 26, 2026 607420-136650

ADDENDUM NO. 3

To Prospective Bidders and Others on:

NATICK

Federal Aid Project No. HIP(NGB)-003S(965)X

Bridge Replacement, N-03-012, Boden Lane over CSX/MBTA

THIS PROPOSAL TO BE OPENED AND READ: TUESDAY, OCTOBER 27, 2026, at 2:00 P.M.

Transmitting revisions to the Contract Documents as follows:

QUESTIONS AND RESPONSES: 1 page.

Please take note of the above and acknowledge Addendum No. 3 in your Expedite Proposal file before submitting your bid.

Very truly yours, Eric M. Cardone, P.E.

Construction Contracts Engineer

JPB

cc: Christoper Cameron, Project Manager

For

THIS PAGE INTENTIONALLY LEFT BLANK

NATICK

Federal Aid Project No. HIP(NGB)-003S(965)X

Bridge Replacement, N-03-012, Boden Lane over CSX/MBTA (607420-136650)

Questions and Responses Addendum No. 3, October 26, 2026

Commonwealth Scaffold e-mail dated October 26, 2026.

Question 4.) For Item 994.01, what shield extent, design loads, support locations and rail-clearance envelope govern the temporary shielding?

Response 4.) Shield extent and design loads shall be in accordance with the MBTA requirements and the project Special Provisions as necessary to protect the railroad from debris throughout construction. Support locations shall be determined and specified by the Contractor on the Shielding System plan. The shielding will be designed to not reduce the existing vertical clearance under the bridge and maintain the required horizontal clearance as determined by the MBTA for abutment demolition and abutment construction.

Question 5.) What railroad work windows/flagging, foundation restrictions and reset phases apply, and who coordinates shielding design and construction?

Response 5.) Shielding installation work windows, flagging requirements, foundation restrictions and reset phases shall be subject to approval by the MBTA in the Railroad Access Agreement to be obtained by the Contractor. Shielding design shall be prepared by the Contractor and submitted to MassDOT for review and approval by the MBTA, Keolis, the Engineer and MassDOT.

NATICK-607420-136650-A-3
ADDENDUM NO. 3

Questions and Responses 607420 Add #3

2026-10-26T12:36:16-0400
Haval Abdulrahman