B1428 Entire Building Renovation Design RFP v2.pdf
PDF 4 MB Posted
- Solicitation number
- N69450-20-R-0006
About this file
This solicitation is for an indefinite delivery indefinite quantity (IDIQ) multiple award construction contract set aside for 8(a) firms. Work will primarily be performed at Naval Air Station Fort Worth Joint Reserve Base, Texas and other areas managed by NAVFAC Southeast as needed and approved. The North American Industry Classification System code is 236220 for commercial and institutional building construction, with a small business size standard of $39.5 million. Construction services will be for Department of Defense activities in the Fort Worth, Texas area managed by NAVFAC Southeast on a firm fixed price basis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6945020R0006 0004.pdf | ||
| N6945020R0006 0003.pdf | ||
| N6945020R0006 0002.pdf | ||
| B1428 Drawings v3.pdf | ||
| N6945020R0006 0001.pdf | ||
| N6945020R0006 v2.pdf | ||
| Exhibit F SECNAV 5512 Base Access v2.pdf | ||
| Exhibit D ProjNet How To Guide v2.pdf | ||
| Exhibit A Construction and Design Experience Project Data Sheet v2.docx | DOCX document | |
| Exhibit C Past Performance Questionnaire v2.docx | DOCX document | |
| Exhibit G NAS FT Worth JRB Digital Access Request Form v2.pdf | ||
| Exhibit E AMAG Form v2.xls | XLS spreadsheet | |
| B1428 Drawings v2.pdf | ||
| Exhibit B Safety Data Sheet v2.docx | DOCX document | |
| DD1155 v2.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVFAC WORK ORDER NO. 1610572
A/E CONTRACT NO. ______NA________
APPROPRIATION: ______NA________
B1428 Entire Building Renovation At
NAS JRB FT WORTH, TX
FORT WORTH, TEXAS
SUBMITTED BY:
NAVFAC Southeast, Capital Improvements P.O. Box 30, Building 903
NAS Jacksonville, FL 32212
Project Manager:
Architectural:
Fire Protection:
Structural:
Mechanical:
Electrical:
Civil:
Cost:
PREPARED BY:
Michael Lash, P.E.
Jeremy DeRyk, R.A.
Joseph Higgins, P.E.
Gill Samson, P.E.
Boyd Hansen,P.E.
Doug Henry, P.E.
P.E.Ronnie Perron
Anthony Willson
NAVFAC SE, CI
NAVFAC SE, CI
NAVFAC SE, CI
NAVFAC SE, CI
NAVFAC SE, CI
NAVFAC SE, CI
NAVFAC SE, CI
NAVFAC SE, CI
Design Manager (DM): Jeremy DeRyk Date: June 18th, 2019
1428 Entire Building Renovation WON: 1610572 NAS Fort Worth JRB
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00.00 25 SUMMARY OF WORK
01 14 00.00 25 WORK RESTRICTIONS
01 20 00.00 25 PRICE AND PAYMENT PROCEDURES
01 30 00.00 25 ADMINISTRATIVE REQUIREMENTS
01 32 16.00 25 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 26.00 25 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.10 25 QUALITY CONTROL FOR MAINTENANCE, REPAIR OR SMALL/MINOR
CONSTRUCTION PROJECTS
01 45 35.00 25 SPECIAL INSPECTIONS
01 50 00.00 25 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS
01 57 19.00 25 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 19.01 25 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00.00 25 PROJECT IDENTIFICATION
01 74 19.00 25 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 75 00.00 25 STARTING AND ADJUSTING
01 78 00.00 25 CLOSEOUT SUBMITTALS
01 78 23.00 25 OPERATION AND MAINTENANCE DATA
01 78 24.00 25 FACILITY ELECTRONIC OPERATION AND MAINTENANCE SUPPORT
INFORMATION (eOMSI)
01 91 13.00 25 GENERAL COMMISSIONING REQUIREMENTS FOR CONSTRUCTION
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
02 82 33.13 20 REMOVAL/CONTROL AND DISPOSAL OF PAINT WITH LEAD
DIVISION 03 - CONCRETE
03 30 00 CAST-IN-PLACE CONCRETE
DIVISION 05 - METALS
05 40 00 COLD-FORMED METAL FRAMING
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 ROUGH CARPENTRY
06 20 00 FINISH CARPENTRY
06 41 16.00 10 PLASTIC-LAMINATE-CLAD ARCHITECTURAL CABINETS
06 61 16 SOLID SURFACING FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 24 00 EXTERIOR INSULATION AND FINISH SYSTEMS
07 31 13 ASPHALT SHINGLES
07 52 00 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 FLASHING AND SHEET METAL
07 72 20 GRAVITY-TYPE ROOF VENTILATORS
07 84 00 FIRESTOPPING
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
PROJECT TABLE OF CONTENTS Page 1
08 11 13 STEEL DOORS AND FRAMES
08 14 00 WOOD DOORS
08 44 00 CURTAIN WALL AND GLAZED ASSEMBLIES
08 71 00 DOOR HARDWARE
08 81 00 GLAZING
08 91 00 METAL WALL AND DOOR LOUVERS
DIVISION 09 - FINISHES
09 22 00 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 GYPSUM BOARD
09 30 10 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 ACOUSTICAL CEILINGS
09 65 00 RESILIENT FLOORING
09 68 00 CARPETING
09 90 00 PAINTS AND COATINGS
DIVISION 10 - SPECIALTIES
10 14 00.10 EXTERIOR SIGNAGE
10 14 00.20 INTERIOR SIGNAGE
10 26 00 WALL AND DOOR PROTECTION
10 28 13 TOILET ACCESSORIES
10 44 16 FIRE EXTINGUISHERS
10 51 13 METAL LOCKERS
DIVISION 12 - FURNISHINGS
12 21 00 WINDOW BLINDS
12 48 13 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 22 - PLUMBING
22 00 00 PLUMBING, GENERAL PURPOSE
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 00 00 AIR SUPPLY, DISTRIBUTION, VENTILATION, AND EXHAUST SYSTEMS
23 03 00.00 20 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC
23 07 00 THERMAL INSULATION FOR MECHANICAL SYSTEMS
23 09 53.00 20 SPACE TEMPERATURE CONTROL SYSTEMS
23 11 25 FACILITY GAS PIPING
23 81 00.00 20 UNITARY AIR CONDITIONING EQUIPMENT
DIVISION 26 - ELECTRICAL
26 00 00.00 20 BASIC ELECTRICAL MATERIALS AND METHODS
26 08 00 APPARATUS INSPECTION AND TESTING
26 12 19.10 THREE-PHASE PAD-MOUNTED TRANSFORMERS
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 41 00 LIGHTNING PROTECTION SYSTEM
26 51 00 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 10 00 BUILDING TELECOMMUNICATIONS CABLING SYSTEM
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
PROJECT TABLE OF CONTENTS Page 2
28 31 76 INTERIOR FIRE ALARM AND MASS NOTIFICATION SYSTEM
DIVISION 31 - EARTHWORK
31 23 00.00 20 EXCAVATION AND FILL
31 31 16.13 CHEMICAL TERMITE CONTROL
DIVISION 33 - UTILITIES
33 30 00 SANITARY SEWERAGE
33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 3
SECTION 01 11 00.00 25
SUMMARY OF WORK
01/17
NAVFAC SE VERSION
NAS FT. WORTH 02/2017 REVISIONS
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
The work includes construction of a new free standing, one story EOD (Explosive Ordinance Disposal) Administration Facility with related site improvements and incidental related work. The administration wing of the facility consists of a single-story structure with masonry walls and standing seam metal roof. The storage and vehicle bay wing of the facility will is a pre-engineered metal building.
1.1.2 Location
The work is located at the NAS Ft. Worth - JRB, approximately indicated on the contract drawings.
1.2 EXISTING WORK
In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.3 LOCATION OF UNDERGROUND UTILITIES
Submit a utility locate and digging request to the Contracting Officer's Representative (COR) 28 calendar days prior to start of an excavation.
Upon receipt of the utlity locate and digging permit, scan the excavation site with Ground Penetrating Radar (GPR), electromagnetic, as well as sonic equipment, and mark the surface of the ground or paved surface where any unmarked underground obstruction is discovered.
Notify the COR if any underground obstruction not indicated on the digging permit is discovered during scanning, and do not proceed with excavation with without further direction from the COR.
1.3.1 Notification Prior to Excavation
Notify the Contracting Officer at least two working days prior to starting excavation work.
SECTION 01 11 00.00 25 Page 1
1.4 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the Government designated storage area located within 10 miles of the construction site.
Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS - Not used
PART 3 EXECUTION - Not used
-- End of Section --
SECTION 01 11 00.00 25 Page 2
SECTION 01 14 00.00 25
WORK RESTRICTIONS
01/17
NAVFAC SE VERSION
NAS FT. WORTH 02/2017 REVISIONS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29.00 25 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
Digital Access Request Form (DARF)
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.2.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.2.1.2 Identification Badges and Installation Access
Application for and use of badges will be as directed. Obtain access to the installation by participating in the Navy Commercial Access Control System (NCACS), or by obtaining passes each day from the Base Pass and Identification Office. Costs for obtaining passes through the NCACS are the responsibility of the Contractor. One-day passes, issued through the Base Pass and Identification Office, will be furnished without charge.
Furnish a completed EMPLOYMENT ELIGIBILITY VERIFICATION (DHS FORM I-9) form for all personnel requesting badges. This form is available at http://www.uscis.gov/portal/site/uscis by searching or selecting Employment Verification (Form I-9) . Immediately report instances of lost or stolen badges to the Contracting Officer.
a. NCACS Program: NCACS is a voluntary program in which Contractor personnel who enroll, and are approved, are subsequently granted access
SECTION 01 14 00.00 25 Page 1 to the installation for a period up to one year, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued NCACS participation and installation access privileges. Under the NCACS program, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON).
Information on costs and requirements to participate and enroll in NCACS is available at http://www.rapidgate.com or by calling 1-877-727-4342. Contractors should be aware that the costs incurred to obtain NCACS credentials, or costs related to any means of access to a Navy Installation, are not reimbursable. Any time invested, or price(s) paid, for obtaining NCACS credentials will not be compensated in any way or approved as a direct cost of any contract with the Department of the Navy.
b. One-Day Passes: Participation in the NCACS is not mandatory, and if the Contractor chooses to not participate, the Contractor's personnel will have to obtain daily passes, be subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government will not be responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the NCACS.
c. One-Day Pass Requests: The Contractor shall submit a one-day pass requests to the Contracting Officer's Representative by 1300 hours 2 working days in advance via the AMRDEC website. NAVFAC will provide a digital access request form (DARF) at the preconstruction meeting
1.2.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.2.2 Working Hours
Regular working hours will consist of an 8 1/2 hour period between 8:00 a.m. and 4:30 p.m., Monday through Friday, excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
SECTION 01 14 00.00 25 Page 2
1.2.4 Exclusionary Period
No work may be performed during the period 26 December to 31 December, inclusive, without prior written approval of the Contracting Officer. This period has been considered in computing the time allowed for the performance of this contract.
1.2.5 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required paragraph WORK OUTSIDE REGULAR HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone/data service, electric service, air conditioning, heating, fire alarm, compressed air, and natural gas are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to six hours. This time limit includes time for deactivation and reactivation.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain. Obtain Installation's Sanitary Sewer Connection Permit 20 working days prior to connection and in accordance with Section 33 30 00 SANITARY SEWERS.
1.3 Restricted Area Requirements
Not Used
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION - Not Used
SECTION 01 14 00.00 25 Page 3
SECTION 01 20 00.00 25
PRICE AND PAYMENT PROCEDURES
01/17
NAVFAC SE VERSION
NAS FT. WORTH 02/2017 REVISIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP-1110-1-8 (2009) Construction Equipment Ownership and Operating Expense Schedule
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29.00 25 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Schedule of Prices; G
1.3 SCHEDULE OF PRICES
1.3.1 Data Required. This contract requires the use of a cost-loaded schedule. The information required for the Schedule of Prices will be entered as an integral part of the Construction Schedule. Within 15 working days after the preconstruction meeting, prepare and deliver to the Contracting Officer a Schedule of Prices (construction contract) as directed by the Contracting Officer on a NAVFAC LANT Form 4330/4 (REV. DEC 2012). Provide the cost for each cost loaded activity on the Construction Schedule.
1.3.2 Schedule Instructions. Payments will not be made until the Schedule of Priceshas been submitted to and accepted by the Contracting Officer.
Identify the cost for site work, and include incidental work to the 5 ft line. Identify costs for the building(s), and include work out to the 5 ft line. Work out to the 5 ft line shall include construction encompassed within a theoretical line 5 ft from the face of exterior walls and shall include attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 ft line.
1.3.3 Real Property Assets. The Government will provide the Draft DD Form 1354, Transfer and Acceptance of Military Real Property filled in with the appropriate Real Property Unique Identifiers (RPUID) and related construction Category Codes to summarize the designed real property assets that apply to this contract. The Contractor shall meet with the
SECTION 01 20 00.00 25 Page 1
Contracting Officer and the Real Property Accounting Officer during the Pre Construction Meeting and the Project Closeout Meetings to modify and include any necessary changes to the DD Form 1354. The Contractor shall provide the Interim DD Form 1354 that uses the appropriate division of the RPUIDs/ Category Codes to represent the final constructed facility and include all associated cost. Coordinate the Contractor's Price and Payment structure with the structure of the RPUIDs/ Category Codes.
Divide detailed asset breakdown into the RPUIDs and related construction Category Codes and populate associated costs which represent all aspects of the work. Where assets diverge into multiple RPUID/ Category Codes, divide the asset and provide the proportion of the assets in each RPUID/ Category Code. Assets and related RPUID/ Category Codes may be modified by the Contracting Officer as necessary during course of the work. Coordinate identification and proportion of these assets with the Government Real Property Accounting Officer.
Cost data accumulated under this section are required in the preparation of DD Form 1354.
1.3.4 Schedule Requirements for HVAC TAB
The field work Section 23 05 93 TESTING, ADJUSTING, AND BALANCING FOR HVAC shall be broken down in the Schedule of Prices and in the Construction Progress Documentation by separate line items which reflect measurable deliverables. Specific payment percentages for each line item shall be determined on a case by case basis for each contract. The line items shall be as follows:
a. Approval of Design Review Report: The TABS Agency is required to conduct a review of the project plans and specifications to identify any feature, or the lack thereof, that would preclude successful testing and balancing of the project HVAC systems. The resulting findings shall be submitted to the Government to allow correction of the design. The progress payment shall be issued after review and approval of the report.
b. Approval of the pre-field engineering report: The TABS Agency submits a report which outlines the scope of field work. The report shall contain details of what systems will be tested, procedures to be used, sample report forms for reporting test results and a quality control checklist of work items that must be completed before TABS field work commences.
c. Season I field work: Incremental payments are issued as the TABS field work progresses. The TABS Agency mobilizes to the project site and executes the field work as outlined in the pre-field engineering report. The HVAC water and air systems are balanced and operational data shall be collected for one seasonal condition (either summer or winter depending on project timing).
d. Approval of Season I report: On completion of the Season I field work, the data is compiled into a report and submitted to the Government.
The report is reviewed, and approved, after ensuring compliance with the pre-field engineering report scope of work.
e. Completion of Season I field QA check: Contract QC and Government representatives meet the TABS Agency at the jobsite to retest portions of the systems reported in the Season I report. The purpose of these
SECTION 01 20 00.00 25 Page 2 tests are to validate the accuracy and completeness of the previously submitted Season I report.
f. Approval of Season II report: The TABS Agency completes all Season II field work, which is normally comprised mainly of taking heat transfer temperature readings, in the season opposite of that under which Season I performance data was compiled. This data shall be compiled into a report and submitted to the Government. On completion of submittal review to ensure compliance with the pre-field engineering report scope, progress payment is issued. Progress payment is less than that issued for the Season I report since most of the water and air balancing work effort is completed under Season I.
1.4 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause "DFARS 252.236-7000, Modification Proposals-Price Breakdown," and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, equipment use rates shall be based upon the applicable provisions of the EP-1110-1-8.
1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.5.1 Content of Invoice
Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27, Prompt Payment Construction Contracts and FAR 52.232-5, Payments Under Fixed-Price Construction Contracts. The requests for payment shall include the documents listed below.
a. Approved updated Project Schedule for invoice interval with the respective reports required by the contract.
b. Contractor Safety Self Evaluation Checklist and Monthly Work-Hour Exposure Report.
c. Other supporting documents as requested. Other supporting documents may include missing QC, production or test reports.
d. Up to date copy of the:
Rework Log Submittal Register Testing Log
e. Solid Waste Disposal Report.
f. Contractor's Monthly Estimate for Voucher (NAVFAC LANT Form 4330/4 (REV.
DEC 2012)) with Subcontractor and supplier payment certification.
g. Contractor's Invoice, NAVFAC Form 7300/30 (DEC 2012).
h. All contractor and subcontractor certified payrolls covering each week for the invoiced period.
Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies.
1.5.2 Submission of Invoices. If DFARS Clause 5252.232-7006 is included in
SECTION 01 20 00.00 25 Page 3 the contract, provide the documents listed in paragraph CONTENT OF INVOICE in their entirety as attachments in the Invoicing, Receipt, Acceptance, and Property Transfer (iRAPT) application in the Wide Area Workflow (WAWF) eBusiness Suite for each invoice submitted. The maximum size of each iRAPT attachment is two megabytes, but there are no limits on the number of attachments. Attachment File Names cannot contain spaces or special characters, except underscore "_". If a document cannot be attached in iRAPT due to system or size restriction, provide it as instructed by the Contracting Officer.
Monthly invoices and the supporting documents shall be submitted to the Contracting Officer's Representative (COR) on a date to be assigned by COR at the preconstruction meeting.
1.5.3 Final Invoice
a. A final invoice shall be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release shall contain the corporate seal. An officer of the corporation shall sign and the corporate secretary shall certify the Final Release.
b. For final invoices being submitted via iRAPT, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor shall then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in iRAPT.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.6 PAYMENTS TO THE CONTRACTOR
Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.
1.6.1 Obligation of Government Payments. The obligation of the Government to make payments required under the provisions of this contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with "FAR 32.503-6:
a. Reasonable deductions due to defects in material or workmanship;
b. Claims which the Government may have against the Contractor under or in connection with this contract;
c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and
d. Failure to provide up to date record drawings not current as stated in
SECTION 01 20 00.00 25 Page 4
Contract Clause "FAC 5252.236-9310, Record Drawings."
1.6.2 Payment for Onsite and Offsite Materials. Progress payments may be made to the contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:
a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
b. Materials delivered on the site but not installed, including completed preparatory Marshall be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings,precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings
c. Materials to be considered for progress payment prior to installation shall be specifically and separately identified in the Contractor's Schedule of Prices submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this contract.
Requests for progress payment consideration for such items shall be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 have been met.
d. Materials are adequately insured and protected from theft and exposure.
e. Not used.
f. Materials to be considered for progress payments prior to installation shall be stored on site.
g. Materials in transit to the job site or storage site are not acceptable for payment.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION - Not Used
SECTION 01 20 00.00 25 Page 5
SECTION 01 30 00.00 25
ADMINISTRATIVE REQUIREMENTS
01/17
NAVFAC SE VERSION
NAS FT. WORTH 02/2017 REVISIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29.00 25 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
View Location Map; G
Progress and Completion Pictures; G
Supervisor's Qualifications; G. Provide a resume describing the qualifications applicable to this project. The Contracting Officer's Representative may interview the proposed superintendent prior to acceptance to verify the qualifications.
SD-04 Samples
Color Boards; G
1.3 COLOR BOARDS FOR AIR FORCE PROJECTS
Submit five sets of color boards within 90 calendar days after Contract Award. Each set of boards must include samples of colors and finishes of interior surfaces, such as walls, floors, and ceilings. Present the samples on 8 by 10-1/2 inches boards (modules) with a maximum spread of 24 by 31-1/2 inches for foldouts. Design modules to fit in a standard loose-leaf, three-ring binder. Where special finishes such as architectural concrete, carpet, or prefinished textured metal panels are required, submit samples not less than 12 inches square with the board. If more space is needed, more than one board per set may be submitted.
Certify that the color samples have been reviewed in detail, and that the color samples are in strict accordance with contract drawings and specifications, except as may be otherwise explicitly stated. Submittal of
SECTION 01 30 00.00 25 Page 1 color samples does not relieve the Contractor of the responsibility to submit samples required elsewhere herein.
1.4 VIEW LOCATION MAP
Prior to taking any photographs submit to the Contracting Officer's Representative a view location sketch or drawing requesting permission to photograph the project from the views locations shown. Update as required if the view locations are moved. Do not take any photographs without the Contracting Officer's Representative's permission.
1.5 PROGRESS AND COMPLETION PICTURES
Photographically document site conditions prior to start of construction operations and at the same locations upon completion of work, digital photographs, 1600x1200x24 bit true color 600 minimum resolution in JPEG file format showing the sequence and progress of work. Take photographs from points identified by the Contracting Officer's Representative and any other locations requested by the Contractor. Submit photographs with the first and final invoice.
Submit a view location sketch indicating photograph points of view. The view location sketch shall also be provided on the CD as digital file. All file names shall include a date designator. Cross reference submittals in the appropriate daily report. Photographs shall be provided for unrestricted use by the Government.
1.6 MINIMUM INSURANCE REQUIREMENTS
Provide the minimum insurance coverage required by FAR 28.307-2 LIABILITY, during the entire period of performance under this contract. Provide other insurance coverage as required by State law.
a. Prior to commencement of work hereunder, furnish to the Contracting Officer a certificate or written statement of the above required insurance. The policies evidencing required insurance must contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the Government in such insurance will not be effective until 30 days after written notice thereof to the Contracting Officer.
1.7 FIRST TIER CONTRACTOR REQUIREMENTS FOR ASBESTOS CONTAINING MATERIALS
Accomplish all contract requirements assigned to the Private Qualified Person (PQP), directly with a first tier subcontractor.
1.8 SUPERVISION
1.8.1 Minimum Communication Requirements
Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual must also have fluent English communication skills.
SECTION 01 30 00.00 25 Page 2
1.8.2 Supervisor's Qualifications
The project superintendent must have a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity with specific experience constructing masonry walls; installing open web steel joist framing, standing seam roofs, plumbing and fire alarms; as well HVAC installation and startup.
The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent.
The Contracting Officer's Representative may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.
1.8.2.1 Duties
The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.
The superintendent is required to attend NAVFAC Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.
1.8.3 Non-Compliance Actions
The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion. Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.
1.9 PRECONSTRUCTION MEETING
After award of the contract but prior to commencement of any work at the site, meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal. Major subcontractors who will engage in the work must also attend.
1.10 FACILITY TURNOVER PLANNING MEETINGS (NAVFAC Red Zone - NRZ)
Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the Pre-Construction Conference meeting with a discussion of the NAVFAC Red Zone (NRZ) process and convene at regularly scheduled NRZ Meetings. Include the following in the facility Turnover effort:
1.10.1 NRZ Checklist
a. Contracting Officer's Representative (COR) will provide the Contractor a copy of the NRZ Checklist template prior to 75 percent completion.
SECTION 01 30 00.00 25 Page 3
b. Prior to 75 percent completion add/delete critical activities to the NRZ Checklist template as necessary to match the project scope, and schedule critical activities and insert planned completion dates in the NRZ checklist for each critical activity. Present the NRZ Checklist to COR and review during a regularly scheduled QC Meeting.
1.10.2 Meetings
a. Upon Government acceptance of the NRZ Checklist, the Project Superintendent is required to lead regular NRZ Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.
b. The Contracting Officer will determine the frequency of the meetings, which is expected to increase as the project completion draws nearer.
c. Using the NRZ Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.
d. Coordinate with the COR any upcoming activities that require Government involvement.
e. Maintain the NRZ Checklist by documenting the actual completion dates as work is completed and update the NRZ Checklist with revised planned completion dates as necessary to match progress. Distribute copies of the current NRZ Checklist to attendees at each NRZ Meeting.
1.11 PARTNERING
To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the Supported Command, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.
The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.
1.12 ELECTRONIC MAIL (E-MAIL) ADDRESS
Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within 10 days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats.
Multiple email addresses are not allowed.
SECTION 01 30 00.00 25 Page 4
It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.
1.13 ELECTRONIC FILES
a. The Contractor must have the capability to create, edit and read pdf files compatible with Adobe Acrobat XI version 11.0.
b. The Contractor must have the capability to transmit and receive documents via AMRDEC Safe Access File Exchange at https://safe.amrdec.army.mil/SAFE/.
c. The Contractor must have the capacity to create, edit and read files compatible with Microsoft Office 2010 products.
PART 2 PRODUCTS - Not Used
PART 3 EXECUTION - Not Used
SECTION 01 30 00.00 25 Page 5
SECTION 01 32 16.00 25
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01/17
NAVFAC SE VERSION
NAS FT. WORTH 02/2017 REVISIONS
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Construction Schedule; G
Resume Outlining The Qualifications Of The Scheduler; G
SD-07 Certificates
Monthly Updates
1.2 ACCEPTANCE
Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a cost loaded construction schedule in the form of a Network Analysis Schedule (NAS) in accordance with the terms in Contract Clause "FAR 52.236-15, Schedules for Construction Contracts," except as modified in this contract.
The acceptance of a Baseline Construction Schedule is a condition precedent to:
a. The Contractor starting work on the demolition or construction stage(s) of the contract.
b. Processing Contractor's invoice(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 SCHEDULE FORMAT
1.3.1 Network Analysis Schedule (NAS)
Use the critical path method (CPM) to schedule and control project activities. Prepare and maintain project schedules using Primavera P6.
SECTION 01 32 16.00 25 Page 1
Importing data into the scheduling program using data conversion techniques or third party software is cause for rejection of the submitted schedule.
Build the schedule as follows:
a. The Project Schedule must show submittals, Government review periods, material/equipment delivery, utility outages, all on-site construction, inspection, testing, preparatory meetings for each definable feature of work, utility locate digging permits, and closeout activities.
Government and Contractor on-site work activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days.
Create activities for modifications as the project progresses.
Identify the activity by the modification title and "P" number.
b. With the exception of the Contract Award and End Contract milestone activities, no activities will be open-ended; each activity must have predecessor and successor ties. No activity must have open start or open finish (dangling) logic. Minimize redundant logic ties. Once an activity exists on the schedule it must not be deleted or renamed to change the scope of the activity and must not be removed from the schedule logic without approval from the Contracting Officer. While an activity cannot be deleted, where said activity is no longer applicable to the schedule but must remain within the logic stream for historical record, it can be changed to a milestone. Document any such change in the milestone's "Notebook", including a date and explanation for the change. The ID number for a deleted activity must not be re-used for another activity.
c. Each activity must be assigned its appropriate Responsibility Code indicating responsibility to accomplish the work indicated by the activity, Phase Code and Work Location Code. Activities must not belong to more than one responsible party.
d. Date/time constraint(s) and/or lags, other than those required by the contract, are not allowed unless accepted by the Contracting Officer.
Include as the last activity in the contract schedule, a milestone activity named "Contract Completion Date".
e. Identify each activities in the project schedule with its respective Division or Specification Section number. Activities must not belong to more than one Division or Section number.
Identify all activities in the project schedule with its respective Drawing Code. The Drawing Code is the Sheet Number on the primary project drawing which indicates work to be performed. If an activity does not have an applicable Drawing Code (e.g. Mobilize), the code must be "0000"
f. Include activities with all items on the NAVFAC Red Zone Checklist/POAM that are applicable to this project. As a minimum, include all testing, specialized inspection activities, Pre-Final Inspection, Punch List Completion, Final Inspection and Acceptance. Add a milestone for the Facility Turnover Planning Meeting at approximately 75 percent construction contract completion or three to six months prior to Contract Completion Date (CCD), whichever is sooner.
1.3.1.1 Primavera P6 Settings and Parameters
Use the following Primavera P6 settings and parameters in preparing the
SECTION 01 32 16.00 25 Page 2
Baseline Schedule. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.
a. General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.
b. Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:
(1) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week, 172.0 Hours/Month and 2000.0 Hours/Year.
(2) Use assigned calendar to specify the number of work hours for each time period: Must be checked.
c. Project Level, Dates Tab:
(1) Set "Must Finish By" date to "Contract Completion Date".
d. Project Level, Defaults Tab:
(1) Duration Type: Set to "Fixed Duration & Units".
(2) Percent Complete Type: Set to "Physical".
(3) Activity Type: Set to "Task Dependent".
(4) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days.
Alternative calendars may be used with Contracting Officer approval.
e. Project Level, Calculations Tab:
(1) Activity percent complete based on activity steps: Must be Checked.
(2) Reset Remaining Duration and Units to Original: Must be Checked.
(3) Subtract Actual from At Completion: Must be Checked.
(4) Recalculate Actual units and Cost when duration percent(%) complete changes: Must be Checked.
(5) Link Actual to Date and Actual This Period Units and Cost: Must be Checked.
f. Project Level, Settings Tab:
(1) Define Critical Activities: Check "Total Float is less than or equal to" and add "0d".
g. No on-site construction activity may have durations in excess of 20 working days.
1.3.1.2 Qualifications
The designated Scheduler for the project must have prepared and maintained at least 3 previous schedules of similar size and complexity of this contract using Primavera P6. Submit a resume outlining the qualifications
SECTION 01 32 16.00 25 Page 3 of the Scheduler. Payment will not be processed until an acceptable Scheduler is provided.
1.3.2 Schedule Submittals and Procedures
Submit Network Analysis Schedules (NAS) and updates in hard copy and on electronic media that is acceptable to the Contracting Officer. Submit an electronic of the project schedule in Primavera P6.
1.4 Cost Loading
Assign Material and Equipment Costs, for which payment will be requested in advance of installation, to their respective procurement activity (i.e., the material/equipment on-site activity).
Assign cost for material/equipment, paid for after installation; labor; and construction equipment to their respective Construction Activities.
Evenly disperse overhead and profit to each activity over the duration of the project.
Each cost loaded activity must have a detailed quantity breakdown and unit of measure. Lump sum costing is not acceptable.
1.5 SCHEDULE MONTHLY UPDATES
Update and submit the Construction Schedule at monthly intervals or when the schedule has been revised. The updated schedule must be kept current, reflecting actual activity progress and plan for completing the remaining work. Schedule updates must incorporate as-built events as they occur and provide ongoing status of anticipated finish dates. As-built events must correspond to contemporaneous records including but not limited to submittals, daily production reports and quality control reports. Submit copies of purchase orders and confirmation of delivery dates as directed by the Contracting Officer. The submission of an acceptable, updated schedule to the Government is a condition precedent to the processing of the Contractor's invoice. Submit an updated schedule to the Government regardless of whether a Contractor's invoice is submitted for the given period. Provide the following supporting documents with the updated schedule:
a. Narrative Report: Provide with schedule updates. Identify and justify;
(1) Progress made in each area of the project
(2) Critical Path
(3) Date/time constraint(s), other than those required by the contract
(4) Changes in the following; added or deleted activities, original and remaining durations for activities that have not started, logic, milestones, planned sequence of operations, and critical path
(5) Status of Contract Completion Date and interim milestones;
(6) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);
SECTION 01 32 16.00 25 Page 4
(7) Description of current and future schedule problem areas.
b. Up to date copy of the:
(1) Rework Log
(2) Submittal Register
(3) Testing Log
c. Contractor's Monthly Estimate for Voucher (NAVFAC LANT Form 4330/4 (REV. DEC 2012)) with Subcontractor and supplier payment certification.
d. Contractor's Invoice, NAVFAC Form 7300/30 (DEC 2012).
e. Other supporting documents such as .xls or .xer files as requested by the Contracting Officer's Representative. Other supporting documents may also include missing QC, production or test reports.
Each entry in the narrative report must cite the respective Activity ID and Activity Description, the date and reason for the change, and description of the change.
1.6 CONTRACT MODIFICATION
Submit a Time Impact Analysis (TIA) with each cost and time proposal for a proposed change. TIA must illustrate the influence of each change or delay on the Contract Completion Date or milestones. No time extensions will be granted nor delay damages paid unless a delay occurs which consumes all available Project Float, and extends the Projected Finish beyond the Contract Completion Date.
a. Each TIA must be in both narrative and schedule form. The narrative must define the scope and conditions of the change; provide start and finish dates of impact, successor and predecessor activity to impact period, responsible party, describe how it originated, and how it impacts the schedule. The schedule submission must consist of three native files:
(1) Fragnet used to define the scope of the changed condition
(2) Most recent accepted schedule update as of the time of the proposal or claim submission that has been updated to show all activity progress as of the time of the impact start date.
(3) The impacted schedule that has the fragnet inserted in the updated schedule and the schedule "run" so that the new completion date is determined.
b. For claimed as-built project delay, the inserted fragnet TIA method must be modified to account for as-built events known to occur after the data date of schedule update used.
c. All TIAs must include any mitigation, and…