N6945018R1735_SectionC_0003.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6945018R1735-0004.pdf | ||
| N6945018R1735_ConformedSectionB.pdf | ||
| N6945018R1735_SectionJ_0003.pdf | ||
| N6945018R1735-0003.pdf | ||
| N6945018R1735_GPIs_0003.pdf | ||
| N6945018R1735-0002.pdf | ||
| N6945018R1735-0002_Attachments.zip | ZIP file | |
| N6945018R1735_Site_Visit_Itinerary.pdf | ||
| N6945018R1735-0001.pdf | ||
| N69450-18-R-1735.pdf | ||
| N69450-18-R-1735_Attachments.zip | ZIP file |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Section C N69450-18-R-1735
0100000 – General Information Table of Contents Spec Item Title 1 General Information
1.1 Outline of Services
1.2 Project Location
1.3 Acquisition of Additional Work
1.4 Background Information
1.5 Verification of Workload and Conditions
1.6 Climate Patterns
1.7 Related Information
1.8 Navy Approach to Service Contracting
1.8.1 Partnering Philosophy
1.8.2 Contractor's Knowledge
1.8.3 Industry Best Practices
1.9 Standard Template
1.10 Navy PBSA Approach
1.11 Technical Proposal Certification
0100000 – General Information Spec Item Title Description 1 General Information
1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at Naval Support Activity (NSA) Orlando, FL and outlying areas under an Indefinite Delivery Indefinite Quantity type, performance-based contract that is comprised of both Recurring Work and Non-Recurring Work Items.
The PWS is organized into annexes. Annex 1 is "General Information".
Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.
The annex numbers are identified as 1 through 18 in the description column, but the full expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).
Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff – N/A Annex 4 Public Safety – N/A Annex 5 Air Operations – N/A Annex 6 Port Operations – N/A Annex 7 Ordnance – N/A Annex 8 Range Operations – N/A Annex 9 Health Care Support – N/A Annex 10 Supply – N/A Annex 11 Personnel Support – N/A Annex 12 Morale, Welfare and Recreation Support – N/A Annex 13 Galley – N/A Annex 14 Housing – N/A Annex 15 Facilities Support 1502000 Facility Investment 1503020 Pest Control 1503030 Integrated Solid Waste Management 1503050 Grounds Maintenance and Landscaping Annex 16 Utilities – N/A Annex 17 Base Support Vehicles and Equipment – N/A Annex 18 Environmental
1.2 Project Location The work shall be performed at various locations and could vary from location to location. The following is an example of the dispersion of work at the various locations.
(1) Facility Investment Services: NSA Orlando, FL, NEX Orlando, FL and NUWC OSO Okahumpka, FL
(2) Pest Control Services: NSA Orlando, FL and NUWC OSO Okahumpka, FL.
(3) Integrated Solid Waste Management Services: NSA Orlando, FL and NUWC OSO Okahumpka, FL.
(4) Grounds Maintenance and Landscaping Services: NSA Orlando, FL, and NUWC OSO Okahumpka, FL.
Non-recurring work outside of the locations identified above may be requested by the KO, but shall not exceed 120 miles from NSA Orlando.
1.3 Acquisition of
Additional Work
The Government reserves the right to acquire additional services at additional locations in addition to the services and locations identified in the recurring work requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the indefinite delivery indefinite quantity provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.
1.4 Background Information Naval Support Activity (NSA) Orlando opened in 1988 as the home of the Naval Air Warfare Center Training Systems Division (NAWCTSD) Orlando. NAWCTSD Orlando is the Navy’s principal center for modeling, simulation, and training systems technologies. The Center provides training systems development for a wide spectrum of military programs, including aircraft, surface ships, submarines, and other specialized requirements.
NSA Orlando consists of five (5) primary facilities, several secondary facilities and structures, internal roads and parking areas, green space, and woods. The main building is the De Florez Building which houses approximately 264,000 square feet of office space, laboratories, and small food service operation. The four smaller buildings, The Annex (Building 2), The Mechanical Equipment Building (Building 3), Welcome Center (Building 4), and the Logistics Support Facility (Building 5). The facility areas are approximately 34,000, 4,000, 2,100, and 1,800 square feet respectively. The land area total for NSA Orlando (Federal lands) is 40.46 acres.
NSA Orlando also has several remote locations referred to as Special Areas. NSA Orlando Special Areas include two additional sites in Orlando, three sites in Tampa, one site in Cape Canaveral, one site in Titusville, one site in Okahumpka, and one site in Daytona Beach. Most of these sites are not included under the Recurring Work portion of this contract, but Non-recurring work may be requested by the KO as stated in Spec Item 2.1, Project Location.
Special Areas locations which are included under the Recurring Work portion of this contract are the Naval Undersea Warfare Center On-Site Office (NUWC OSO) in Okahumpka and Navy Exchange Orlando just west of Orlando International Airport.
1.5 Verification of
Workload and Conditions
Throughout the PWS, the workload data is generally referred to as being located in Section J. Section J provides data such as inventories, maps, floor plans, and tables to represent the type, quantity and location of services to be provided. However, offerors are encouraged to visit the project site during the site visit for offerors and to visit the technical library during posted hours as part of its due diligence to assess the nature of work and conditions under which work is to be performed.
1.6 Climate Patterns Orlando, FL and areas near, has mild winters and hot and humid summers.
1.7 Related Information There are four types of Related Information that can be found in the
Description and Related Information columns of the specification as follows:
Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 is subject to this disclaimer. Offerors may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractual requirement on either party to this contract.
Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.
Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.
Requirement Information further describes client requirements associated with each Performance Objective.
1.8 Navy Approach to
Service Contracting
The Department of Navy (DoN) spends over $1 billion in annual obligations to meet global requirements for facility operations and maintenance provided through Facility Support Contracts (FSC) and additional billions to provide other base operations support services (OBOS). The Head of the Contracting Activity (HCA) of the Naval Facilities Engineering Command (NAVFAC) has focused increased attention on re-engineering FSC contracts in response to customer and industry feedback, budget constraints, and the impact of a variety of contracting, program management and financial management regulations.
The Navy also supports the following principles:
1.8.1 Partnering Philosophy The first principle is that the Navy views its contractors as partners and not just abstract service providers. The Navy wants its contractors to succeed because partners' success drives the Navy's successful mission completion.
Within the bounds of acquisition policy the Navy intends to work to find solutions that will be beneficial to both the Government and its partners.
1.8.2 Contractor's Knowledge The second principle is that the Navy will receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle.
Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.
1.8.3 Industry Best Practices The third principle is that the Navy will adopt industry best commercial practices and maintain state-of-the-art service delivery. It is the Navy's and contractor's responsibility as partners to reach this goal. To that end, the Navy's emphasis will be in evaluating performance objectives (end results).
1.9 Standard Template Key to implementing a programmatic approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs. This contract conforms to the standard template and has been tailored for this solicitation. NAVFAC intends to use this template-based approach for future service contracts. Offerors should develop an understanding of the template as part of performing due diligence in reaching an understanding of the Navy’s requirements and expectations.
The standard template contains 18 standard annexes. Annex 1 will always contain information that is relevant to the entire scope of the contract.
Annex 2 contains on-site project management and administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 contain the technical information and requirements peculiar to that technical annex. Within each technical annex, the organization of information and requirements are also standardized. Specification item 1 will always contain General Information. Specification item 2 will always contain the management and administrative requirements. Specification item 3 will always contain the Recurring Work requirements.
Specification item 4 will always contain the Non-recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.
Specification Items 3.2 and 3.3 are not considered subordinate to 3.1. All costs associated with Annexes 1 and 2 and Specification items 1 and 2 must be priced and distributed within Specification Item 3 of Annexes 3 through 18.
1.10 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.
1.11 Technical Proposal
Certification
The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.
0200000 – Management and Administration Table of Contents
2 Management and Administration
2.1 Definitions and Acronyms
2.2 General Information
2.2.1 Government Regular Working Hours
2.2.1.1 Observed Federal Holidays
2.2.1.2 Restriction to Contractor Working Hours
2.2.2 Wage Determinations
2.2.3 Requirements Hierarchy
2.3 General Administrative Requirements
2.3.1 Required Conferences and Meetings
2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment
2.3.3 Partnering
2.3.3.1 Informal Partnering
2.3.3.2 Contract Partnering Administration
2.3.3.3 Contract Partnering Session Attendees
2.3.4 Permits and Licenses
2.3.5 Insurance
2.3.5.1 Certificate of Insurance
2.3.5.2 Minimum Insurance Amounts
2.3.6 Protection of Government Property
2.3.7 Government Information Technology (IT) System
2.3.8 Directives, Instructions, and References
2.3.9 Invoicing Procedures
2.3.10 Forms
2.4 Government-Furnished Property, Materials and Services
2.4.1 Government-Furnished Facilities (GFF)
2.4.2 Government-Furnished Utilities
2.4.3 Government-Furnished Materials (GFM)
2.4.4 Government-Furnished Equipment (GFE)
2.5 Contractor-Furnished Items
2.6 Management
2.6.1 Work Reception
2.6.2 Work Control
2.6.3 Work Schedule
2.6.4 Deliverables
2.6.5 Service Interruptions
2.6.6 NAVFAC MAXIMO
2.6.6.1 MAXIMO Data
2.6.6.2 MAXIMO Method of Data Entry
2.6.6.3 MAXIMO Access
2.6.6.4 MAXIMO Training
2.6.6.5 Inventories and Workload Data
2.6.7 Quality Management System (QMS)
2.6.7.1 Quality Management (QM) Plan
2.6.7.2 Quality Inspection and Surveillance
2.6.7.3 Quality Inspection and Surveillance Report
2.6.8 Property Management Plan
2.6.9 System and Equipment Replacement
2.7 Personnel Requirements
2.7.1 Key Personnel
2.7.1.1 Project Manager (PM)
2.7.1.2 Quality Manager
2.7.1.3 Site Safety and Health Officer (SSHO)
2.7.2 Employee Requirements
2.7.2.1 Employee Certification and Training
2.7.2.2 Employee Appearance
2.7.2.3 Employee Conduct
2.7.2.4 Identification as Contractor Employee
2.7.2.5 Removal of Employees
2.7.2.6 Proof of Legal Residency
2.7.3 Enterprise-wide Contractor Manpower Reporting Application (eCMRA)
2.8 Security Requirements
2.8.1 Employee Listing
2.8.2 Vehicles
2.8.3 Passes and Badges
2.8.4 Access to Installation
2.8.4.1 DBIDS Program
2.8.4.2 DBIDS Credentials
2.8.4.3 DBIDS Paper Passes
2.8.5 Access to Buildings
2.8.6 Access Arrangements
2.8.6.1 Escort Arrangement for Secured Areas
2.8.7 Security Clearances
2.8.8 Access to Sensitive Unclassified Information
2.8.9 Employee Status
2.8.10 Access to Navy Marine Corp Intranet (NMCI)
2.9 Contractor Safety Program
2.9.1 Subcontractor Safety Requirements
2.9.2 Accident Prevention Plan (APP)
2.9.3 Activity Hazard Analysis (AHA)
2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans
2.9.4.1 Alcohol and Drug Abuse Prevention Plan
2.9.4.2 Chemical Hazard Communication Program
2.9.4.3 Confined Space Program
2.9.4.4 Fire Prevention Program
2.9.4.5 Health Hazard Control Program and Hazard Communication Program
2.9.4.6 Respiratory Protection Program
2.9.4.7 Critical Lift Plan
2.9.4.8 Fall Prevention and Protection Plan
2.9.5 Crane Operations
2.9.5.1 Crane Inspections
2.9.5.2 Rigging Gear
2.9.5.3 Crane Operators
2.9.6 Accident and Damage Reporting
2.9.6.1 Accident Reporting and Notification Criteria
2.9.7 Fire Protection
2.9.8 Monthly On-Site Labor Report
2.9.9 OSHA Citations and Violations
2.9.10 Safety Inspections and Monitoring
2.9.11 Safety Certification
2.9.12 Safety Apparel on Jobsites
2.9.13 Emergency Medical Treatment
2.9.14 Hazardous Energy Control Program (HECP)
2.9.15 Excavations
2.10 Environmental Management and Sustainability
2.10.1 Energy Management Program
2.10.1.1 Water Conservation Plan
2.10.1.2 Energy Efficient Products
2.10.2 Environmental Protection
2.10.2.1 ODS Requirements for Refrigerant Recycling
2.10.2.2 Solid Waste Management and Recycling
2.10.2.3 Contractor’s controlled Solid Waste, Recycling, and Re-use Report
2.10.2.4 Non-Hazardous Waste Disposal
2.10.2.5 Hazardous Waste Disposal
2.10.2.6 Spill Prevention, Containment, and Clean-up
2.10.2.7 Hazardous Material Management
2.10.2.8 Protection of Endangered and Threatened Species (Flora and Fauna)
2.10.2.9 Noise Control
2.10.2.10 Salvage
2.10.2.11 Asbestos Containing Material (ACM)
2.10.3 Sustainable Procurement and Practices
2.10.3.1 Environmentally Preferable Products
2.10.3.2 Use of Recovered Materials
2.10.3.3 Use of Biobased Products
2.11 Disaster Preparedness and Recovery
2.12 Technical Library
2.13 Warranty Management
2.14 Recurring Work Procedures
2.14.1 Notification to the Government for Work Above the Recurring Work Limitations
2.14.2 Recurring Work Exhibit Line Item Numbers (ELINs)
2.15 Non-recurring Work
2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)
2.15.1.1 Acceptance and Performance
2.15.1.2 Invoicing and Receiving Payment
2.15.2 Unit Priced Labor (UPL)Work (Negotiated)
2.15.2.1 Non-recurring Work Preparation of Proposals
2.15.2.1.1 Labor Requirements
2.15.2.1.2 Material and Equipment Requirements
2.15.2.2 Issuance of Final Task Order
2.15.3 Non-recurring work ELINS
0200000 - Management and Administration
2 Management and
Administration
2.1 Definitions and
Acronyms
Definitions and Acronyms are listed in J-0200000-01.
2.2 General Information
2.2.1 Government Regular
Working Hours The Government's regular working hours are from 0800-1700, five days per week, Monday through Friday, except observed Federal holidays.
Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours requires prior KO approval.
2.2.1.1 Observed Federal
Holidays
The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.
2.2.1.2 Restriction to
Contractor Working Hours
If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.
2.2.2 Wage Determinations Statute wage determinations are provided in J-0200000-02.
2.2.3 Requirements
Hierarchy Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.
Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.
2.3 General Administrative
Requirements
2.3.1 Required Conferences
and Meetings
The Contractor shall be required to attend administrative and coordination meetings as scheduled by the KO.
2.3.2 Training for
Maintenance and Operation of New and Replacement Systems and Equipment
When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.
2.3.3 Partnering To increase the likelihood of successful performance of this contract, the Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who will receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and subcontractors teams, including senior management personnel must participate. The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.
Partnering should accomplish three goals:
- The first goal is to develop a cohesive team with common purpose, commitment and established communication processes.
- The second goal of partnering is contract specific, identifying risks and opportunities for the team to address.
- The third goal is to sustain the Partnership throughout the contract by identifying and addressing issues that affect the Partnership.
2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.
The Partners will determine the frequency of the follow-on sessions.
2.3.3.2 Contract Partnering
Administration
Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.
Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.
The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.
2.3.3.3 Contract Partnering
Session Attendees
The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.
President/Vice President
* Project Manager
* Quality Manager Site Safety and Health Officer
2.3.4 Permits and Licenses The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.
2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause 52.228-5, INSURANCE – WORK ON A GOVERNMENT INSTALLATION. This insurance must be maintained during the performance period.
2.3.5.1 Certificate of Insurance The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.
2.3.5.2 Minimum Insurance
Amounts
The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:
Comprehensive General Liability: $500,000 per occurrence
Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage
Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes
Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers
Other as required by state law
2.3.6 Protection of
Government Property
During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of negligence under this contract to their original condition at no cost to the Government.
2.3.7 Government
Information Technology (IT) System
Additional information about NMCI may be obtained at http://www.eds.com/nmci.
2.3.8 Directives, Instructions, and References
Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.
2.3.9 Invoicing Procedures Refer to DFARS Clauses 252.232-7003 titled “Electronic Submission of Payment Request” and 252.232-7006 WIDE AREA WORKFLOW
PAYMENT INSTRUCTIONS (MAY 2013).
2.3.10 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-04.
2.4 Government-Furnished
Property, Materials and Services
In accordance with Section H, paragraph H.10 Govt-Furnished Property, and the following paragraphs, the Government will furnish or make available to the Contractor certain Government-owned facilities, utilities, materials, equipment and services for use in connection with this contract as stated below:
2.4.1 Government-Furnished
Facilities (GFF)
Government furnished facilities are limited to Rooms 1111 (storage closet) and 1112, totaling approximately 813 SF, for Contractor use. The Government will also provide single 20 foot long "sea container" located inside the dumpster enclosure for additional storage.
Any additional off-site storage required is the responsibility of the Contractor at no additional costs to the Government.
2.4.2 Government-Furnished
Utilities
The Government will furnish water and electricity at existing outlets required for the work to be performed under the contract at no cost to the
Contractor. Information concerning the location of existing outlets may be secured from the KO. The Government will also provide one (1) government phone line and phone for Contactor use.
2.4.3 Government-Furnished
Materials (GFM)
The Government will not furnish any material for the accomplishment of this contract.
2.4.4 Government-Furnished
Equipment (GFE)
The Government will furnish a workstation in order to permit the Contractor to monitor, access, and maintain the Direct Digital Control (DDC) system. The workstation is located in Room 1112 per Spec Item
2.4.1. The workstation includes a central processing unit (CPU), monitor, and printer.
The Government will furnish two (2) fall protection system lanyard connectors (Flexible Lifeline Systems Transfastener, Part Number 168508500, Manufactured by Latchways, Serial Numbers 30208 & 30209) for the Contractor’s use for applicable work tasks.
2.5 Contractor-Furnished
Items
Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements. Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.
2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards.
Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.
2.6.1 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble calls/service orders and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours. Personnel receiving phone calls must be knowledgeable of the contract requirements and the facilities within the contract. Work reception personnel must be a direct employee of the prime contractor. A third-party answering service is not allowed.
Regular working hours are defined as 0800-1700 Monday through Friday.
2.6.2 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the KO. A status update of any item of work must be provided within four
(4) hours of the request.
2.6.3 Work Schedule The Contractor's work shall not interfere with normal Government business. In those cases where some interference is unavoidable, the
Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall notify the KO of any difficulty in scheduling work due to Government controls.
2.6.4 Deliverables Records and reports are specified in Section C and listed as deliverables in Section F. The Contractor shall submit accurate and complete documents within the required timeframes as specified in Section F. The Government may change of deliverable formats at any time at no additional cost to the Government.
Government acceptance of deliverables will not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.
The format of all documents shall be similar to the deliverable formats herein and in accordance with the formats agreed upon between Government and the Contractor. Any submittals that are not delivered in the proper format or without a cover sheet will be rejected and the contractor shall submit the proper deliverable within 24 hours of notification of rejection.
All submittals shall include a cover sheet with a minimum of the following:
Date Contract # Title of Deliverable Description/Summary of Deliverable Corrective Actions
The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website. Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The Contractor shall notify the Government by email whenever there are new or updated deliverables posted to the website.
Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.
2.6.5 Service Interruptions If any utilities, lighting or any other services defined in the contract must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO and affected tenants, within seven (7) calendar days. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, affected tenants and customers as soon as practicable.
2.6.6 NAVFAC MAXIMO MAXIMO is the Computerized Maintenance Management System (CMMS) used by the Government for work order history, asset management, and condition assessment.
2.6.6.1 MAXIMO Data Required data fields for work orders are indicated in the Service Provider Information provided in J-0200000-05. Asset inventory data requirements are indicated in the Asset Information provided in J-0200000-06.
Specified data shall be provided for all work performed in 1502000 Facility Investment, work/service orders for all annexes/sub-annexes, and Environmental Spill and Control Responses work orders. Further instructional information detailing the process for submitting the specified information for NAVFAC MAXIMO Data Reporting is provided in J- 0200000-07.
The Service Provider, Asset, Specification, and Characteristic Meter Reading Interfaces are used in multiple processes for loading data into MAXIMO by the Government and the format may be updated periodically.
As part of the update the Contractor may be asked to modify the file to add/move columns in their submission. The Contractor also shall provide up to 10 extra data elements or columns with as many as 150 characters per element for the Government to define during contract performance at no additional cost to the Government. The Government will provide the Contractor 60 calendar day notice of modifications to the Service Provider, Asset, or Specification file format.
2.6.6.2 MAXIMO Method of
Data Entry
The Contractor shall provide data for NAVFAC MAXIMO using Direct Entry. The Contractor shall manually enter required work order and condition assessment data directly into NAVFAC MAXIMO. The Contractor shall ensure all information is updated by the end of each workday for all work performed.
2.6.6.3 MAXIMO Access Contractor employees shall obtain a CAC in accordance with security requirements, successfully complete required training, submit a Systems Authorization Access Request (SAAR) Form, and meet all eligibility requirements prior to being granted access to the Government’s Maximo.
The Government will determine the level of access, restrictions, and provide user identification, password, and system access URL details when eligibility requirements are met.
Once accounts have been established, MAXIMO can be accessed at https://maximo.navfac.navy.mil.
The Government will provide access to a NMCI workstation located in Room 1112 for the dedicated use of the Contractor to access MAXIMO for Direct Entry of required data.
The Contractor shall submit a complete list of personnel requiring access to Government’s Maximo per Section F. The Contractor shall provide information on each employee as required by Government information technology personnel.
2.6.6.4 MAXIMO Training The Government will provide or make available initial training on NAVFAC MAXIMO to Contractor personnel responsible for direct entry of work order, asset, specification, and condition assessment data. The Contractor shall request training within 15 days prior to contract start.
Additional training will be provided by the Government when there are significant changes to the NAVFAC MAXIMO software or data entry requirements. Training due to changeover of personnel will be the responsibility for the Contractor. The Contractor will be provided a general user guide, local instructions, and other materials by the Government as reference material for the use of NAVFAC MAXIMO.
2.6.6.5 Inventories and
Workload Data
The Contractor shall maintain and keep current all inventories associated with any annex in this contract. The Contractor shall maintain and keep current all workload data, such as: service orders, preventive maintenance, preventive maintenance incidental repairs, integrated maintenance, integrated maintenance repairs, inspection, testing, and certifications, warranty information, etc. Current and accurate inventories and workload data shall be submitted to the KO per Section F
2.6.7 Quality Management
System (QMS)
The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:
Accurate documentation of work processes, procedures, and output measures.
A systematic procedure for assessing compliance with performance objectives and standards.
Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.
Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.
2.6.7.1 Quality Management
(QM) Plan
The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, submit to the KO a revised QM Plan for acceptance.
The Contractor’s QM Plan shall include, at a minimum, the following:
• Policy and objectives of Quality Management System (QMS)
• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications
• Approach to assuring quality of services provided and conformance with performance objectives and standards
• Methods and procedures for effective planning, operation and control of processes and performance of work
• Procedures for inspection and surveillance of services o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work
• Documentation and records management
• Communication with government (customers)
2.6.7.2 Quality Inspection and
Surveillance
The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be turned over to the KO within five calendar days of termination of the contract.
2.6.7.3 Quality Inspection and
Surveillance Report
The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a summary and results of the quality inspection and surveillance events performed and assessment-driven corrective actions and process adjustments during the previous month.
The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.
2.6.8 Property Management
Plan
The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished Property, Materials and Services, of this Annex. This plan shall identify the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Property Management Plan shall be submitted per Section F.
2.6.9 System and Equipment
Replacement
The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work. Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced.
Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.
2.7 Personnel
Requirements
The Contractor shall comply with the personnel requirements stated below.
2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO necessary to certify their qualifications.
The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract. The key personnel shall be revised as applicable for the contract.
The List of Key Personnel and Qualification and Organizational Chart shall be provided as two separate submittals.
2.7.1.1 Project Manager (PM) The Contractor shall provide a PM and designated alternate, as applicable, who has the have full authority to act for the Contractor on all contract matters relating to this contract. The PM or an equally-qualified designated alternate shall be on-site during the Government's regular working hours and shall be available on-site within one (1) hour after the Government's regular working hours.
The PM may not be the same person as the Quality Manager or the Site Safety and Health Officer (SSHO). The PM shall have at least three (3) years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.
2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager and designated alternate, as applicable, who has full responsibility to prepare and enforce the Contractor’s Quality Management System on this contract. The Quality Manager or an equally-qualified designated alternate shall be on site during Government regular working hours and shall be available on-site within one (1) hour after the Government's regular working hours. The Quality Manager must report directly to a senior corporate official and shall not report directly to the Project Manager.
The Quality Manager shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:
The Quality Manager shall have at least three (3) years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager may be the same person as the SSHO, but shall have fulfilled the pre-requisite qualification and experience. The Quality Manager may not be the same as the PM.
2.7.1.3 Site Safety and Health
Officer (SSHO)
The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project.
Provide a Safety oversight team that includes a minimum of one (1) Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.
A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the Contracting Officer for acceptance in consultation with the Safety Office.
The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract. The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:
The SSHO shall have completed five years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past or three years experience if he possesses a Certified Safety Professional (CSP) or safety and health degree. The SSHO shall have completed the OSHA 30-hour construction safety class or equivalent and maintain competency through 24 hours of formal safety and health related coursework every four years. The SSHO may be the same person as the Quality Manager but shall have fulfilled the pre-requisite qualification and experience.
Duties of the SSHO include the following:
a. Conduct daily safety and health inspections and maintain a written log which includes area/operation inspected, date of inspection, identified hazards, recommended corrective actions, estimated and actual dates of corrections. Attach safety inspection logs to the Contractors' daily production report.
b. Conduct mishap investigations and complete required accident reports.
Report mishaps, Good Catches and or near misses.
c. Use and maintain OSHA's Form 300 to log work related injuries and illnesses occurring on the project site for Prime Contractors and subcontractors, and make available to the Contracting Officer upon request. Post and maintain the Form 300A on the work sites.
d. Maintain applicable safety reference material on the job site.
e. Attend pre-work meetings including periodic in-progress meetings.
f. Review the APP and AHAs for compliance and approve, sign, implement and enforce them.
g. Establish a Safety and Occupational Health (SOH) Deficiency Tracking System that lists and monitors outstanding deficiencies until resolution.
h. Ensure subcontractor compliance with safety and health requirements.
i. Maintain a list of hazardous chemicals on site.
j. Maintain a weekly list for review of high hazard activities involving energy, equipment, excavation, entry into confined space, and elevated work at heights, and be prepared to discuss details during management meetings.
k. Provide and keep a record of site safety orientation and indoctrination for all employees including subcontractor employees and site visitors.
Superintendent, Site Manager, QC Manager, and SSHO are subject to dismissal if the above duties are not being effectively carried out and in such cases work will be stopped and will not be allowed to resume until suitable replacements are approved and the above duties are again being effectively carried out.
2.7.2 Employee
Requirements
The Contractor shall provide experienced, qualified, and capable personnel to perform the work in this contract. Personnel shall be fully knowledgeable of all safety, environmental, and energy requirements associated with the work they perform. Personnel shall speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures.
2.7.2.1 Employee Certification
and Training
The Contractor shall maintain personnel certification, training, and licensing records for employee requirements specified herein and within all technical annexes/sub-annexes. Certification, training, and licensing records shall be kept current and on file for the duration of the contract including all option periods. Records shall be made available for Government review within 4 hours of request.
2.7.2.2 Employee Appearance The Contractor shall ensure that all employees present a professional appearance that is appropriate for their position. The KO reserves the right to determine the acceptability of any clothing worn. All Contractor/subcontractor employees working under this contract shall be identified by a distinctive nameplate, emblem, or patch attached in a prominent place on an outer garment. Employee identification shall not be substituted for station required passes or badges.
2.7.2.3 Employee Conduct Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner.
2.7.2.4 Identification as
Contractor Employee Contractor employees shall identify themselves as Contractor personnel by introducing themselves or being introduced as Contractor personnel and displaying distinguishing badges or other visible identification for meetings with Government personnel. All Contractor employees shall appropriately identify themselves as contractor employees in telephone conversations and in formal and informal written correspondence.
2.7.2.5 Removal of Employees The Contractor shall remove from the site any individual whose continued employment is deemed by the KO to be contrary to the public interest or inconsistent with the best interests of National Security.
2.7.2.6 Proof of Legal
Residency
No employee or representative of the Contractor will be admitted to the site of work unless satisfactory Proof of Legal Residency is furnished per Section F.
2.7.3 Enterprise-wide
Contractor Manpower Reporting Application (eCMRA)
The following manpower reporting is required by NMCARS 5237.102.
The Contractor shall report all contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://www.ecmra.mil/
Per Section F, reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk, linked at https://www.ecmra.mil/.
2.8 Security Requirements The Contractor shall comply with all Federal, state, and local security statutes, regulations, and requirements.