Section F – 0200000 Management and Administration
Section F-0200000 Deliveries or Performance
Annex/ Sub-annex Spec Item Report Title Submit To Number of Copies
Due Date/Frequency
0200000 2.2.1 2.2.1.2
Request to Work Outside Government’s Regular Working Hours
KO 1 At least seven calendar days prior to requested day.
0200000 2.3.4 Permits and Licenses
KO 1 Before work commences and as requested by the
KO.
0200000 2.3.5 Certificate of Insurance
KO 1 Within 15 calendar days after award.
0200000 2.5 Samples, MSDS, Manufacturer’s Data Cut Sheets of Materials
KO 1 When requested.
0200000 2.6.1 Work Status Report
KO 1 Within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.
0200000 2.6.2 Notification of Work Scheduling Conflicts due to Government Controls
KO 1 At least seven calendar days prior to work scheduling conflict.
0200000 2.6.3 Phase-in Plan and Phase-out Plan
KO 1 In accordance with the FAR Clause 52.237-3
0200000 2.6.4 Service Interruption Notification
KO, affected tenants, and customers
As required In accordance with local procedures. If due to an emergency, then as soon as practicable.
0200000 2.6.5.1 Quality Control Plan (QCP)
KO 1 Within 15 calendar days after award and within seven calendar days of changes.
0200000 2.6.5.2 QC Inspection File KO 1 As requested and within five calendar days of completion/termina tion of the contract.
0200000 2.6.5.3 Contractor Quality Control / Assessment Report
KO 1 Monthly
N69450-14-R-7610 Amendment 0002 Local Guard Services Page 1 of 5
Jacksonville, Florida
Copies
Due Date/Frequency
0200000 2.6.6 Property Management Plan
KO 4 Within 45 calendar days after award.
0200000 2.6.7 EMS Goals and Policy Measurement Information
KO 1 As requested
0200000 2.6.8 Recovered Material Certification
KO 1 For approval when a product containing recovered materials is equal to or better than the original.
0200000 2.7.1 List of Key Personnel and Qualifications
KO 1 Within 15 calendar days after award.
0200000 2.7.3 Enterprise-wide Contractor Manpower Reporting Application (eCMRA)
KO/Web- Based
Reporting
1 Annually NLT 30 Days after completion of FY.
0200000 2.8.1 Employee List KO 1 Upon request.
0200000 2.8.3 Passes and Badges KO 1 Within 10 calendar days when an employee leaves the Contractor’s service.
0200000 2.8.7 SF-85P and SF-87 Fingerprint Card
KO/
Government
Security Manager
1 Prior to use of Government computers, IT, etc.
0200000 2.9.2 Accident Prevention Plan
(APP)
KO 1 Within 15 calendar days after award and within 15 calendar days of changes.
0200000 2.9.3 Activity Hazard Analysis (AHA)
KO 1 Together with the Accident Prevention Plan and for changes.
0200000 2.9.4 Hazard Specific Safety Plans
KO 1 Together with the Accident Prevention Plan and for changes.
0200000 2.9.5 Accident and Damage Report
KO 1 As soon as practical, but no later than 4 hours after accident.
0200000 2.9.5 Navy Contractor Significant Incident
KO 1 Within one calendar day of
N69450-14-R-7610 Amendment 0002 Local Guard Services Page 2 of 5
Copies
Due Date/Frequency
Report accident.
0200000 2.9.5 Crane and Rigging
Gear Accident Form
KO 1 NLT 30 Days after accident.
0200000 2.9.7 On-Site Labor Report
KO 1 Monthly, by the fifth day of the month.
0200000 2.9.8 OSHA Citations and Violations Corrective Action Report
KO 1 Within 48 hours after receiving a citation.
0200000/ 2.9.10 Safety Certifications
KO 1 Prior to start of work and as old certifications expire.
0200000 2.10 Environmental Management System Goals and Policy Measurement Information
KO 1 When requested.
0200000 2.10.4 Endangered and Threatened Species Discovered Notification
KO 1 Immediately when discovered in the course of work.
0200000 2.10.7 Asbestos Containing Material Notification
KO 1 Verbally within 1 hour and written within 24 hours if ACM is encountered or suspected in the performance of work.
0200000 2.10.8 Sustainable Procurement and Practices Plan
KO 1 Within 15 calendar days after award.
0200000 2.12.1 Water Conservation Plan
KO 1 Within 15 calendar days after award.
0200000 2.13 Notification to the Government for Work Above the FFP Limitations
KO 1 Within two hours of identification
0200000 2.15.1.1 IDIQ Quantities Ordered Via EMALL Report
KO 1 Monthly
0200000 2.15.1.2 Consolidated IDIQ Invoice
KO 1 Monthly for IDIQ work completed during the preceding month.
0200000 2.15.2.1 IDIQ Proposal KO 1 Within two
N69450-14-R-7610 Amendment 0002 Local Guard Services Page 3 of 5
Copies
Due Date/Frequency working days after Government's Request for Proposal.
N69450-14-R-7610 Amendment 0002 Local Guard Services Page 4 of 5
Section F – 0401060 Security Operations
Section F-0401060
Annex/
Sub-annex Spec Item Report Title Number of
Copies Submit To Due
Date/Frequency 0401060 2.12.3 Physical
Examinations 1 COR/KO Upon Request.
0401060 2.12.4 Physical Fitness Test Records
1 COR KO Upon Request
0401060 2.12.7 Drug Screening and Testing Reports
1 COR/KO Upon Request
0401060 2.12.8 Training Plan 1 COR/KO Within 10 days after contract award.
0401060 2.13 Firearm Licensing and Permit Documentation
1 COR/KO Before work commences and upon request.
0401060 3.2.2.1 Building Check Sheets, Tapes, and Reports from Scanners and Key Stations
1 COR/KO By 0900 the following work day
N69450-14-R-7610 Amendment 0002 Local Guard Services Page 5 of 5