Copy of Industry Feedback_Final RFP ASE Working Copy v04.xlsx
XLSX spreadsheet 40 KB Posted
- Solicitation number
- N6852022R0029
About this file
This is a request for proposal for maintenance, repair, overhaul, and logistics support services for the Fleet Readiness Center, Aviation Support Equipment. The Navy intends to award a single-source indefinite-delivery/indefinite-quantity contract for the required services over a three-year ordering period to an 8(a) small business. The incumbent contractor is Amentum Services, LLC. Interested 8(a) firms must submit questions by 15 November 2022 and final proposals by 5 December 2022 through the Procurement Integrated Enterprise Environment system. The services include maintenance, repair, and overhaul of engines, components, and equipment across multiple industrial sites. A statement of work further outlines specific requirements.
View the file
Other files
Show all 49
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions
General Information
| Solicitation Number: | N6852022R0029 |
| Question(s) for Draft or Final: | Final |
| # | Document | |||||
| (RFP, Attachment) | Section | |||||
| (A-M) | Reference Paragraph | Page Number | Question | Proprietary (Yes/No) | Answer | |
| 1 | RFP | C | 3.16.2.3 | 35 | The Contractor shall utilize Government provided vehicles for the transportation of equipment and materials in support of this Contract. The cost of equipment and materials transport vehicles supporting SOW requirements for the Contractor will not be considered as an allowable direct cost in the performance of the Contract. |
| Q: Are there currently any contractor provided vehicles in use or required in support of this contract, and if so, will the Government please provide a list of all contractor provided vehicles/equipment in use? | No | Contractor provided vehicles are not required or authorized for the transportation of equipment and materials in support of this contract. |
| 2 | RFP |
and
| Attachment 15 | C | ||
| 4.3.6.2 | 56 | The Position of Administrative Assistant is indicated at JRBFWTX on Attachment 15 and in the hours on L-4, but that position is not indicated as a work location in the RFP. |
| Q: Will the Government please indicate which of the Attachments is correct and update the RFP and other Attachment accordingly? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 3 | RFP |
and Attachments L-3, L-4 &15 C 4.3.6.2 and multiple tabs/pages 56 The RFP lists nine (9) locations for Administrative Assistant, but Attachments L-3, L-4 & 15 indicate 10 locations.
| Q: Will the Government please clarify locations for the administrative assistant and update the RFP and/or Attachments accordingly? | No | The labor category location has been identified. The Government has updated the RFP. Please see the amended RFP. |
| 4 | RFP |
and Attachment 15 and
| L-4 Vol 3 Hours | C | ||
| 4.3.6.23 | 63 | The RFP shows Site Supervisor Work Locations at BIC, BFT, CPNC, JAX, JRBFWTX, NOLA, NBC, and ELCEN. Site Supervisors are not marked in Attachments 15 and L-4. It is our understanding that there are currently 4 Site Supervisors. |
| Q: Will the Government please clarify the work locations for Site Supervisors, the total number of required Site Supervisors, and update the documents accordingly? | No | The labor category location has been identified. The Government has updated the RFP. Please see the amended RFP. |
| 5 | RFP |
and Attachment 15 and L-4 Vol 3 Hours C 4.3.6.25 63 Supply Technician FTE and Hours for SERF LMR are on Attachments 15 and L-4; however, SERF LMR is not included as a work location for this position in the RFP.
| Q: Will the Government please clarify the work locations for this position and update the documents accordingly? | No | A Supply Technician is required at work location LMR. Please see the amended RFP. | ||||
| 6 | Attachment L-4 | N/A | N/A | N/A | The hours listed for Administrative Assistant at BFT is 7,680; however, Attachment 15 indicates one (1) FTE. |
| Q: Will the Government please confirm that the hours are 7,680? If so, to what Ordering Year/Ext Period is the Offeror to add the additional 960 hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 7 | RFP |
and Attachment 15 and Attachments L-3, L-4 C 4.3.6.3 and multiple tabs/pages 56 The RFP lists 10 locations for Aerospace Structural Welder, but Attachments L-3, L-4 & 15 indicate 9 locations.
| Q: Will the Government please update the RFP and/or Attachments so they all match? | No | There is no requirement for an Aerospace Structural Welder at work location CHT. Please see the amended RFP. |
| 8 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are no hours for Stock Clerk at CHT in Attachment L-4; however, Attachment 15 indicates one (1) FTE.
| Q: Will the Government please confirm a Stock Clerk is required at CHT and update Attachment L-4 with the required hours? | No | Yes, a Stock Clerk is required at CHT. Please see the amended RFP. | ||
| 9 | Attahment L-3 | |||
| Attachment 15 | N/A | N/A | N/A | A Stock Clerk is Listed at CPNC on Attachment 3 but not on Attachment 15. |
| Q:Will the government please clarify whether a stock clerk is required at CPNC and update the Attachments accordingly? | No | There is no requirement for a Stock Clerk at work location CPNC. |
| 10 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Tech Order Librarian at CHT in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please clarify whether a Tech Order Librarian is located at CHT and update the attachments accordingly? | No | There is no requirement for a Tech Order Librarian at work location CHT. |
| 11 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Site Supervisor at CPNC in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please clarify whether a Site Supervisor is located at CPNC and update the attachments accordingly? | No | There is no requirement for a Site Supervisor at work location CPNC. |
| 12 | Attachment L-4 |
and Attachment 15 N/A N/A N/A The hours listed for Administrative Assistant at JAX in Attachment L-4 are 7,680; however, Attachment 15 indicates one (1) FTE.
Q:
1) Will the Government please confirm that the hours are 7,680?
| 2) If so, to what Ordering Year/Ext Period is the Offeror to add the additional 960 hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 13 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are no hours for Ground Support Equipment (GSE) Mechanic at JAX in Attachment L-4; however, Attachment 15 indicates eleven (11) FTEs.
| Q: Will the Government please update Attachment L-4 to account for the hours required? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 14 | Attachment L-4 |
and Attachment 15 N/A N/A N/A The hours listed for Ground Support Equipment (GSE) Worker at JAX in Attachment L-4 is 73,920; however, Attachment 15 indicates only two (2) FTEs.
| Q: Will the Government please update the Attachments to match? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 15 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are no hours for Production Control Clerk at JAX in Attachment L-4; however, Attachment 15 indicates one (1) FTE.
| Q:Will the Government please update Attachment L-4 to account for the hours required? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 16 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are no hours for Supply Technician at JAX in Attachment L-4; however, Attachment 15 indicates one (1) FTE.
| Q: Will the Government please update Attachment L-4 to account for the hours required? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 17 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Machinery Maintenance Mechanic at JAX in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update Attachment L-4 to remove these hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 18 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Program / Operations Manager at JAX in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update Attachment L-4 to remove these hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 19 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Tech Order Librarian at JAX in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update Attachment L-4 to remove these hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 20 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are no hours for Ground Support Equipment (GSE) Mechanic at JRB FWTX in Attachment L-4; however, Attachment 15 indicates eleven (11) FTEs.
| Q: Will the Government please update Attachment L-4 to account for the hours required? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 21 | Attachment L-4 |
and Attachment 15 N/A N/A N/A The hours listed for Ground Support Equipment (GSE) Worker at JRB FWTX in Attachment L-4 are 73,920; however, Attachment 15 indicates only three (3) FTEs.
| Q: Will the Government please update the Attachments to match? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 22 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are no hours for Production Control Clerk at JRB FWTX in Attachment L-4; however, Attachment 15 indicates one (1) FTE.
| Q: Will the Government please update Attachment L-4 to account for the hours required? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 23 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are no hours for Supply Technician at JRB FWTX in Attachment L-4; however, Attachment 15 indicates one (1) FTE.
| Q: Will the Government please update Attachment L-4 to account for the hours required? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 24 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Machinery Maintenance Mechanic at JRB FWTX in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update Attachment L-4 to remove these hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 25 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Program / Operations Manager at JRB FWTX in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update Attachment L-4 to remove these hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 26 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Tech Order Librarian at JRB FWTX in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update Attachment L-4 to remove these hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 27 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Ground Support Equipment (GSE) Mechanic (Site Lead) at NNSY in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update Attachment L-4 to remove these hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 28 | Attachment L-4 |
and Attachment 15 N/A N/A N/A The hours listed for Material Coordinator (Hazard / Non Hazard) at NNSY in Attachment L-4 is 960; however, Attachment 15 indicates one (1) FTE.
| Q: Will the Government please update the Attachments to match? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 29 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Tech Order Librarian at NOLA in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update Attachment L-4 to remove these hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 30 | Attachment L-4 |
and Attachment 15 N/A N/A N/A The hours listed for Painter, Automotive at SERF NTHI in Attachment L-4 are 26,880 (14 FTE); however, Attachment 15 indicates five (5) FTEs (9,600 hrs).
| Q: Will the Government please update the Attachments to match? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 31 | Attachment L-4 |
and Attachment 15 N/A N/A N/A There are hours for Ground Support Equipment (GSE) Mechanic (Site Lead) at NBC in Attachment L-4; however, Attachment 15 indicates zero (0) FTEs.
| Q: Will the Government please update the Attachments to match? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 32 | Attachment L-4 |
and Attachment 15 N/A N/A N/A The hours listed for Site Supervisor at SOLM in Attachment L-4 is 13,440 (7 FTEs); however, Attachment 15 indicates two (2) FTEs.
| Q: Will the Government please update the Attachments to match? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||||
| 33 | Attachment L-4 | N/A | N/A | N/A | The total hours for SOLM do not match the SUM of the column. |
| Q: Will the Government please update SOLM column to show the correct individual and sum hours? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents |
| 34 | RFP |
and Attachment 15 and Attachment L-4 C 4.3.6.26 64 FTEs are listed for Technical Librarian in three locations on Attachment 15 (NNSY,NBC, SOLM), L-4 has hours for 7 locations (CHT, JAX, FWTX, NNSY, NOLA, NBC, and SOLM) , The RFP has 4 locations (NNSY, NOLA, NBC & SOLM.
| Q:Will the government please update the documents and provide the correct location, FTE, and hours so all documents match. | No | The Government has updated the RFP. Please see the amended RFP. |
| 35 | RFP |
and Attachment 15 and Attachments L-3, L-4 C 4.3.6.18 and multiple tabs/pages 61 The RFP lists six (6) locations for Painter, Automotive, but Attachments L-3, L-4 & 15 indicate nine (9) locations.
| Q: Will the Government please update the RFP and/or Attachments so they all match? | No | The Government has updated the RFP. Please see the amended RFP. |
| 36 | RFP |
and Attachment 15 and Attachments L-3, L-4 C 4.3.6.23 63 The RFP lists ten (10) locations for Site Supervisor, but Attachments L-3 & 15 indicate three (3) locations and L-4 indicates four (4) locations.
| Q: Will the Government please update the RFP and/or Attachments so they all match? | No | The Government has updated the RFP. Please see the amended RFP. |
| 37 | RFP |
and Attachment 15 and Attachments L-3, L-4 C 4.3.6.24 63 The RFP lists eleven (11) locations for Supply Technician, but Attachments L-3 & 15 indicate twelve (12) locations and L-4 indicates ten (10) locations.
| Q: Will the Government please update the RFP and/or Attachments so they all match? | No | The Government has updated the RFP. Please see the amended RFP. |
| 38 | RFP |
and Attachment 15 and Attachments L-3, L-4 C 4.3.6.25 64 The RFP lists four (4) locations for Technical Publication Librarian (TPL) Clerk, but Attachments L-3 & 15 indicate three (3) locations, and L-4 indicates seven (7) locations.
| Q: Will the Government please update the RFP and/or Attachments so they all match? | No | The Government has updated the RFP. Please see the amended RFP. |
| 39 | RFP |
and Attachment 15 and Attachments L-3, L-4 C 4.3.6.8 58 The RFP shows 7 locations for Ground Support Equipment (GSE) Site Lead (BIC, BFT, CPNC, JAX, JRBFWTX, LMR, EL Cen), Attachment L-4 has hours for 9 locations (BIC, BFT, CPNC, JAX, JRBFWTX, LMR, NNSY, NBC, EL Cen), and Attachment 15 has FTEs at 7 locations (BIC, BFT, CPNC, JAX, JRBFWTX, LMR, and El Cen).
Q:
1) Will the Government please clarify which is correct?
| 2) L-4 has 1920 hours for NNSY, will the Government please clarify which year those hours apply to? | No | Attachment L-4 has been updated. Please see the amended RFP | ||||
| 40 | Questions+Industry+All+Questions+Finalized | N/A | Questions 37 & 38 | N/A | Per the Government's answer, the Order Clerk and Order Filler are to be considered as SCA if not listed in a CBA wage table. However, the WDs provided with the Solicitation do not include these Occupation Codes/Titles. |
| Q: Will the Government please release an updated WD that includes the 01192 - Order Clerk II and 21071 - Order Filler wages the Offeror is to use for these two positions? | No | The Government has added an additional Wage Determination. Please view the updated Section J and RFP. | ||||
| 41 | RFP | L | 3.3(c) | 135 | The RFP states escalation is to be applied to the Option to Extend; however, per FAR 52.217-8 the continued performance of any services are within the limits and rates specified in the contract. |
| Q: Will the Government please amend the RFP to remove the escalation requirement on the Option to Extend? | No | The Government will apply escalation as stated in accordance with Section L, Part B, Volume 3, Paragraph 3.3 Cost/Price Information in order to establish a Most Probable Cost to the Government. | ||||||
| 42 | RFP, Amend 0001 | A | SF33, Box 9 | 1 | Due to the two major holidays included in this proposal response timeframe (Veteran's Day and Thanksgiving), and the disruption caused by these non-working holidays, will the Government please extend the due date to 12 December? | No | The Government will extend the proposal due date to 03 January 2023 at 1400 EST to take the holiday and the Q&A process into consideration. | |
| 43 | RFP | L | 2.3 | 125 | A post on 10 November 2022 to SAM.gov stated "Interested parties may submit questions using the Enclosure (1) “Industry Worksheet” Excel file no later than 2:00 PM Eastern Standard Time (EST) on 15 November 2022", however, per Section 2.3 of the solicitation instructions, "questions must be submitted ...no later than 12:00pm on the 14th calendar day after the date that the solicitation is issued." The SF33 is dated 3 November, therefore 14 calendar days from that date is 17 November. |
| Q: Will the Government please extend the due date for questions to 17 November to allow offerors to identify areas that need to be clarified? | No | The Government will extend the due date of the RFP question submission to 25 November 2022 at 1400 EST. |
| 44 | Questions+Industry+All+Questions+Finalized |
and RFP L Questions and Answers #s 61-64 and Part B Instructions for Proposal Content and Volumes N/A and 125 The answer to questions 61-64 stated The "Suggested Page" Count is provided as a guide, only, and is not a required maximum page count.
| Q: Will the Government please clarify whether an offeror will be removed from competition, negatively affected during evaluation, or otherwise penalized during evaluation if they exceed the suggested page count (i.e., using 30 pages instead of 20 for the Technical Response)? | No | The suggested page count is the number of pages the Government believes is needed to answer the question sufficiently. As this is a suggested page count the Offeror will not be removed from the competition for going over the page count. The Government does ask that the contractor succintly and efficiently answer instructions for offerors (Section L - Instructions, Conditions and Notices to Bidders) and stay as close to the page count as possible. | 1 | |||
| 45 | RFP | L | Section 3, para. 2 | 126 | Information submitted as an Annex to a particular proposal volume could include manuals, specifications, plans, procedures, and company policies, as well as other information requested in “Part B Specific Instructions” do not count towards the suggested page count. |
Q:
1) Will the Government please confirm our understanding that we may use an Annex "B" as a separate electronic file to provide additional information related to our Volume 2 Technical response?
| 2) Will the Government please clarify what restrictions exist for providing additional information in our "Annex B" aside from the prohibition of cost information and large-file graphics? | No | The Government confirms that information submitted as an Annex to a particular proposal volume could include manuals, specifications, plans, procedures, and company policies, as well as other information requested in “Part B Specific Instructions” do not count towards the suggested page count. Additional information submitted must follow what is requested within Part B Specific Instructions. Offerors are encouraged to follow the suggested page count and to only submit information in accordance with the solicitation. | ||||||
| 46 | RFP | |||||||
| Answers to Questions Draft | C | Question and Answers 66 | ||||||
| Para 3.15.2.2 | NA | |||||||
| The government responded to the question regarding the Quality Assurance Specialist (QAS) referenced in 3.15.2.1 as follows "The Statement of Work has been updated to incorporate the QAR. Please see SOW Section 3.15.2.2." | ||||||||
| Question: Section 3.15.2.2 still references a QAS. Does the government view the position of QAS to be the same as the Quality Assurance Reprsentatives (QARs). If yes can the government please update the PWS for consistency. If no will the government please define the role of the QAS and add the position to Attachment 15. | No | Please see the amended RFP. The Government is utilizing the Quality Assurance Representative (QAR) verbiage. | ||||||
| 47 | RFP | C | Quality Program | 33 | Does the government require a Dedicated Contractor Quality Assurance Lead in support of this contract. If yes will the government please add the position to Attachmet 15. | No | No, the Government does not require a Dedicated Quality Assurance Lead in support of this contract. | |
| 48 | Attachmnet 15 | NA | NA | NA | ||||
| Within the final FRCASE MRO and Logistics RFP documentation, Attachment 15 – Team Complement Table all FRCASE MRO and Logistics support labor categories for this solicitation are provided. The incumbent LTM INC (page 138 para 3.4.3) logistics support resides in Solomons and is exempt from the Union CBA. These exempt positions have Labor Categories that are not addressed within Attachment 15 nor defined in paragraph 4.0 (Labor Categories) within the Final RFP document . Will the government consider adding these unique labor categories for logistics and related engineering support for SE. | No | As stated in Section C of the Statement of Work, the Government's Labor Categories are provided. | ||||||
| 49 | Attachment 16 | J | NA | 111 | Section J indicates Attachment 16 Quality Assurance Surveillance Plan and a page count of 12. Attachment 16 does not appear to have been included as part of the attached documents. Will the Gov't please provide Attachment 16 QASP? | No | Attachment 16 has been provided via Amendment 0001 on PIEE and SAM. | |
| 50 | RFP | B | IDIQ MIN/MAX | 10 | Per the Contract Min/Max Quantity and Contract Value, there are Maximum hours of 3,570,0000. However, clause 5252.211-9503 on page 11 lists 3,565,440 hours. Will the Government please confirm and update the RFP to reflect the max hours under this IDIQ? | No | The Government has amended the RFP. The total hours for this solicitation are 3,548,160.00 | |
| 51 | Attachments L-4 & 15 | N/A | N/A | N/A | Attachments L-4 & 15 lists a Forklift Operator with zero hours allocated. Will the Government please update the Attachments adding the hours required? | No | The Forklift Operator line has been deleted. Please see the updated Attachment 15 and L-4. | |
| 52 | RFP Amendment 0001 | L | 3.4.2. Labor Hours | 20 of 21 | As per RFP Section L.3.4.2, a work year is defined as 1,920 hours and bidders are directed not to deviate from the labor categories or the hours associated to each labor category at each site. Table 4.1.1 as stated in the RFP provides the historical minimum FTEs per site. However, a calculation using the RFP specified work year of 1,920 hours multiplied by 3 years and the total numbers of FTEs on this table does not result in the same LOE presented at RFP Attachment L-4_Vol_3 Hours Table. Can the Government please confirm that this table is provided for information purposes only to delineate union versus non-union locations and that all bidders are to propose the LOE and Labor Categories per site location as presented at Attachment L-4 with no deviations? | No | The Government has amended the RFP and the relevant attachments. | |
| 53 | RFP | J | Attachment 15 | 111 of 150 | The total number of hours for the SOLM reflects an incorrect total. Hour calculations for this site equal 1,256,640 versus 1,249,920. Currently the LOE presented in this attachment is stated as 3,565,440 but totals 3,558,720. Request the Government provide a correction to the total for this site? | No | The Government has amended the RFP. The total hours for this solicitation are 3,548,160.00 | |
| 54 | RFP Amendment 0001 | L | 3.3( c ) | 16 of 21 | Can the Government confirm our understanding that the Area Wage Determinations as referenced above are the same Wage Determinations provided at RFP Attachments 7 and 8 and that bidders are required to propose WD direct labor rates at a minimum using the Wage Determined rates provided at Attachments 7 and 8? | No | Yes, the Offeror cannot propose a lower rate than what is listed in the AWD. "The Offeror shall (be used as a basis) propose in compliance at a minimum, with the current hourly rate set forth in the Area Wage Determination or CBA as applicable." | |
| 55 | Attachment 13 LOE Chart B-1 Vol 1 FBL | J | Instructions | Worksheet 1 | The first worksheet in Attachment 13 workbook is labeled as “Instructions” however there are no instructions provided. Can the Government provide instructions or confirm that this worksheet will be deleted from the workbook? | No | Please see the updated Attachment 13. | |
| 56 | RFP Amendment 0001 | L | 3.4.2. Labor Hours | 20 of 21 | The instructions presented at RFP Attachment L-2, worksheet entitled, “Instructions” state that the Offeror is not required to utilize the Government's labor categories, however, each proposed labor category should appear opposite of the government labor category it is comparable to. The language on Attachment L-2 conflicts with L.3.4.2 which requires bidder to not deviate from the labor categories or the hours associated to each labor category at each site. Can the Government provide a revision to correct this discrepancy? | No | Attachment L-2 was updated with new verbiage and will be released with Amendment 0002 | |
| 57 | Attachment L-2_Vol3_CSS | J | N/A | N/A | Can this workbook be modified to add worksheets to provide pricing for each of the fourteen sites identified in the RFP that can then be rolled into a Total Cost Summary? | No | In Attachment L-2_CSS, the Instructions state only one worksheet shall be prepared for the entire period of performance (for each Prime and Subcontractor). In Column E, the Offeror shall insert the location where the work will be performed utilizing the correct location acronyms (i.e BIC (Blount Island), BFT (Beaufort), SOLM (Solomons Islands) per Section C of the Statement of Work. | |
| 58 | RFP Amendment 0001 | L | 3.3(i) | 18 of 21 | Can the Government review the instruction at L.3.3(i) as it appears to conflict with Section M. Are Offerors required to bid 5% or higher escalation or is an explanation provided as to why there is a deviation sufficient not to have a bidders proposal adjusted to include 5% escalation? | No | If an Offeror submits an escalation rate lower that 5%, that will be deemed unrealistically low and adjusted to a minimum of 5%. An Offeror may propose an escalation rate higher than 5% if desired. | |
| 59 | RFP | B | B.1(1) | 4 of 150 | Will the Government amend this paragraph as it appears to refer to an incorrect attachment? Section J, Attachment 15 is currently labeled and presents the Team Complement Table versus Composite Labor Rates. | No | Please see the amended RFP. The correct Attachment number is 13. | |
| 60 | Attachment 13 | Column D | Assuming this attachment is actually intended to present the bidders proposed Composite Rates per year, can the Government please provide an explanation as to what Column D entitled, Individual Designator* is to be utilized for? | No | Please see the updated instructions in Attachment 13. | |||
| 61 | Attachment L-4 and Attachment 5 Solomons Island CBA Amentum | J | N/A | N/A | Attachment 5 CBA list a wage rate for Quality Control Inspector (QCI). Attachment L-4 does not reflect a labor category with this same nomenclature. Additionally, Attachment 5 CBA provides a wage rate for a Forklift Operator. However, Attachment L-4 assigns no level of effort (LOE) for this labor category at this site. Is there a requirement for the Government to amend the RFP to include the QCI labor category and assign LOE for this site? Should labor hours also be assigned for the Forklift Operator at this site? | No | The updated Attachment L-4 are the labor categories assigned for this solictation. | |
| 62 | Attachment L-4_Vol_3_Hour Locations | J | N/A | N/A | Attachment 6 provides labor rates for both a Ground Support Equipment Mechanic CDI and a Ground Support Equipment Mechanic. Attachment L-4 provides only total hours for a Ground Support Equipment Mechanic. Can the Government provide the number of labor hours that will be required for the Ground Support Equipment Mechanic CDI position? | No | The updated Attachment L-4 are the labor categories assigned for this solictation. | |
| 63 | Attachment L-4_Vol_3_Hour Locations | J | N/A | N/A | Attachment 6 provides a labor rate for both an Aerospace Structural Welder and Aircraft Mechanic II (NDI) at this site. However, Attachment L-4 does not provide LOE for either labor category. Can the Government confirm that there is no requirement for these positions at the Lemoore site? | No | There is no requirement for an Aerospace Structural Welder and Aircraft Mechanic II at the Lemoore site. | |
| 64 | Attachments 4 through 6, RFP CBAs | J | N/A | N/A | In each of the RFP CBA attachments, the CBA specifies that employees performing in certain capacities will be paid premium pay above the labor rate cited to be paid for the labor category. Can the Government firm that all bidders should include these premiums in the costing of this effort in order to complete a consistent evaluation of the cost proposal submissions. | No | As stated in Section A, Paragraph #2, The cost/price proposal shall demonstrate compliance with the minimum monetary wages and fringe benefits for service employees as specified in the Wage Determination or Collective Bargaining Agreement, as applicable. | |
| 65 | Attachment 6 Lemoore FRC ASE CBA/Article 8.0 | J | N/A | N/A | The CBA for the Lemoore site requires employees be paid 12 holidays versus the 11 that are in the RFP. The additional holiday provided is the day after Thanksgiving. Can the Government revise the RFP to include this holiday so that the awardee can support charging the holiday to contract after award? | No | The Offerors are advised to follow the Holiday Schedule per the CBA at each site. | |
| 66 | Vol 1 - Executive Summary | L | 1.3(d) | 128 | Item d provides that SF33 or SF1449 for basic solicitation and acknowledgement of each amendment, including completion of any RFP clause or provision that requires a fill-in response and that Signed Representations and Certification, and acknowledgements and/or SAM be included as part of the Volume 1 - Executive Summary response. Please provide concurrence that this section is excluded from the 15 pages that are suggested. | No | The Volume 1 - Executive Summary is not excluded from the 15 page that are suggested. However, the suggested page count is the number of pages the Government believes is needed to answer the question sufficiently. As this is a suggested page count the Offeror will not be removed from the competition for going over the page count. The Government does ask that the contractor succintly and efficiently answer instructions for offerors (Section L- Instructions, Conditions and Notices to Bidders) and stay as close to the page count as possible. | |
| 67 | Solicitation - Amendment 0001 | L | 3 | 7 | Table G-3 Proposal Structure, provided suggested pages for Volume/Annex. If an offeror exceeds page count, will those pages still be evaluated? | No | The suggested page count is the number of pages the Government believes is needed to answer the question sufficicnetly. As this is a suggested page count the Offeror will not be removed from the competition for going over the page count. The Government does ask that the contractor succintly and efficiently answer questions for offerors (Section L - Instructions, Conditions and Notices to Bidders) and stay as close to the page count as possible. | |
| 68 | Attachment 13 | Multiple tabs include a "*** Site Supervisor", what does the "***" represent? | No | Please see the updated Attachment 15. | ||||
| 69 | RFP | Section L | 2.1.1.d | 129 | Section L, Overall Management Approach, paragraph 2.1.1.d, instructs, "The Offeror shall provide an overview of its previous experience...". DISCUSSION: Section L, Part A, I. General, defines "Offeror" as "the prime contractor with its CAGE code identified in Block 15A" on the SF33 form. Based on this, JV team members and principal subcontractors would be excluded from the discussion of previous experience. However, these principal entities will perform major or critical aspects of the requirement so it would make sense to evaluate their corporate experience as well. RECOMMENDATION: Recommend that the experience narrative shall take into account the experience of the principal entities, which will perform major or critical aspects of the requirement, consistent with 13 CFR § 125.8(e) and FAR 15.305(a)(2)(iii). SUGGESTED RE-WORDING: "The Offeror shall provide an overview of the previous experience of the principal entities..." | No | The Government intends to evaluate the JV itself and all of the JV partners. The Government will evaluate the prime contractor and any subcontractor that provides over 20% of the total proposed cost. | |
| 70 | RFP - AMD 0001 | SF 33 | Block 9 | 1 | The due date for the proposal is 05 December NLT 2:00 P.M. EST. | |||
| DISCUSSION: Because questions are due NLT Tuesday November 15th and with the amount of time it will take for the Government to answer all questions, as well as the time it will take for Offeror's to correct their proposals as a result of answers to questions, along with the Thanksgiving holiday, Offeror's will need more time to develop their proposals. RECOMMENDATION: Recommend that the Government extend the proposal by two weeks to Tuesday December 20th, 2022 NLT 2PM EST to allow sufficient time for Offeror's to prepare and revise their proposals. | No | The Government will extend the proposal due date to 03 January 2023 to take the holiday and the Q&A process into consideration. | ||||||
| 71 | RFP | Section C | 3.27 | 40 | DISCUSSION: Section C, paragraph 3.27MRO Corrosion Maintenance states, "The Contractor shall prepare all surfaces for painting and paint using materials, application methods, and procedures set forth in the appropriate maintenance instruction manuals." QUESTION: Does the preparation of surfaces include processes such as the use of media blasting? | No | Yes, the preparation of surfaces includes processes such as scuffing, sanding, and abrasive media blasting. | |
| 72 | RFP | Section C | 3.14.3.1 Personal Protective Equipment / 3.14.3.6 | 30 | DISCUSSION: Contractor personnel shall be familiar with the location and operation of firefighting equipment available in and around FRCASE work locations. Contractor personnel shall be |
familiar with safety equipment (i.e. Automatic External Defibrillator) available in and around FRCASE work locations. Fire lanes shall be kept clear of equipment.
| QUESTION: Does everyone need to be CPD/AED certified? | No | No, there is not a requirement for every person to be CPR/AED Certified. However, it is the offerors responsibility to ensure all employees are familiar with all safety equipment. | ||||||
| 73 | RFP | Section C | 3.14.3.1 Personal Protective Equipment. | 30 | As this indicated that PPE for employees is at the Contractor's expense, is this cost included in the ODC Material plugged figure provided by the Govt.? | No | PPE for contractor employees is a Contractor's expense and is not included in the ODC Material figure. | |
| 74 | RFP | Section C | 3.14.3.2 Gas Free Engineering | 30 | Is the cost to maintain this program included in the ODC Material plugged figure provided by the Govt.? | No | The cost to maintain the requirement at SOW 3.14.3.2 shall be a labor expense not an ODC Material expense. The Contractor is responsible for maintenance of gas-free test equipment and tank safety certification IAW Ground Operating Procedures prior to contractor personnel entering enclosed spaces. The Government will provide all gas-free certification consumables and equipment. | |
| 75 | RFP and Attachment 15 | 3.14.3.4 Tool Control Program, 3.17 Hand Tools and Attachment 15 | 31,37 | 3.17 indicates the contractor shall provide all tools with adequate safeguards, however Attachment 15 only includes a Tool and Parts Attendant labor category at 6 of the 14 locations. Would the Govt. please indicate its intention for the other 8 locations without this labor category? | No | Due to the volume of parts, material, and GFE that must be maintained, controlled, and issued to contractor personnel performing maintenance on engines, components, and equipment at the larger sites, Tools and Parts Attendants are only required at three locations: NNSY, NBC, and SOLM. All other locations do not require Tools and Parts Attendants. Paragraph 3.17 refers to management of contractor-owned hand tools only. | ||
| 76 | RFP | Section M | B. Cost/Price General | 147 | RFP indicated that if an offeror proposes less than the median seniority level for any CBA labor category, the Govt. will adjust that rate up to the median level. As the CBA documents currently do not include different wages based on seniority level, would the government please clarify how they would adjust the rates? | No | Even though the CBAs do not include different wages based on seniority level, all Offerors shall assume all employees, for any CBA Labor Category, at the median (3 years but less than 8 years) seniority/years of service level. If the Offeror proposes seniority/years of service for any CBA Labor Category of less than the median (3 years but less than 8 years.) seniority level, the Government will adjust that rate up to the median level rate. | |
| 77 | RFP | Section C | 3.4.2 Labor Hours, 3.3 Cost/Price Information | 138,135 | The Govt provided a work year of 1920 but also indicated to assume 3-8 years seniority. The CBA documents above 5 years include a higher vacation accrual than 80 hours assumed in the 1920 calculation. Would the Government please clarify the purpose of the seniority statement in relation to the man year? | No | The Government's purpose of the seniority statement in relation to the man year is to ensure all offerors have the same information for proposal development purposes. The Government will be utilizing the median seniority/years of service for proposal evaluation purposes. | |
| 78 | RFP | N/A | Section L.3.4.1 ODCs and |
RFP Reference: Attachment L-2_Vol_3_CSS and
| RFP Reference: Attachment L-4_Vol_3_Hour Locations | 138 | In order to price hours by Ordering Years as required in RFP Attachment L-2 Cost Summary, can the Government revise Attachment L-4 to designate LOE by labor category/location of each Ordering Year consistent with the ODCs that are to be estimated for each Ordering Period in Attachment L-2 Cost Summary? | No | The Government has updated Attachment L-4. Please see the amended documents. However, the Government did not break out by Ordering Year in Attachment L-4 as Attachment L-2 breaks down by Ordering Year. | |||||
| 79 | RFP | N/A | Attachment L-4_Vol_3_Hour Locations and | ||||||
| Section M.5.II.B EVALUATION OF OPTIONS/TOTAL EVALUATED PRICE | 148 | Can the Government confirm that Offerors are not required to break out LOE by labor category on Attachment L-4 Cost Summary and that it will be acceptable to provide only total cost for the 6 month extension period in accordance with Section M evaluation criteria? If this is not acceptable, can the Government revise Attachment L-4 to include LOE by site and labor category for each Ordering Year and also the 6-month extension period that is to be priced? | No | The Offerors are required to break out the labor category on Attachment L-2 which includes all ordering periods including the 6-mo extension. | |||||
| 80 | RFP | L | 2.1.1 Overall Management Approach, Item d.i. | 11 | In the spirt of an 8(a) competition, and in order to receive qualified offerors proposals, would the Government please reconsider Item d.i., which states that Offerors shall provide an overview of its previous experience… specifically "Managing a large services contract across multiple industrial MRO sites with a skilled labor workforce in excess of 400 artisans. | No | As stated in Section M, II (A), "Note that for paragraph 2.1(d), the Government will evaluate previous experience in terms of risk, with the assessment being incorporated into the overall Technical factor evaluation. " | ||
| 81 | RFP | L | 2.1.1 Overall Management Approach, Item d.i. | 11 | Similar to the above question, if the Government will not reconsider this item: "Managaging a large services contract across muliple industrial MRO sites with a skilled labor workforce in excess of 400 artisans. Respectfully, would the Government consider updating at a minimum to consider management of a workforce in excess of 400 artisans on mutiple contracts (that are concurrently active) as a demonstration of experience as it relates to MRO and Logistics Support? | No | As stated in Section M, II (A), "Note that for paragraph 2.1(d), the Government will evaluate previous experience in terms of risk, with the assessment being incorporated into the overall Technical factor evaluation. " | ||
| 82 | Attachment L-3 & Attachment 13 Tab CHT | L | 3.4.2 | 138 | Attachment L-3 AFBL and Attachment 13 CHT Tab lists labor categories for Stock Clerk and Supply Technician. However, Attachment L-4 Vol 3 Hours Column F CHT lists hours for labor category Supply Technician and Tech Order Librarian. What labor categories are to be priced in Attachment L-3, Stock Clerk/Supply Tech or Supply Tech/Tech Order Librarian? Request the government correct all Attachments so they match. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 83 | Attachment L-3 & Attachment 13 Tab CPNC | L | 3.4.2 | 138 | Attachment L-3 AFBL and Attachment 13 CPNC Tab labor categories correlate to Attachment L-4 Vol 3 labor categories except for Stock Clerk (Attch 3) and Production Control Clerk and Site Supervisor (Attch 4). Which Attachment is correct? Request the government correct all Attachments so they match. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 84 | Attachment L-3 & Attachment 13 Tab JAX | L | 3.4.2 | 138 | Attachment L-3 AFBL and Attachment 13 JAX Tab labor categories don't correlate to Attachment L-4 Vol 3 labor categories. Attch L-3 and Attch L-4 labor category disparities exist. Which Attachment is correct? Request the government correct all Attachments so they match. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 85 | Attachment L-3 & Attachment 13 Tab JRBFTW | L | 3.4.2 | 138 | Attachment L-3 AFBL and Attachment 13 JRBFTW Tab labor categories don't correlate to Attachment L-4 Vol 3 labor categories. Attch L-3 and Attch L-4 labor category disparities exist. Which Attachment is correct? Request the government correct all Attachments so they match. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 86 | Attachment L-3 & Attachment 13 Tab NNSY | L | 3.4.2 | 138 | Attachment L-3 AFBL and Attachment 13 NNSY Tab labor categories don't correlate to Attachment L-4 Vol 3 labor categories. Attch L-3 and Attch L-4 labor category disparities exist. Which Attachment is correct? Request the government correct all Attachments so they match. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 87 | Attachment L-3 & Attachment 13 Tab NOLA | L | 3.4.2 | 138 | Attachment L-3 AFBL and Attachment 13 NOLA Tab labor categories don't correlate to Attachment L-4 Vol 3 labor categories. Attch L-3 and Attch L-4 labor category disparities exist. Which Attachment is correct? Request the government correct all Attachments so they match. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 88 | Attachment L-3 & Attachment 13 Tab NBC | L | 3.4.2 | 138 | Attachment L-3 AFBL and Attachment 13 NBC Tab labor categories don't correlate to Attachment L-4 Vol 3 labor categories. Attch L-3 and Attch L-4 labor category disparities exist. Which Attachment is correct? Request the government correct all Attachments so they match. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 89 | Attachment L-3 & Attachment 13 Tab SOLM | L | 3.4.2 | 138 | Attachment L-3 AFBL and Attachment 13 SOLM Tab labor categories don't correlate to Attachment L-4 Vol 3 labor categories. Attch L-3 and Attch L-4 labor category disparities exist. Which Attachment is correct? Request the government correct all Attachments so they match. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 90 | Attachment L-4 | L | 3.4.2 | 138 | Attachment L-4 SOLM column hours total in cell Q:35 shows 1,249,920 hrs but when you total the column the hours equal 1,256,640. Which value is correct and which labor category needs adjusting? Request the government correct Attachment L-4. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 91 | Attachment L-4 | L | 3.4.2 | 138 | Hours for Program/Operations Manager shows a PM at JAX, JRBFTW, and SOLM. Is it the intent to have PM's at each location? Request the government correct Attachment L-4. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 92 | RFP | L | 2 | 38415 | Offerors are required to submit PDF of all files. Question: The issues are the page set up on the excel files. Do the fonts have to meet the font requirement of 10pt in the pdf version? Can the pdf be sized to fit to page? Do we just pdf the excel file with the page set up the Excel file already is? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 93 | Attachment L-4 Vol 3 Hours and Attachment 15 - Team Complement Table | N/A | Total Hours/FTEs | N/A | The total FTEs provided in Attachment 15 - Team Complement Table are 528 FTEs, however the total hours provided in Attachment L-4 Vol 3 Hours are 3,565,440 which based on 1,920 productive hours equates to 530.57 FTEs. Will the Government please provide the correct number of FTEs to bid based on productive hours of 1,920? | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 94 | Attachment L-4 Vol 3 Hours | N/A | Hours | N/A | Will the Government please confirm that the hours provided for locations BFT, JAX, NNSY and NBC are correct and based off productive hours of 1,920? Currently the hours provided for the referenced locations based on 1,920 productive hours equate to fractional FTEs; BFT = 33.14 FTEs, JAX = 18.14 FTEs, NNSY = 56.43 FTEs and NBC = 79.86 FTEs. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 95 | Attachment L-2 Vol 3 CSS | N/A | Cost Summary Spreadsheet | N/A | Instruction #4 states that, "proposed labor categories with more than one person providing service shall identify the total number of personnel on one line for each site", currently the Cost Summary Spreadsheet does not have a column to identify the total number of personnel. Can the Offeror insert a column within this spreadsheet to identify the number of personnel on a given line? | No | Please see the upated instructions in Attachment L-2 | ||
| 96 | Attachment L-4, Attachment L-3, Attachment 15, and Attachment 13 | C | 4.3.6.23 | 63 | Work locations for the Site Supervisors are identified in RFP Section C, para. 4.3.6.23 at the following: FRCASE BIC, BFT, CPNC, JAX, JRBFWT, NNSY, NOLA, NBC, EL CEN and SOLM. However, Attachment L-4 shows hours for Site Supervisors at only CPNC, NNSY, NBC, and SOLM. Attachments L-3 and 13 do not show Site Supervisors on the following tabs in contradiction to para. 4.3.6.23: BIC, BFT, CPNC, JAX, JRBFTW, NOLA, and EL CEN. Lastly, Attachment 15 shows Site Supervisors at only NNSY, NBC, and SOLM. Which attachments are correct? Request the government correct all identified attachments. | No | The Government has updated Attachment 15 and L-4. Please see the amended documents | ||
| 97 | RFP | A | 2 | 2 | The USG has provided 2 different nationwide NWDs that are applicable to this effort: 2015-0025 and | 04/19/2022. Which of these NWDs are applicable to which non-union site? | No | The NWDs are applicable to the non-union sites. If a labor category is not under one of the NWDs, the Offeror shall utilize the NWD that contains the labor category. | |
| 98 | RFP | B | N/A | 5 | CLIN 0001 states it is "Cost,Plus Fixed Fee Labor Ceiling for CLIN 0002-0004" - should this state "Cost,Plus Fixed Fee Labor Ceiling for CLIN 0002-0005"? | No | Please see the amended RFP. | ||
| 99 | RFP | B | N/A | 6, 7 | CLIN 0006 states is is "Material Other Direct Costs (ODCs) Ceiling in support of CLIN 0006- 0008" - should this state "Material Other Direct Costs (ODCs) Ceiling in support of CLIN 0007- 0010"? | No | Please see the amended RFP. | ||
| 100 | RFP | B | N/A | 8 | CLIN 0011 states is is "Travel Other Direct Costs (ODCs) Ceiling in support of CLIN 0010- 0012" - should this state "Travel Other Direct Costs (ODCs) Ceiling in support of CLIN 0012-0015"? | No | Please see the amended RFP. | ||
| 101 | RFP | PWS | 3.5 Other Direct Costs | ||||||
| 3.5.1 Travel: | 21 | Will the USG allow an OH (overhead) indirect rate pool added to travel, in addition to general and administrative (G&A) expenses? | No | The Offerors shall propose to their approved cost accounting standards. | |||||
| 102 | RFP | PWS | 3.5.2 Material | 22 | Will the USG allow an OH (overhead) indirect rate pool added to material costs, in addition to general and administrative (G&A) expenses? | No | The Offerors shall propose to their approved cost accounting standards. | ||
| 103 | SOW and Attachment 15 - Team Complement | C and Attachment | 3.3.1.16 and 4.3.6.19 | 19 and page 1 | SOW paragraph 3.3.1.16 states "The Contractor shall have four (4) Site Supervisors (BLS-49-1011) at the following sites SOL (2), NNSY (1) , NBC (1). At the other remaining sites (with the exception NWS Cheatham Annex Williamsburg), the Contractor shall designate a Ground Support Equipment Mechanic or Electronic Technician III (Site Lead) to perform as the site lead." In Attachment 15, there is also an Automotive Painter listed as a Site Lead. Question: Is there also an Automotive Painter Site Lead at SERF NTHI and SERF EVRT? | Please see the amended RFP. | |||
| 104 | RFP and Attachments 7 and 8 | I and Attachment | 52.222-42 | 104 | RFP paragraph 52.222-42 states "STATEMENT OF EQUIVALENT RATES FOR FEDERAL HIRES (MAY 2014). In compliance with the Service Contract Labor Standards statute and the regulations of the Secretary of Labor (29 CFR Part 4), this clause identifies the classes of service employees expected to be employed under the contract and states the wages and fringe benefits payable to each if they were employed by the contracting agency subject to the provisions of 5 U.S.C. 5341 or 5332. |