ECU_2017_Contract_SOW_030617.docx

DOCX document 23 KB Posted

Attached to
Environmental Control Units (ECUs)
Solicitation number
N68335-17-R-0094
Issued by

View the file

Other files

File Type Posted
Technical_Manual_Placeholder.docx DOCX document
General_Requirement_and_Test_Specification_for_ECU_030617.docx DOCX document
ECU_Logistics_Statement_of_Work_2017.doc DOC document
N68335-17-R-0094.docx DOCX document
CDRLs_A001-A008.PDF PDF
CDRLs_L001-L003.PDF PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Manufacturing and Delivery of A/E32C-45A Environmental Control Units (ECU) Statement of Work (SOW) July 2016

1.0 Introduction

1.0 Scope:

This acquisition is structured for the contractor to identify parts obsolescence and integrity of the drawing package prior to full production We intend to procure two (2) Pilot Production Units (PPUs) for functional testing by the contractor. In the process of producing the PPUs, the contractor will be responsible to identify part substitutions and provide technical information to support the substitutions as defined below. At the completion of the two PPUs, the contractor will be responsible to conduct and document a functional test to insure the unit still meets its top performance requirements as per Enclosure (1). With the successful completion of the test program, the government will provide a release for production for the units awarded through the life of the contract. The ECU shall be manufactured in accordance with a government data package and Enclosure (1). Any modifications of the data package shall meet the General Requirement and Test Specification for A/E32C-45A.

1.1 Purpose:

This SOW defines and describes the requirements for the contractor to manufacture A/E32C-45A ECU’s in accordance with government drawing package (3003) 1559AS400-1. Delivery of the PPUs is required within 90 Days After Contract (DAC) selection. The evaluation will last for a period of 90 days. Upon successful completion of functional testing we intend to place orders for the first production year. Another four ordering years will be available to place orders beyond that. Delivery shall be 120 Days After Receipt of Order (ARO).

1.2 Objective:

Contractor shall provide a design that satisfies requirements of SOW, Logistics Support SOW and Enclosure (1).

1.3 Background:

NAVAIR is seeking to procure ECU’s to be installed in Mobile Facilities (MF’s). The MF is a mobile habitable shelter that is 8 feet wide by 20 feet long by 8 feet high. The ECU is a heat pump that provides heating and cooling to maintain the MF at a suitable temperature for the inhabitants and the equipment installed in the shelter. Operationally, MF’s are setup in a complex austere expeditionary environment. The ECU will take standard 60Hz utility power from either a plant grid or Mobile Electric Power Plant (MEPP), a diesel engine driven generator set.

2.0 Applicable Documents:

a. Drawing Package (3003) 1559AS400-1, which defines the manufacturing and assembly of the ECU.

b. Manual NAVAIR _17-1-573, Operation and Maintenance with Illustrated Parts Breakdown.

c. Enclosure (1) General Requirement and Test Specification for A/E32C-45A ECU.

3.0 Task Requirements:

3.1 Program schedule: Within 30 DAC, a program schedule will be delivered in accordance with CDRL A001. The program schedule will outline all steps in the manufacturing, testing and delivery of the ECU.

3.2 Bill of Materials: Within 60 DAC, a complete bill of materials will be delivered in accordance with CDRL A002. The bill of materials will be based on the components listed in the drawing package and shall list the drawing numbers, part numbers and vendors for all purchased parts as listed on the drawings. If the drawing’s suggested source will be used no further information is needed. If an alternate source for any component is proposed that are form, fit, and function interchangeable with the parts on the drawings, the list shall be annotated with the alternate vendor and part number, reason for substitution and catalog specification sheet and other supporting information showing interchangeability. Alternate parts that are not form, fit, and function substitutes will not be accepted unless the part from suggested source is no longer available and no interchangeable part can be found after reasonable research. In this case, the bill of materials shall be annotated as such and in addition to the information described above, all other changes necessary to use the substitute shall be provided. Identification of these changes shall be through ‘redline’ mark-ups of all drawings as well as mark-up of the technical manual pages affected by the substitution.

3.3 Technical Interchange Meetings: The government intends to conduct at least two technical interchange meetings prior to the manufacturing of the PPUs. The first will be the Post Award Conference occurring on or about 30 DAC. The purpose of the meeting will be to review the drawing package to address any questions and concerns on the performance of the contract. The second meeting will be held after the delivery of CDRL A002 to review the parts substitution and address any issues and concerns with the bill of materials. The contractor will be responsible for hosting the meeting (approximately 5 government attendees), preparing any review material and for recording and delivering the minutes of the meeting in accordance with CDRL A005.

3.4 Acceptance Test Plan: Within 60 DAC, an acceptance test plan shall be provided in accordance with CDRL A003. This data item shall describe each of the tests/inspections that are needed to demonstrate that the PPUs meet all the top performance requirements outlined in Enclosure (1). The test plan shall include all check lists, data sheets and procedures to perform the inspections and functional tests. The plan shall also list all equipment and measurement tools (with calibration certifications as required) that will be used during testing. Note: This test plan will be used for production testing/inspections for acceptance of each production unit.

3.5 PPU Testing: Within 90 DAC, the contractor shall have two PPUs ready for inspection and testing as per Enclosure (1) and demonstration in accordance with the acceptance test plan. The contractor shall notify the government at least 14 days prior to the test event to allow for witnessing of the event. PPUs will remain with the contractor and all testing will be performed at the contractor’s location.

3.6 PPU Testing Report: Within 180 DAC a test report shall be delivered in accordance with CDRL A004. The test report shall document the results of all testing. If any failures occurred during the testing the contractor shall provide a detailed description of the failure, steps taken to correct it, any changes to the unit design that will be necessary to correct the underlying cause of failure (this information can be communicated through mark-ups of the drawing package and or technical manual) and results of the retest.

3.7 Release for production: With approval of the test report, the government shall release the contractor to begin the production of all units under contract. Prior to this, all purchase of materials and manufacturing shall be at the contractor’s expense and risk. Within 90 days of the release for production, the contractor shall begin delivery of the production units and will continue to do so at an indefinite quantity rate. Each unit shall be subjected to the subset of production tests/inspections as identified in CDRL A003. Test report and completed data sheets for each unit shall be maintained at the contractor’s facility and delivered in accordance with CDRL A003 30 days after the delivery of the last production unit.

3.8 Preservation/Packaging and Marking:

Preservation: No additional preservation is required to the manufactured end article prior to packing.

Packing: Each unit is to be packed in a skidded, wood box conforming to ASTM D6251, type III, class 1 with the following additional requirements:

· Box is to be completely demountable using fasteners described in ASTM D6251.

· Units shall be secured properly to the base of the box.

· Units are to be packed individually and strapped together as sets of two for shipping.

· Acceptance Test Report shall be placed in envelope and attached to each production unit.

Marking: Each item marked shall be in accordance with MIL-STD-130N, Military Marking for Shipment and Storage current at the date of award. Units and Linear Bar Code marking for individual units are detailed on ID Plate drawing 1559AS593.

3.9 Configuration Control: (CDRLs A006, A007, A008): The contractor shall submit Engineering Change Proposals (ECPs), see CDRL A006, and all minor, major and critical Request for Deviation/Waiver (see CDRLs A007 and A008). The procuring activity will assume configuration control of the ECU.

3.10 Quality Assurance: The contractor shall continually manage and improve the quality of all products and services delivered under this contract and the processes by which they are realized. The system used by the contractor to manage quality shall be compliant with all requirements of, and at a minimum be functionally equal to, a current version of the ANSI/ISO/ASQ Q9001-2008 compliance. The Government shall have access, for review and analysis purposes, to contractor QMS documents; raw data that have not been subjected to processing or any other manipulation; summarized, tabularized, or graphical depictions of the data; and records under this contract.

3.11 Unique Identification Requirement: Unique Identification (UID) is a Department of Defense (DoD) program that will enable easy access to information about DoD possessions that will make acquisition, repair, and deployment of items faster and more efficient. In accordance with DFARS Clause 252.211-7003 Item Identification and valuation, the contractor is required to mark and register all end items and their components meeting the requirements called out in MIL-STD-130M. UID Data is encoded into Data Matrix symbols that are applied directly to parts. The UID for these items shall be created in accordance with NAVAIR drawings and MIL-STD-130M. UID plates will be located in accordance with the NAVAIR drawings.

3.11.1UID Registration. The prime Contractor has the responsibility to furnish IUID data to the IUID registry. Data submission of IUID data and acquisition cost should be submitted via Wide Area Work Flow (WAWF), IUID XML file, IUID flat file or web entry. Additional information regarding data submission as well as the actual marking can be found at <http://www.acq.osd.mil/dpap/pdi/uid/index.html>.
3.11.2UID Records. The Contractor shall maintain an accurate, current list of IUIDs for all manufactured items on this contract. This shall be supplied to the Government periodically and upon request. The list shall include Part Number, Serial #, CAGE, IUID Location, Construct used, how it was marked and the registration method used. If a third party is utilized they shall be identified.