This is Standard Form 30, Amendment 0006 to solicitation N6817126QN006, issued by NAVSUP FLC Sigonella Naples Office (Naval Regional Contracting Center Detachment) on February 13, 2026. The amendment provides responses to bidder questions and extends the quotation due date.
The amendment addresses three bidder inquiries regarding ship repair work. Question #1 concerns Work Item 1001 (Pedestal Foundation Plate), with the answer clarifying foundation height as 2'4" and providing additional photographs as attachments. Question #2 addresses Work Item 515 (Deck Grating), confirming that 1/4" plate thickness is acceptable rather than 3/8", authorizing contractors to bring additional lighting towers onboard powered by ship's supply, and indicating painting work shifts are permitted. Question #3 clarifies that no tank cleaning or wastewater disposal is required during this period. The quotation receipt deadline is extended to 13:00 CET on Tuesday, February 17, 2026. The contracting officer is Antonella De Fraia Frangipane, located at Naval Regional Contracting Center Detachment, PSC 817 Box 50, FPO, AE 09622-0050, reachable at antonella.defraiafrangipane.ln@us.navy.mil or telephone 0815683560. All other terms and conditions of the original solicitation remain unchanged.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
J 1 2
0006 13 Feb 2026 See Continuation Sheet N68171
NAVSUP FLC SIGONELLA NAPLES OFFICE
NAVAL REGIONAL CONTRACTING CEN DET, PSC 817 BOX 50
FPO, AE 09622-0050
UNITED STATES
Antonella De Fraia Frangipane, Email: antonella.defraiafrangipane.ln@us.navy.
mil Telephone: 0815683560
SCD: PAS:
N6817126QN006
17 Dec 2025
See Section G - Contract Administration Data
See Schedule
Antonella De Fraia Frangipane
13 Feb 2026
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Block 14 (Description of Amendment/Modification): The purpose of this amendment is to provide the answers to bidder's questions, and to extend the due date for receipt of quotations. Accordingly:
1. The following Bidder's questions and answers are hereby provided:
Question #1: Work Item 1001 - Pedestal Foundation Plate:
What is the height of the foundations? Are there any approximate figures regarding how many cables are connected per box? (is a photo available?)
Answer #1: 2'4" . Additional photos are provided as attachments.
Question #2: Work Item 515 - Deck Grating Please confirm whether the new chequer plates are indeed required to be 3/8" (approx. 10 mm) thick. (weight...?) Given the volume of work and the limited time available, we are considering the possibility of carrying out the painting works in shifts.
Given the volume of work and the limited time available, in order to be prepared in the event that it becomes necessary to carry out the painting works in shifts, we would like to know whether lighting is available in the kingpost area.
If required, would it be possible to bring additional light towers on board, to be powered by the vessel's onboard supply?
Answer #2:
- 1/4" plate is acceptable.
- Yes, Contractor can bring additional lighting towers onboard and use ship's power.
Question #3: Please also confirm whether you require to perform tank cleaning and/or wastewater disposal included into the Ship Repair quotation?
If so please specify amounts to be disposed as well as tank volumes and surfaces in square meters to be cleaned.
Answer #3: No tanks will be cleaned during this period.
2. The due date for receipt of quotations is hereby extended to 13:00 (CET) on Tuesday, 17 Feb 2026
3. All other information remains unchanged.
N6817126QN0060006