Exhibit B – Delivery and Performance Information Rev. 2 N66604-14-R-0921
Item
No.
Item Qty
Unit Delivery Date
After date of contract award
Ship to Address UIC
0001 Alternator
First Article
5 Each 18 months Newport
See Clause D3
FOB Destination
N66604
0003 Regulator
First Article
5 Each 18 months
OPTIONS
See Page 4 for Estimated Option Exercise Dates
After exercising option
0005 – 0019 Deleted
0021 Alternator
Production Run 1
10-20 Each 12 months Keyport
See Clause D3
FOB Destination
N00253
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0023 Alternator
Production Run 2
10-20 Each 12 months
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0025 Alternator
Production Run 3
10-20 Each 12 months
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0027 Alternator
Production Run 4
10-20 Each 12 months
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0029 Alternator
Production Run 5
10-20 Each 12 months
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
Continued next page
0031 Regulator
Production Run 1
10-20 Each 12 months Keyport
See Clause D3
FOB Destination
N00253
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0033 Regulator
Production Run 2
10-20 Each 12 months
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0035 Regulator
Production Run 3
10-20 Each 12 months
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0037 Regulator
Production Run 4
10-20 Each 12 months
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0039 Regulator
Production Run 5
10-20 Each 12 months
21-30 Each 13 months
31-40 Each 14 months
41-50 Each 15 months
0041 Long Lead Material
10-20 Each TBD Contractor’s facility N/A
21-30 Each
31-40 Each
41-50 Each
0043 Long Lead Material
Production Run 2
10-20 Each
21-30 Each 31-40 Each 41-50 Each
0045 Long Lead Material
Production Run 3
10-20 Each
21-30 Each 31-40 Each 41-50 Each
0047 Long Lead Material
Production Run 4
10-20 Each
21-30 Each 31-40 Each 41-50 Each
0049 Long Lead Material
Production Run 5
10-20 Each
21-30 Each 31-40 Each 41-50 Each
0061 Engineering Services
Yr 1
N/A N/A Est. Period of Performance
1 Sep 2014 – 31 Aug 2015
Newport
See Clause D3
FOB Destination
N66604
0063 Engineering Services
Yr 2
Est. Period of Performance
1 Sep 2015 – 31 Aug 2016
0065 Engineering Services
Yr 3
1 Sep 2016 – 31 Aug 2017
0067 Engineering Services
Yr 4
1 Sep 2017 – 31 Aug 2018
0069 Engineering Services
Yr 5
1 Sep 2018 – 31 Aug 2019
0071 Engineering Services
Travel/Other Direct
Costs
Yr 1
N/A N/A Est. Period of Performance
1 Sep 2014 – 31 Aug 2015
Newport
See Clause D3
FOB Destination
N66604
0073 Engineering Services
Travel/Other Direct
Costs
Yr 2
Est. Period of Performance
1 Sep 2015 – 31 Aug 2016
0075 Engineering Services
Travel/Other Direct
Costs
Yr 3
Est. Period of Performance
1 Sep 2016 – 31 Aug 2017
0077 Engineering Services
Travel/Other Direct
Costs
Yr 4
Est. Period of Performance
1 Sep 2017 – 31 Aug 2018
0079 Engineering Services
Travel/Other Direct
Costs
Yr 5
1 Sep 2018 – 31 Aug 2019
ESTIMATED OPTION EXERCISE DATES
The Government may exercise, if at all, any of the Option Items as follows:
CLINs Estimated Option Exercise Date
0021/0022 24 months after date of contract
0023/0024 30 months after date of contract
0025/0026 36 months after date of contract
0027/0028 42 months after date of contract
0029/0030 50 months after date of contract
0031/0032 24 months after date of contract
0033/0034 30 months after date of contract
0035/0036 36 months after date of contract
0037/0038 42 months after date of contract
0039/0040 50 months after date of contract
0041/0042 TBD
0043/0044 TBD
0045/0046 TBD
0047/0048 TBD
0049/0050 TBD
0061/0062 6 months after date of contract
0063/0064 12 months after date of contract
0065/0066 24 months after date of contract
0067/0068 36 months after date of contract
0069/0070 48 months after date of contract
0071/0072 6 months after date of contract
0073/0074 12 months after date of contract
0075/0076 24 months after date of contract
0077/0078 36 months after date of contract
0079/0080 48 months after date of contract
OFFEROR'S PROPOSED DELIVERY SCHEDULE IAW FAR Clause 52.211-8. Offeror to fill in.
After date of contract award
0001 Alternator
First Article
5 Each
0003 Regulator
First Article
5 Each
OPTIONS
0021 Alternator
10-20 Each
21-30 Each
31-40 Each
41-50 Each
0023 Alternator
Production Run 2
10-20 Each
21-30 Each
31-40 Each
41-50 Each
0025 Alternator
Production Run 3
10-20 Each
21-30 Each
31-40 Each
41-50 Each
0027 Alternator
Production Run 4
10-20 Each
21-30 Each
31-40 Each
41-50 Each
0029 Alternator
Production Run 5
10-20 Each
21-30 Each
0031 Regulator
Production Run 1
10-20 Each
21-30 Each
31-40 Each
41-50 Each
0033 Regulator
Production Run 2
10-20 Each
21-30 Each
31-40 Each
41-50 Each
0035 Regulator
Production Run 3
10-20 Each
21-30 Each
31-40 Each
41-50 Each
0037 Regulator
Production Run 4
10-20 Each
21-30 Each
31-40 Each
41-50 Each
0039 Regulator
Production Run 5
10-20 Each
21-30 Each
0041 Long Lead Material
10-20 Each TBD
21-30 Each
31-40 Each
41-50 Each
0043 Long Lead Material
Production Run 2
10-20 Each
21-30 Each 31-40 Each 41-50 Each
0045 Long Lead Material
Production Run 3
10-20 Each
21-30 Each 31-40 Each 41-50 Each
0047 Long Lead Material
Production Run 4
10-20 Each
21-30 Each 31-40 Each 41-50 Each
0049 Long Lead Material
Production Run 5
10-20 Each
21-30 Each
File details come from the government source that posted it. Updated .