DELIVERY ORDER (DO) PERFORMANCE WORK STATEMENT (PWS)
SPACE AND NAVAL WARFARE SYSTEMS CENTER, ATLANTIC
SHORT TITLE: CSRR SSN-XXX NEW CONSTRUCTION EQUIPMENT, MATERIAL AND
PRE-CABLING MATERIAL
1.1 PRIMARY PLACE(S) OF PERFORMANCE
The following site(s) identify contractor employees’ originating office location and the location of government provided facilities, if applicable to this DO. Travel locations (i.e., temporary duty sites) are specified in the Travel Section under DO PWS Para 10.0.
a. Contractor facility
b. SPAWARSYSCEN Atlantic, Charleston facility
2.0 DELIVERY ORDER PURPOSE
2.1 SCOPE
Naval Sea Systems Command (NAVSEA) PMS 450 tasked Space and Naval Warfare Systems Center (SPAWARSYSCEN) Atlantic to provide the Common Submarine Radio Room (CSRR) Program New Construction Equipment, Material and Pre-Cabling Material for one ship set.
3.0 APPLICABLE DOCUMENTS
3.1 REQUIRED DOCUMENTS
The contractor shall utilize all required documents listed within the basic contract as applicable to this DO. In addition, the following required documents are applicable to this specific DO:
Document Number Title
a. CAEI-M-01 CAEI Management Plan
b. CAEI-00015 CAEI Project Management Plan Template
c. QMS-M-01 CAEI Quality Manual
d. CMP-F-003 CAEI Kickoff Presentation Template
e. CMP-F-004 CAEI Closeout Presentation Template
f. N/A CAEI Milestone Summary Template (Slide 6 of Kickoff
Presentation Template)
g. DCMA-INST 109 Contractor Purchasing System Reviews
3.2 GUIDANCE DOCUMENTS
The contractor shall utilize all guidance documents listed within the basic contract as applicable to this DO. In addition, the following guidance documents are applicable to this specific DO:
a. NAVSEA 0902-018-
General Overhaul Specifications for Deep Diving SSBN/SSN Submarines
b. FY-13 (CH-4) NAVSEA Standard Items
c. 009-004 NAVSEA Standard Item: Quality Management System; provide
d. 009-16 NAVSEA Standard Item: Electronic Equipment; repair
e. 009-20 NAVSEA Standard Item: Government Property; control
f. 009-22 NAVSEA Standard Item: Shipboard Electric Cable; Test
g. 009-24 NAVSEA Standard Item: Authorization, Control, Isolation, Blanking, and Tagging Requirements; accomplish
h. 009-73 NAVSEA Standard Item: Shipboard Electrical/Electronic/Fiber
Optic Cable; remove, relocate, repair and install
i. 009-79 NAVSEA Standard Item: Government Owned Material (GOM);
status, reporting
j. MIL-STD-130 DOD Standard Practice – Identification marking of U.S. Military
Property
k. DoD-STD-2003/MIL-
STD-2003
Electric Plant Installation Methods For Surface Ships and Submarines
l. NAVSHIPS 302- 4456087
SSN688 Class Submarine Electronics/Electrical Standard Installation Methods
m. NAVSEA SE000-00-
EIM-110 (0967-LP-000-
0110)
Navy Installation and Maintenance Book (NIMB) Installation Standards
n. MIL-STD-2042 & ALL
PARTS OF MIL-STD-
2042)
Fiber Optic Cable Topology Installation Standard Methods for
3.3 ACRONYMS
CAM CONTRACTOR ACQUIRED MATERIAL
CAP CONTRACTOR ACQUIRED PROPERTY
CAEI C4ISR ACQUISITION ENGINEERING AND INTEGRATION
CDAD CPARS Draft Approval Document
CDRL CONTRACT DATA REQUIREMENTS LIST
COR CONTRACTING OFFICER REPRESENTATIVE
CMPRO CONFIGURATION MANAGEMENT PROFESSIONAL
CPOR COMPONENT PROGRAM OF RECORD
CSRR COMMON SUBMARINE RADIO ROOM
CSWF CYBERSECURITY WORKFORCE
CV/BT CONFIGURATION VERIFICATION/BENCH TEST
DWG DRAWING
FCL FACILITY CLEARANCE
GFE GOVERNMENT FURNISHED EQUIPMENT
GFM GOVERNMENT FURNISHED MATERIAL
IUID ITEM UNIQUE IDENTIFICATION
LAR LIAISON ACTION RECORD
MKA MECHANICAL KIT ASSEMBLY
NSERC NAVAL SYSTEMS ENGINEERING RESOURCE CENTER
PCL PERSONNEL CLEARANCE
PARM PARTICIPATING ACQUISITION RESOURCE MANAGER
PARMALT PARTICIPATING ACQUISITION RESOURCE MANAGER ALTERATION
PLAR PARTICIPATING ACQUISITION RESOURCE MANAGER LIAISON
ACTION RECORDS
PMP PROJECT MANAGEMENT PLAN
QA QUALITY ASSURANCE
QASP QUALITY ASSURANCE SURVEILLANCE PLAN
RLAR REVERSE LIAISON ACTION RECORD
SOP STANDARD OPERATING PROCEDURE
SSN ATTACK SUBMARINE (NUCLEAR PROPULSION)
ST SPECIAL TOOLING
STE SPECIAL TEST EQUIPMENT
TDP TECHNICAL DATA PACKAGE
TO TASK ORDER
4.0 SECURITY REQUIREMENTS
4.1 ORGANIZATION
As specified in the basic Contract Security Classification Specification form, DD-254, the contractor shall perform classified work in support of this delivery order. At time of DO award, the contractor shall have a SECRET facility clearance (FCL).
4.2 PERSONNEL
Prior to any labor hours being charged on contract, the contractor shall ensure their personnel (including administrative and subcontractor personnel) have obtained and can maintain favorable background investigations at the appropriate level(s) for access level required by this delivery order, and if applicable, are certified/ credentialed for the Cybersecurity Workforce (CSWF). Investigations are not necessarily required for personnel performing unclassified work who do not require access to government installations/facilities and/or government IT systems/IT resources.
4.2.1 Security Clearance Classification
This DO allows for various Personnel Security Clearance (PCL) levels to support the requirements of specific PWS paragraphs. The contractor shall provide only personnel meeting or exceeding the specified minimum PCL to support the PWS requirements listed below:
DO PWS Task Paragraph Required Minimum PCL 6.1,6.3,6.4, 6.8 No classification required 6.2,6.5,6.6,6.7 Secret
5.0 COR DESIGNATION
The Contracting Officer Representative (COR) for this delivery order will be identified at the time of delivery order award.
6.0 DESCRIPTION OF WORK
6.1 PROGRAM MANAGEMENT
6.1.1 Program Initiation
Contractor shall conduct a project kickoff and document the meeting using the CAEI Kickoff Presentation Template (CDRL A007).
6.1.2 Program Planning
6.1.2.1 The contractor shall provide a Cost and Milestones Schedule Plan within 10 days after delivery order award (CDRL A008).
6.1.2.2 Contractor shall update the Project Management Plan (PMP) using the CAEI-00015 Project Management Plan Template (CDRL A007). The Government will review the plan within ten days of submission by the contractor and will provide comments and recommendations in writing for revisions.
6.1.3 Program Monitoring and Control
6.1.3.1 Contractor shall collect and report metrics (CDRL A009) as defined and planned for in the
PMP.
6.1.3.2 The contractor shall provide technical representation at reoccurring or ad hoc meetings (includes weekly production and financial meetings - see Attachment 3).
6.1.3.3 Contractor shall provide monthly Delivery Order Status Reports (CDRL A012).
6.1.3.4 The contractor shall complete the Contractor CPARS Draft Approval Document (CDAD) Report monthly (CDRL A021).
6.1.3.5 The contractor shall provide any requested Invoice Support Documentation within 24 hours of the request (CDRL A015).
6.1.4 Program Closeout
6.1.4.1 No later than fifteen (15) days after production completion, the contractor shall conduct and document team and customer closeout meetings (CDRL A007) using the CAEI Closeout Presentation Template.
6.1.4.2 The contractor shall provide a Delivery Order Closeout Report (CDRL A013).
6.2 TECHNICAL DATA PACKAGE (TDP) MANAGEMENT
6.2.1 Data Maintenance Support
The contractor shall review Government Furnished drawings that are produced specifically for this requirement and shall provide recommendations for corrections to the COR for corrective action on a monthly basis (CDRL T001 – CSRR GFI Drawing Issues).
6.3 INFRASTRUCTURE SUPPORT
6.3.1 Production Facility
Currently, the Government does not have space available for performance of this production requirement. The contractor will be required to provide the necessary space.
6.4 PROCUREMENT
6.4.1 Procure Equipment
Equipment is defined as functional electronic commercial off the shelf (COTS) and modified COTS including but not limited to routers, switches, uninterruptable power supplies (UPS), power distributions units (PDU), amplifiers, keyboard video and mouse switch (KVM), servers, modems, printers, modules, etc.
6.4.1.1 The contractor shall procure all necessary Contractor Acquired Material (CAM) to complete the work.
6.4.1.2 The contractor shall interface with vendors to establish procurement terms and conditions consistent with Contractor Purchasing System Review. The contractor shall keep in contact with vendors until material has been received.
6.4.1.3 The contractor shall generate weekly procurement status reports of each line item ordered (CDRL T002 – CSRR Procurement Status Report).
6.4.1.4 The Contractor is not responsible for procuring any Component Program of Record (CPOR) equipment.
6.4.1.5 Contractor shall deliver complete equipment kit (ND-1) to government via DD-1149 no later than the date specified in the PMP.
6.4.2 Procure Material
Material is defined as fabricated items or items that are used in the fabrication or integration of assemblies (i.e. engineered cables not included in pre cabling kit, mounting kit assemblies (MKA)), and consumables called out in the TDP.
6.4.2.1 The contractor shall procure all necessary Contractor Acquired Material (CAM to complete
6.4.2.2 The contractor shall interface with vendors to establish procurement terms and conditions consistent with Contractor Purchasing System Review. The contractor shall keep in contact with vendors until material has been received.
6.4.2.3 The contractor shall generate weekly procurement status reports of each line item ordered
6.4.2.4 The contractor is not responsible for procuring CPOR material.
6.4.2.5 Contractor shall deliver complete material kit (ND-2) to government NLT the date specified in accordance with the PMP via DD-1149.
6.4.3 Procure Pre-Cabling Material
Pre-cabling material is defined as material included in pre-cabling kits as defined in the TDP.
6.4.3.1 The contractor shall procure all necessary Contractor Acquired Material (CAM) to complete
6.4.3.2 The contractor shall interface with suppliers to establish procurement terms and conditions consistent with Contractor Purchasing System Review. The contractor shall keep in contact with vendors until material has been received.
6.4.3.3 The contractor shall generate weekly procurement status reports of each line item ordered
6.4.3.4 The Contractor is not responsible for procuring any CPOR equipment.
6.4.3.5 Contractor shall deliver complete pre-cabling material kit (ND-3) to government NLT the date specified in accordance with the PMP via DD-1149.
6.4.4 Equipment Warranty
6.4.4.1 The contractor shall generate the Warranty Tracking and Administration for Serialized Item Report (CDRL A006) at the time a warrantied item is delivered to government.
6.4.4.2 A Warranty and Non-Warranty Failure Status Repair Report (CDRL A009) shall be submitted to the COR on all warranty and non-warranty actions taken during the preceding quarter and collected cumulatively.
6.4.4.3 If equipment fails while still under manufacturer warranty, the contractor shall return the equipment to the vendor/manufacturer for product repair/replacement.
6.4.5 Material Warranty
6.4.5.1 The contractor shall generate the Warranty Tracking and Administration for Serialized Item
6.4.5.2 A Warranty and Non-Warranty Failure Status Repair Report (CDRL A009) shall be
6.4.5.3 The contractor shall return all nonconforming material to the vendor/manufacturer for product repair/replacement.
6.4.6 Pre-Cabling Material Warranty
6.4.6.1 The contractor shall generate the Warranty Tracking and Administration for Serialized Item
6.4.6.2 A Warranty and Non-Warranty Failure Status Repair Report (CDRL A009) shall be
6.4.6.3 The contractor shall return all nonconforming pre-cabling material to the vendor/manufacturer for product repair/replacement.
6.5 ASSET MANAGMENT
6.5.1 Manage Equipment
6.5.1.1 The contractor shall receive and process the necessary CAM.
6.5.1.2 The contractor shall provide production inventory and asset management monthly via the Inventory Tracking Report (CDRL A002) and shall update the government database system
(CMPRO).
6.5.1.3 The contractor shall store equipment items.
6.5.1.4 The contractor shall pull the equipment items when required for production or shipment.
6.5.1.5 Contractor shall provide Product Delivery Documentation confirming receipt within five days of receipt from the vendor (CDRL A007).
6.5.1.6 The contractor shall track all equipment and GFM from receipt until time of delivery to the
COR (CDRL T003).
6.5.1.7 The contractor shall include a comprehensive PLAR list with each completed kit. This list shall include the incorporated and outstanding PLAR’s (CDRL T004).
6.5.1.8 The contractor shall package all equipment for storage or shipment.
6.5.2 Manage Material
6.5.2.1 The contractor shall receive and process the necessary CAM .
6.5.2.2 The contractor shall provide production inventory and asset management monthly via the
6.5.2.3 The contractor shall store material items.
6.5.2.4 The contractor shall pull the material items when required for production or shipment.
6.5.2.5 Contractor shall provide Product Delivery Documentation confirming receipt within five
6.5.2.6 The contractor shall track all material from receipt until time of delivery to the COR (CDRL T003).
6.5.2.7 The contractor shall include a comprehensive PLAR list with each completed kit. This list
6.5.2.8 The contractor shall package all material for storage or shipment.
6.5.3 Manage Pre-Cabling Material
6.5.3.1 The contractor shall receive and process the CAM.
6.5.3.2 The contractor shall provide production inventory and asset management monthly via the
6.5.3.3 The contractor shall store pre-cabling material items.
6.5.3.4 The contractor shall pull the pre-cabling material items when required for production or shipment.
6.5.3.5 Contractor shall provide Product Delivery Documentation confirming receipt within five
6.5.3.6 The contractor shall track all pre-cabling material from receipt until time of delivery to the
COR (CDRL T003).
6.5.3.7 The contractor shall include a comprehensive PLAR list with each completed kit. This list
6.5.3.8 The contractor shall package all pre-cabling material for storage or shipment.
6.5.4 Equipment Marking and Labeling
6.5.4.1 Upon receipt of equipment, the contractor shall produce and place IUID tags on equipment IAW Common Submarine Radio Room (CSRR) Item Unique Identification (IUID) Standard Operating Procedure (SOP) CSRR-SOP-UID-GEN-13-0.1.
6.5.5 Material Marking and Labeling
6.5.5.1 Mechanical Kit Assembly (MKA) shall be clearly marked with the following: Parmalt Dwg, Item number, Reference Designator, Description, Part number and Quantity. Items that make up or are within a MKA shall be marked with the following: MKA DWG NO., Item number, Description, Part Number and Quantity.
6.5.5.2 PARMALT Misc Items shall be clearly marked with the following: Parmalt Dwg, Reference Designator, Item number, Description, Part number and Quantity.
6.5.5.3 Shipalt Misc Items – shall be clearly marked with the following: Shipalt Dwg, Item number, Description, Part Number and Quantity.
6.5.6 Pre-Cabling Material Marking and Labeling
6.5.6.1 The contractor shall produce and place IUID tags on equipment IAW Common Submarine Radio Room (CSRR) Item Unique Identification (IUID) Standard Operating Procedure (SOP) CSRR-
SOP-UID-GEN-13-0.1.
6.5.6.2 Pre-cabling Kit Items shall be clearly marked with the following: Parmalt Dwg, Item number, Reference Designator, Description, Part number, Quantity and Schedule A Item Number.
6.6 PRE-INTEGRATION
6.6.1 Equipment Fabrication
6.6.1.1 The contractor shall provide the necessary fabrication to complete the assembly of items.
6.6.2 Material Fabrication
6.6.2.1 The contractor shall provide the necessary fabrication to complete the assembly of all harnesses and material.
6.6.2.2 The contractor shall place protective caps over the ends of all connectors to provide protection during storage and shipment.
6.6.3 Pre-Cabling Material Fabrication
6.6.3.1 The contractor shall provide the necessary fabrication to complete the assembly of all pre-cabling material.
6.6.3.2 The contractor shall place protective caps over the ends of all connectors to provide protection during storage and shipment.
6.7 TESTING
6.7.1 Equipment Verification
The contractor shall perform configuration verification/bench test (CV/BT) on all equipment received whether procured or fabricated to include CPOR.
6.7.2 Equipment Validation
Upon turning over the equipment to the government, contractor shall provide Final Quality / Test Acceptance Documentation (CDRL A009) to prove products have been electrically and mechanically tested during the contractor’s receipt process.
6.7.3 Material Validation
Upon turning over the material to the government, contractor shall provide Final Quality / Test Acceptance Documentation (CDRL A009) to prove products have been electrically and mechanically tested during the contractor’s receipt process.
6.7.4 Pre-Cabling Material Validation
Upon turning over the pre-cabling material to the government, contractor shall provide Final Quality / Test Acceptance Documentation (CDRL A009) to prove products have been electrically and mechanically tested during the contractor’s receipt process.
6.7.5 PITCO Support
6.7.5.1 The contractor shall depopulate Government testbed mockup of existing equipment.
6.7.5.2 The contractor shall populate Government testbed mockup with kitted equipment.
6.7.5.3 The contractor shall take appropriate corrective action for system defects identified during testing.
6.7.5.4 The contractor shall depopulate tested system from the Government testbed mockup.
6.7.5.5 The contractor shall rekit the tested equipment.
6.8 TASK ORDER ADMINISTRATION
6.8.1 Basic Contract Requirement
In accordance with the basic contract PWS and the requirements of this delivery order PWS, the contractor shall develop and submit documentation (see CDRL under Para 12.1.1) for DO administration.
6.8.2 Task Order Requirement
The following DO specific administrative support and CDRLs are required for this delivery order; see Attachment #4 for applicable DD-1423 forms:
CDRL T001 CSRR GFI Drawing Issues CDRL T002 CSRR Procurement Status Report CDRL T003 Equipment, Material, Pre-Cabling Material and GFM Tracking CDRL T004 CSRR PLAR List
7.0 GOVERNMENT FURNISHED INFORMATION (GFI)
Contractors shall use online sources to obtain copies of any necessary documentation (specifically listed under Para 3.0) needed for performance on this DO. For those documents not available online, the government will provide the following GFI listed in the table below. The contractor shall inventory all GFI by tracking distribution and location and provide a GFI inventory to the government as needed. The contractor shall use the GFI provided to only support this DO – use of GFI document(s) to support other projects beyond this DO is not allowed. Unless otherwise specified, all GFI will be provided by the government by the estimated delivery date listed in the table below, and the contractor shall return all GFI to the government at completion of the DO.
Item # Description GFI Estimated Delivery Date
VA Class CSRR BLK IV Mechanical Installation (06983610)
14 days after DO award
2 VA Class BLK IV Electrical Installation (06983611) 14 days after DO award 3 VA Class CSRR BLK IV Wiring Tables (06983612) 14 days after DO award 4 Virginia Class Block IV ECS Cable List (06761206) 14 days after DO award 5 Top and Connector Plates ECS Kit (06983400) 14 days after DO award
Virginia Class CSRR RETMA Rail Installation (06902550)
7 CSRR MASTER DRAWING INDEX 14 days after DO award
Access to CMPRO and NSERC for updates to drawings in the form of revisions, PLARs, and detailed lower level drawings.
The Government will provide the latest version of the GFI to the contractor.
8.0 GOVERNMENT FURNISHED PROPERTY (GFP)
8.1 TYPES OF GFP
8.1.1 Government Furnished Equipment (GFE)
No GFE is to be provided on this DO.
8.1.2 Government Furnished Material (GFM)
Government Furnished Material (GFM) consisting of Operating Material and Supplies (OM&S) identified in the Consolidated Government Furnished Property form, Attachment #2, will be provided to the contractor.
8.1.3 Special Test Equipment (STE)
No STE is provided on this DO.
8.1.4 Special Tooling (ST)
No ST is provided on this DO.
8.2 GFP REPORTING AND TRACKING
The contractor shall ensure compliance with DFARS clause 252.211-7007, GFP Reporting. The primary and preferred means to do this is via electronic transaction reporting of GFP transfers in Invoices, Receipt and Property Transfer (IRAPT), an application within Wide Area Workflow (WAWF). This will automatically update the GFP records in the GFP Repository portion of the Item Unique Identification (IUID) Registry. The contractor is also required to track all GFP (and CAP) in the contractor property management system. As part of the DOSR (CDRL A012) requirements, the contractor shall provide a monthly GFP listing of items physically received by the contractor. The contractor shall list items within the constraints (type and quantity) of the items identified in the Consolidated Government Furnished Property form at time of DO award.
8.3 COMPUTER ASSETS REPORTING
For NMCI assets that are assigned to a contractor and removed from a government facility, the contractor employee shall have a Property Pass (OF-7) for each asset which will be authorized and signed by the COR or other authorized Government personnel. Although NMCI assets are not currently tracked as GFP, the contractor shall separately track and report all NMCI assets assigned to all contractor employees for use on this delivery order. For GFP laptops assigned to contractor employees, in addition to the signed DD1149 that specifies contract number, company name, model number, and serial number of the computer, a contractor-generated property pass with the employee’s name may be attached to validate possession in accordance with applicable company internal procedures.
9.0 CONTRACTOR ACQUIRED PROPERTY (CAP)
CAP consists of Contractor Acquired Equipment (CAE) which includes Property, Plant and Equipment (PP&E), Contractor Acquired Material (CAM) which includes Operating Material and Supplies (OM&S), Special Tooling (ST), and Special Test Equipment (STE). CAP items are acquired, fabricated, or otherwise provided by the contractor to support the DO and may be turned-in to SPAWARSYSCEN Atlantic, incorporated into a system, consumed, or delivered as an end item in the performance of the DO. In the performance of this DO, the contractor shall be responsible for providing the necessary CAP.Prior to actual items being acquired, fabricated, or provided, the contractor shall obtain COR concurrence.
10.0 TRAVEL
No travel is required on this DO.
11.0 TRANSPORTATION OF EQUIPMENT/MATERIAL
Transportation of equipment and/or material is applicable for the noted GFP and/or CAP. The contractor shall be responsible for packing, shipping, and delivery of items. For estimating purposes, the contractor shall plan for the following transportation requirements:
Type
(GFP/CAP)
Item
Description
Qty
Origination
Destination
Schedule
Responsibility
(GOVT/CTR)
CAP CSRR Pre- Cabling Kit
1 Charleston, SC General Dynamics Electric Boat
QUONSET
POINT
FACILITY
North Kingstown, RI 02852
ASREQ by
PMP
(CDRL
A007)
CTR
12.0 DELIVERABLES
12.1 CONTRACT DATA REQUIREMENTS LIST (CDRL)
12.1.1 Administrative CDRL
As referenced under TO PWS Para 6.0, the following table lists all required administrative data deliverables, Contract Data Requirements Lists (CDRLs), applicable to this task:
CDRL #
Deliverable Title
TO PWS
Reference
Para
Frequency
Date Due
A007
Program Management Reports
6.1.1, 6.1.2.2, 6.1.3.1, 6.5.1.5, 6.5.2.5, 6.5.3.5
1TIME
ASREQ
A008
Cost and Schedule Milestone
Plan
6.1.2.1
One time with revisions
(ONE/R)
NLT 10 DADO;
revision NLT 7 days after receipt of govt review
A012 Delivery Order (DO) Status
Report
6.1.3.3, 8.2
MTHLY
30 Days after DO award (DADO) and monthly on the 10th
A021
Contractor CPARS Draft Approval Document (CDAD)
Report
6.7.2, 6.7.3
30 DADO and monthly on the 10th
A015 Invoice Support Documentation
6.1.3.5 ASREQ
Within 24 hrs from request
A013 Delivery Order Close Out
Report
6.1.4.2 1TIME
NLT 15 days before completion date
12.1.2 Technical CDRL
The following table lists all required technical data deliverables, Contract Data Requirements Lists (CDRLs), applicable to this production requirement:
CDRL #
T001 CSRR GFI Drawing Issues 6.2.1, 6.8.2
MTHLY
T002
CSRR Procurement Status Report
6.4.1.3, 6.4.2.3, 6.4.3.3, 6.8.2
WEEKLY
COB every Friday
T003
Equipment, Material, Pre-Cabling Material and GFM Tracking
6.5.1.6, 6.5.2.6, 6.5.3.6, 6.8.2
T004 CSRR PLAR List 6.8.2 1TIME Submitted with each completed kit
A006 Warranty Tracking and Administration for Serialized Item Report
6.4.4.1, 6.4.5.1, 6.4.6.1
ASREQ
At time warrantied item is delivered to government
A009 Warrant y and Non-Warranty Failure Status Repair Report
6.4.4.2, 6.4.5.2, 6.4.6.2
QRTLY
15 days after completion of the
FY quarter
A002
Inventory Tracking Report
6.5.1.2.
6.5.2.2, 6.5.3.2
10th of Each Month
A009
Final Quality / Test Acceptance Documentation
6.7.2, 6.7.3, 6.7.4
Upon turnover of equipment/material/ pre-cabling material to Government
12.2 NON-DATA DELIVERABLES
The following table lists all required non-data deliverables:
ND-1
One (1) New Construction Equipment kit
6.4.1.5
12 months from date of Delivery Order
Award
ND-2
One (1) New Construction Material kit
6.4.2.5
18 months from date
ND-3
One (1) New Construction Pre-Cabling Material kit
6.4.3.5
9 months from date
13.0 ACCEPTANCE PLAN
Inspection and acceptance is performed by the COR on all services, data, and non-data deliverables in accordance with the Quality Assurance Surveillance Plan (QASP), Attachment 1.
14.0 OTHER CONDITIONS/REQUIREMENTS
14.1 EARNED VALUE MANAGEMENT (EVM)
No EVM implementation required. The Common Submarine Radio Room IPT utilizes data provided by the contractor to develop independent EVM report.
14.2 GOVERNMENT FACILITIES
Work performed in Government facilities will include PITCO and shipping support.All Contractor personnel with supplied government facilities shall be located at SSC Atlantic in Charleston, SC. Work under this order shall be performed during normal working hours when practical.
Pursuant to clause 5252.237-9602, when conversing with Government personnel during business meetings, over the telephone, or via electronic mail contractor and subcontractor personnel shall identify themselves as such to avoid situations arising where sensitive topics might be better discussed solely between Government employees. Contractors and subcontractors shall identify themselves on any attendance sheet or any coordination documents they may review. Electronic mail signatures shall identify company affiliation.
14.3 CONTRACTOR FACILITIES
The majority of this production requirement requires close liaison with the government. The contractor shall have a local facility within a thirty (30)-mile radius of the SPAWARSYSCEN Atlantic, Charleston, SC Building 3112. Close proximity allows for proper contract administration duties. The contractor’s facility is not necessary for the exclusive use of this contract and can be utilized on a shared basis. The Charleston local facility shall include sufficient physical security to protect government assets. The contractor’s facility shall meet all location and size requirements to perform work requirements within 30 days after delivery order award. Facility space shall include offices, conference rooms, lab work, and a staging area for materials and equipment, as required.
Work performed in Contractor facilities will include all activities in support of material receipt, inspection, kitting, packaging, and handling.
14.4 KEY PERSONNEL
As specified in basic contract Clause 5252.237-9601, Key Personnel will be identified at the delivery order level. The résumé for any proposed individual qualifying for the cited labor category is subject to COR approval prior to the individual charging to this requirement. Contractor shall submit the required resume no later than 10 days after DO award. The contractor shall track and maintain a list of Key Personnel in the Staffing Plan which is part of the monthly Delivery Order Status Report
(DOSR) CDRL.
15.0 LIST OF ATTACHMENTS
Attachment 1 – Quality Assurance Surveillance Plan (QASP) Attachment 2 – Consolidated Government Furnished Property Attachment 3 - EVM/Schedule/Meeting Information Attachment 4 – CDRLs
Contract Number: TBD Date: TBD
Delivery Order/Task Order (DO/TO): 0001
Unsatisfactory
Marginal
Satisfactory
Very Good
Exceptional
CPARS Group
Task
Objectives
Acceptable Quality Level (AQL)
Applic Y N
Method of
Surveillance
Quality of Product
#1
DEFECTS PER
MILLION
OPPORTUNITIES
(DPMO)
DPMO greater than or equal to
3.5 sigma
X
Measures final quality based on opportunities for defects identified in production planning versus findings at
Government acceptance.
(Number of Defects x 1,000,000) / (Number of units x Number of
Opportunities)
DPMO less than
2 sigma
DPMO greater than or equal to 2 sigma and less than 3 sigma
3 sigma and less than 3.5
3.5 sigma and less than 4 sigma than or equal to 4
(CPFF DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected with no additional fee
(CPIF DO/TO) REMEDY
Rework until corrected fee reduced by.5% for each instance
(FFP DO/TO) REMEDY
FOR AQL PROBLEMS
with no change in price
(FPI DO/TO) REMEDY
Delivery Order/Task Order (DO/TO): 0001 Unsatisfactor y
Marginal
Satisfactory
Very Good
Exceptional
Method of Surveillance
Product
#2
PMP
PMP includes all 15 elements identified in the method of surveillance
AND
Demonstrates an innovative approach in at least one section
Government will verify the following at project plan review:
Correct revision of PMP
Referenced corporate and project documents are attached
IMS is included
Production Plan
- IDs Unit
- Includes layout with flow
- Procedures identified/developed)
Quality Plan
- Includes FAI Approach,
- Includes Receipt
Inspection approach
- Explains Supplier
Management/evaluation
- Procedures/Checklists identified/developed
- In Process QC checks identified/discussed
- Final QC checks identified/discussed
- Sampling Approach) identified
Risk
- Process developed
- Risk matrix developed
PMP includes 13 or less elements identified in the method of
PMP includes 14 elements identified in the
PMP includes all 15 elements identified in the identified in the
Demonstrates an innovative approach in on section identified in the
Demonstrates an innovative approach in two or more sections
(CPFF DO/TO) REMEDY
with no additional fee
Rework until corrected fee reduced by.5% for each instance
FOR AQL PROBLEMS
Delivery Order/Task Order (DO/TO): 0001 Unsatisfactory Marginal Satisfactory Very Good Exceptional
CPARS Group Task Objectives Applic Method of 1 2 3 4 5 Acceptable Quality Level (AQL) Y N Surveillance
% ON TIME
PRODUCT
DELIVERY
Greater than or equal to 96% on time product delivery
Based on meeting the milestone called out in an IMS: Number of "on time" deliveries /
Number of total deliveries
Customer requirements changes affecting schedule will prompt an acceptable schedule shift.
Contractor will be measured based on meeting the new %
ON TIME PRODUCT
DELIVERY milestone date.
In the case that a
PRODUCT DELIVERY
milestone date(s) changes due to contractor causes, the contractor will be measured against the original PRODUCT
DELIVERY milestone date(s).
Less than 90% on time product delivery
Greater than or equal to 90% on time product delivery and less than 95% on time product delivery equal to 95% on time product delivery and less than 96% on time equal to 96% on time product delivery and less than 99% on time equal to 99% on time product delivery
(CPFF DO/TO) REMEDY
FOR AQL PROBLEMS
PCO to negotiate "consideration" to reduce adverse impact to mission
PCO to negotiate "consideration"
FOR AQL PROBLEMS
PCO to negotiate "consideration"
PCO to negotiate "consideration"
CPARS Group Task Objectives Applic Method of 1 2 3 4 5 Acceptable Quality Level (AQL) Y N Surveillance
Cost Control
OVERALL COST
VARIANCE
Less than or equal to 100% of target cost
Round to closest %
(Planned Material costs - Actual Material costs ) / Actual Material costs (for a reporting period) equal to 105% of
Greater than 100% of target cost and less than 105% of target cost
Less than or equal to 100% of equal to 95% target cost and less than 98%
WITH
Justification of cost-savings improvements to project
Less than 95% target
WITH
Justification of cost-savings improvements to project
(CPFF DO/TO)
(CPIF DO/TO)
(FFP DO/TO)
(FPI DO/TO)
Method of
Surveillance
Business Relations
Conformance to management system
No more than 1 minor nonconformances with the CAEI management system resulting in a corrective action
Number of nonconformances to the management
2 or more major nonconformances with the CAEI
*A major non-conformance is one with systemic impact
1 major with the CAEI
*A major non-one with systemic impact
2 or more minor with the CAEI management system resulting in a corrective action
*A minor non-one without systemic impact
1 minor with the CAEI management system resulting in a corrective action
0 minor with the CAEI
CAEI Standard Monthly CPARS Draft Approval Document (CDAD)
Contractor Number:
TBD
Delivery Order/Task Order Number (DO/TO):
Reporting Month: Date:
CPARS
GROUP
TASK
MONTHLY CONTRACTOR INPUT
CALCULATED
RATING
CONTRACTOR
INPUT
COR INPUT
RATIONALE COMMENTS
DEFECTS PER
DPMO greater than or (Number of Defects x 1,000,000) / DPMO < 2 Sigma = 1 equal to 3.5 Sigma (Number of units x Number of
Opportunities) DPMO > 2 Sigma & < 3 Sigma = 2 DPMO > 3 Sigma & < 3.5 Sigma = 3 DPMO > 3.5 Sigma & < 4 Sigma = 4(CPFF DO/TO) REMEDY FOR AQL
PROBLEMS Rework until corrected with no additional fee
(CPIF DO/TO) REMEDY FOR AQL
PROBLEMS Rework until corrected fee reduced by.5% for each instance
DPMO > 4 Sigma = 5
MILLION
Measures final quality based on OPPORTUNITIE
S (DPMO) (FFP DO/TO) REMEDYFOR AQL
PROBLEMS Rework until corrected with no change in price
(FPI DO/TO) REMEDY FOR AQL
PROBLEMS Rework until corrected with no change in price opportunities for defects identified in production planning versus findings at Government acceptance
PMP
PMP includes all 15 elements identified in the method of surveillance
AND
Demonstrates an innovative approach in at least one section
(Measure based upon elements identified and innovative approach)
PMP includes <13 elements identified = 1 PMP includes <14 elements identified = 2 PMP includes <15 elements identified = 3
PMP includes all 15 elements identified & Demonstrates 1 innovative approach = 4
PMP includes all 15 elements identified & Demonstrates 1 innovative approach in 2 + approach sections = 5
Government will verify the following at project plan review:
Correct revision of PMP
Referenced corporate and project documents are attached
IMS is included Production Plan
‐ IDs Unit ‐ Includes layout with flow
‐ Procedures identified/developed) Quality Plan
‐ Includes FAI Approach, ‐ Includes Receipt Inspection approach
‐ Explains Supplier Management/evaluation
‐ Procedures/Checklists identified/developed ‐ In Process QC checks identified/discussed
‐ Final QC checks identified/discussed ‐ Sampling Approach) identified
Risk
Product or Service (CPFF DO/TO) REMEDY FOR AQL
PROBLEMS Rework until corrected with no additional fee
(CPIF DO/TO) REMEDY FOR AQL
PROBLEMS Rework until corrected fee reduced by.5% for each instance
(FFP DO/TO) REMEDY FOR AQL
PROBLEMS Rework until corrected with no change in price
(FPI DO/TO) REMEDY FOR AQL
PROBLEMS Rework until corrected
Product or
Service ‐ Process developed ‐ Risk matrix developed
Documents
Weight of Documents Due Weight of Documents Delivered
% Weight of Compliant Documents
% ON TIME
PRODUCT
DELIVERY
Greater than or equal to 96% on time product delivery
(Measure based upon % of product delivered on time)
% OTPD < 90% = 1
% OTPD > 90% BUT < 95% = 2
% OTPD > 95% BUT < 96% = 3
% OTPD > 96% BUT < 99% = 4
% OTPD > 99% = 5
Based on meeting the milestone called out in an IMS: Number of "on time" deliveries / Number of total deliveries
Customer requirements changes affecting schedule will prompt an acceptable schedule shift. Contractor will be measured based on meeting the new % ON TIME PRODUCT DELIVERY milestone date.
In the case that a PRODUCT DELIVERY milestone date(s) changes due to contractor causes, the contractor will be measured against the original PRODUCT
DELIVERY milestone date(s).
(CPFF DO/TO) REMEDY FOR AQL
PROBLEMS PCO to negotiate "consideration" to reduce adverse impact to mission
(CPIF DO/TO) REMEDY FOR AQL
PROBLEMS PCO to negotiate "consideration" to reduce adverse impact to mission
(FFP DO/TO) REMEDY FOR AQL
PROBLEMS PCO to negotiate "consideration" to reduce adverse impact to mission
(FPI DO/TO) REMEDY FOR AQL
PROBLEMS PCO to negotiate "consideration" to reduce adverse impact to mission
COST
CONTROL
OVERALL COST
VARIANCE
(OCV)
Less than or equal to 100% of target cost Round to closest %
(Rounded to the closest %) CV > 105% of target cost = 1 CV > 100% BUT < 105% of target cost =2 CV < 100% of target cost =3 CV > 95% BUT < 98% of target cost WITH Justification of cost savings improvements to project =4 CV < 95% of target cost WITH Justification of cost savings improvements to project =5
(Planned Material costs ‐ Actual
Material costs ) / Actual Material costs (for a reporting period)
(CPFF DO/TO)
(CPIF DO/TO)
(FFP DO/TO)
(FPI DO/TO)
Business Relations
Conformance to management system
GOAL : No more than 1 minor nonconformance (NC) with the CAEI management system resulting in a corrective action
((Measure based upon Nonconformance(s))
Number of nonconformance (NC) to the management system
2(+) major NC with the CAEI management system =1 1 major NC with the CAEI management system =2 2(+) minor NC with the CAEI management system resulting in a corrective action (CA) =3 1 minor NC with the CAEI management system resulting in a corrective action
(CA) =4
0 minor NC with the CAEI management system =5
*A major non‐conformance is one with systemic impact
Consolidated GFP Attachment Version 1.0
Government Furnished Property
Attachment Number 2
Attachment File 1 of 1
Attachment Date 2017‐03‐16
Government Contracting Officer
Name TBD Email Phone
● Contract Award Contract Modification OR Solicitation Amendment
Modification Number Amendment Number
Reference Procurement Instrument Number
Custodial Procurement Instrument Identification
Solicitation, Contract or Uniform PIID Number Order Number (PIID Format FY16+)
Issuing Office DoDAAC
Issue Year
(YY)
Contract Type
Sequence Number
Issuing Office DoDAAC
Issue Year
(YY)
Contract Type
Sequence
Number OR Old Format
N65236 15 R 0010
Reset Form Validate
Government Furnished Property
ADD SERIALLY MANAGED ITEMS LIST
Line Number
Item Name Item Description NSN CAGE Part
Model Number
Serial Number UII QTY
Unit of Measure
Unit Cost Use As Is
Delivery Date (On or Before)
Duration Time Unit Delivery Event Notes
ADD NON‐SERIALLY MANAGED ITEMS LIST
Number
Model Number QTY
1 ADNS AN/USQ‐144K(V)3 55910
0205982‐02
1 Each 318,243.0 FALSE
Delivery Date (On or Before)
Duration Time Unit Delivery Event Notes
2018‐06‐30
Line Number Item Name Item Description NSN CAGE
Part
Number
Model Number QTY
Unit of Measure
Unit Cost Use As Is
2 NMT AN/BSC‐3(V)3 and IKEE (CG) (V)3 7Y193 H417644‐3 1 Each 513,000.0 FALSE
Delivery Date (On or Before)
Duration Time Unit Delivery Event Notes
2018‐06‐30
Line Number Item Name Item Description NSN CAGE
Part
Number
Model Number QTY
Unit of Measure
Unit Cost Use As Is
3 SLVR AN/WRR‐12B 50225
AN/
WRR‐12B
1 Each 280,000.0 FALSE
Delivery Date (On or Before)
Duration Time Unit Delivery Event Notes
2018‐06‐30
Remove
Remove
Remove
QTY
4 CUE ON‐730(V)15/U 55910 0205759‐10 1 Each 230,000.0 FALSE
2018‐06‐30
Item Name Item Description NSN CAGE
Part Number
Model
5 RFDACS OK‐664(V)18 50225 06912020‐1 1 Each 750,000.0 FALSE
Number
Model Number QTY
6 Thin Client Z00D, 2GF/2GR, 2s1P, USB 65128 909692‐68L 2 Each 535.00 FALSE
Number
Model Number QTY
7 Circuit Card
Assembly Heat Exchanger CCA 29355
537029‐00
9 Each 1,025.00 FALSE
Remove
8 TFDS Slave AN/BSQ‐9(V)4 03NF8 001‐0053 1 Each 70,912.00 FALSE
Item Name Item Description NSN CAGE
Part Number
Model
9 Power Supply KY‐99A Power Supply 80058 HYP‐57/TSEC 6 Each 300.00 FALSE
Number
Model Number QTY
10 Laser Jet Printer Laser Printer – Refer to PLAR‐16‐P00103 29355 43150‐CSRR‐PTR‐002 1 Each 325.00 FALSE
Number
Model Number QTY
11 Display Display (General Digital) REV D 1JA77 90‐949‐002
‐D
4 Each 6,300.00 FALSE
Delivery Date (On or Before)
Duration Time Unit Delivery Event Notes
2018‐06‐30
Remove
Remove
Measure
12 GBS AN/USR‐10B(V)2 ACL 04071
R1002536‐
02A
1 Each 220,000.0 FALSE
Item Name Item Description NSN CAGE
Part Number
Model
13 Scanning Receiver CDR‐3280 59532 260001‐13 1 Each 36,249.00 FALSE
Number
Model Number QTY
14 AIS AN/URN‐31 3CX85
20706481‐
1 Each 400,000.0 FALSE
Number
Model Number QTY
Offline Encryption Device
AN/PYQ‐20 (V)2 621Q4 1000084 1 Each 9,000.00 FALSE
Remove
Number Item Name Item Description NSN CAGE
Part Number
01‐P45710F600
Model
QTY
Number Unit of
Unit Cost Use As Is Measure
16 DMR RT‐1799B(P)/(C)/USC‐61 (C), IW/MUOS 1VPW8
1 Each 425,000.0 FALSE
Item Name Item Description NSN CAGE
Part Number
Model
17 HF Power Amplifier AM‐7625/USC‐61(C) 94987 351000 1 Each 100,000.0 FALSE
Number
Model Number QTY
VHF/UHF Power Amplifier
AM‐7584D/USC61(C) Amplifier, Radio
1VPW8 27000‐4 3 Each 75,000.00 FALSE
Number
Model Number QTY
19 EBEM MD‐1392/U EBEM 47358 0231358‐1 1 Each 25,000.00 FALSE
Items Authorized to be Requisitioned by the Contractor and Paid for by DoD
Number
QTY
Remove
Remove
ADD
Attachment – EVM/Schedule/Meeting Information
The following is submitted for refinement of tasking in relation to the Common Submarine Radio Room, Afloat Submarine C4I Production, Integration and Test (ASCP) Sub--‐Integrated Product Team (IPT).
1) CSRR Milestone Schedule
a) Due – Weekly
i) Meet with Project Controls Managers every Friday morning to discuss and update.
b) Type of information needed:
i) Feedback on calculated milestone dates
ii) Feedback on impact of changing dates
iii) Status when a milestone is actually started or finished
•Delivery Order is executed •Rack Integration / Kitting started •Packing Started •Kits / Equipment Staged
2) CSRR PITCO Schedule
a) Due – Weekly
i) Meet with Project Controls Managers every Friday morning to discuss and update
b) Type of information needed:
i) Installation of GFE into racks (start date)
ii) Installation of GFE into racks (finish date)
iii) Removal of GFE from racks (start date)
iv) Removal of GFE from racks (finish date)
v) Packing of GFE (start/finish)
vi) Shipping of GFE (start/finish)
vii) GFE delivered to platform finished
3) CSRR Harness/Cable Fab Report
a) Due – Weekly
i) Email report by Noon every Friday to the Project Controls Managers
b) Type of information needed:
i) List of all cables and harnesses expected to be built for each platform
ii) Expected duration and start date for fabrication
iii) Actual start date for the first cable or harness
iv) Actual finish date for the last cable or harness
v) Changes to the expected duration
4) CSRR Summary Schedule
a) Due – Weekly
i) Information to Project Controls Managers by 14:00 every Tuesday
b) Type of information needed:
i) Expected durations for various activities
ii) Projected changes in start and finish dates for various activities
iii) Actual start and finish dates for various activities
5) CSRR Detailed Project Schedules
i) Due – Original information will be drafted with Project Controls Managers upon completion of cost estimate in response to PWS
(1) Activities or tasks required to accomplish the Task Order / Work Request
(2) Activities or tasks durations, predecessors and successors
(3) Significant milestones for the Task Order / Work Request
b) Type of information needed:
i) Information needs emailed to Project Controls Managers by COB every Monday
c) Type of information needed:
i) Confirmation activities or tasks are on schedule
ii) If activities are not on schedule, a brief explanation
6) CSRR Weekly Schedule Report (Five Week Look-Ahead)
a) Due – Weekly
i) Information needs emailed to Project Controls Managers by 14:00 every Tuesday
b) Type of information needed:
i) Confirmation activities are on schedule
ii) If activities are not on schedule, a brief explanation
7) Outstanding Equipment & Material Report
a) Due - Before a Task Order / Work Request begins and Weekly thereafter
i) Information needs emailed to the Project Controls Managers
b) Type of information needed, sorted by Task Order / Work Request:
i) List of all equipment (2.1.1) to be purchased
ii) List of all material (2.1.3) to be purchased
iii) Whether the item being purchased was part of the original Task Order / Work Request or a particular mod
iv) Date ordered
v) Estimated Delivery Date
vi) Actual Delivery Date
vii) Unit Rate
viii) Quantity In the Estimate for the original Task Order / Work Request or a particular mod
ix) Quantity Ordered
x) Quantity Received
8) Earned Value Management Data
a) Information Due Before a Task Order / Work Request (or subsequent modification) Begins
i) Detailed estimate for both labor and material
ii) Spend plan/curve for both labor and material, by WBS
b) Type of information due monthly:
i) Labor cost: actual start and finish dates, cumulative expended by WBS
ii) Estimate at complete (for both labor and material), if substantially different than estimate, starting around 50% complete
iii) For Task Order / Work Request modifications, report monthly CTD labor by Mod number and WBS (we will not rebaseline)
9) Meeting required (overview)
a) Production (SSBN/SSGN/LA/VA) Weekly
b) Financial Weekly
c) Systems Integration Team. Weekly. As scheduled by NUWC.
d) Systems Engineering Team. Weekly. As scheduled by NUWC.
e) Others as requested by the government
10) Weekly Production Meeting
a) Type of information needed:
i) Schedule Status
ii) Cut-off date for PLAR’s
iii) List of PLAR’s, LAR’s, RLAR’s in the kit
iv) Cabling and Harnessing Material On
Order/Received
v) Mechanical Kits On Order/Received
vi) Cables and Harnesses Kitted for Fabrication
vii) Cables and Harnesses Returned from Fabrication
viii) Cable and Harness Percentage turned over to Government QA
11) Weekly Financial Meeting
a) Type of information needed:
i) Report of all open work orders/work requests
ii) Cost of PLAR’s, LAR’s, RLAR’s (over and above original work request estimate)
12) Network Access Required at a minimum
a) CnE
b) SE2
c) CIMS
17. PRICE GROUP
NSP
18. ESTIMATED
TOTAL PRICE
DD FORM 1423-1, FEB 2001 PREVIOUS EDITION MAY BE USED. Page of Pages
CONTRACT DATA REQUIREMENTS LIST
(1 Data Item)
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT C.CATEGORY: X CSRR GFI Drawing Issues
TDP TM OTHER
D. SYSTEM/ITEM
See BLK 16
E. CONTRACT/PR NO.
N65236-15-R-0010
F. CONTRACTOR
TBD
1. DATA ITEM NO.
T001
2. TITLE OF DATA ITEM
CSRR GFI Drawing Issues
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.)
DI-ILSS-80949
5. CONTRACT REFERENCE
PWS Paragraph 6.2.1, 6.2.2, 6.2.3
6. REQUIRING OFFICE
62200
7. DD 250 REQ
LT
9. DIST STATEMENT
REQUIRED
F
10. FREQUENCY
MONTHLY
12. DATE OF FIRST SUBMISSION
See BLK 16
14. DISTRIBUTION
a. ADDRESSEE
b. COPIES
8. APP CODE
N/A
11. AS OF DATE
SEE BLK 16
13. DATE OF SUBSEQUENT
SUBMISSION
Monthly on the 10th
Draft
Final
Reg Repro
16. REMARKS
BLK D: CSRR SSN-XXX NEW CONSTRUCTION EQUIPMENT, MATERIAL
AND PRE-CABLING MATERIAL
BLK 12: 30 DATO and monthly on the 10th
The contractor shall review Government Furnished drawings that shall be produced specifically for this task and shall provide recommendations for corrections to the COR for corrective action on a monthly basis. EXCEL format acceptable.
The CDRL shall be e-mailed to the addressees identified in BLK 14:
15. TOTAL 0 0 0
G. PREPARED BY
INLOW.ELSA.JANE.12526 Digitally signed by IN
DN: c=US, o=U.S. G
68353 ou=USN, cn=INLOW Date: 2017.03.20 07:
H. DATE
LOW.ELSA.JANE.1252668353
overnment, ou=DoD, ou=PKI, ELSA.JANE.1252668353
43:54 -04'00'
I. APPROVED BY
FAITH.STEVEN.TRAVIS. Digitally signed by FA
DN: c=US, o=U.S. G
1201350693 cn=FAITH.STEVEN.T Date: 2017.03.20 08:
J. DATE
ITH.STEVEN.TRAVIS.1201350693
overnment, ou=DoD, ou=PKI, ou=USN, RAVIS.1201350693
39:53 -04'00'
18. ESTIMATED
Form Approved OMB No. 0704-0188
The public reporting burden for this collection of information is estimated to average 110 hours per response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the collection of information. Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing the burden, to the Department of Defense, Executive Services and Communications Directorate (0704-0188). Respondents should be aware that notwithstanding any other provision of law, no person shall be subject to any penalty for failing to comply with a collection of information if it does not display a currently valid OMB control number. Please do not return your form to the above organization. Send completed form to the Government Issuing Contracting Officer for the Contract/PR No. listed in Block E.
A. CONTRACT LINE ITEM NO.
B. EXHIBIT C. CATEGORY: X See BLK 16
TDP TM OTHER
D. SYSTEM/ITEM
See BLK 16
E. CONTRACT/PR NO.
N65236-15-R-0010
F. CONTRACTOR
T002
CSRR Procurement Delivery Status Report
3. SUBTITLE
4. AUTHORITY (Data Acquisition Document No.) 5. CONTRACT REFERENCE
PWS Paragraphs 6.4.1.3, 6.4.2.3, 6.4.3.3
6. REQUIRING OFFICE
62200
7. DD 250 REQ
LT
WEEKLY
12. DATE OF FIRST SUBMISSION
8. APP CODE
N/A
11. AS OF DATE
SEE BLK 16
13. DATE OF SUBSEQUENT
SUBMISSION
COB every Friday
Draft
Final
Reg Repro
16. REMARKS
BLK C: CSRR Procurement Delivery Status Report
BLK D: CSRR SSN-XXX NEW CONSTRUCTION EQUIPMENT, MATERIAL
AND PRE-CABLING MATERIAL
BLK 12: COB first Friday after TO Award
The contractor shall generate weekly…