Contract Number: TBD Date: TBD
Delivery Order/Task Order (DO/TO): TBD Unsatisfactory Marginal Satisfactory Very Good Exceptional
CPARS Group Task Objectives Acceptable Quality Level (AQL)
Applic Y N
Method of Surveillance 1 2 3 4 5
Quality of Product
#1
DEFECTS PER
MILLION
OPPORTUNITIES
(DPMO)
DPMO greater than or equal to
3.5 sigma X
Measures final quality based on opportunities for defects identified in production planning versus findings at
Government acceptance.
(Number of Defects x 1,000,000) / (Number of units x Number of
Opportunities)
DPMO less than 2 sigma
DPMO greater than or equal to
2 sigma and less than 3 sigma
DPMO greater than or equal to
3 sigma and less than 3.5 sigma
DPMO greater than or equal to
3.5 sigma and less than 4 sigma
DPMO greater than or equal to 4 sigma
(CPFF DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected with no additional fee
X
(CPIF DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected fee reduced by.5% for each instance
X
(FFP DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected with no change in price
X
(FPI DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected with no change in price
X
Delivery Order/Task Order (DO/TO): TBD Unsatisfactor y Marginal Satisfactory Very Good Exceptional
CPARS Group Task Objectives Acceptable Quality Level (AQL)
Applic Y N Method of Surveillance 1 2 3 4 5
Quality of Product
#2
PMP
PMP includes all 15 elements identified in the method of surveillance
AND
Demonstrates an innovative approach in at least one section
X
Government will verify the following at project plan review:
Correct revision of PMP
Referenced corporate and project documents are attached
IMS is included
Production Plan
- IDs Unit
- Includes layout with flow
- Procedures identified/developed)
Quality Plan
- Includes FAI Approach,
- Includes Receipt
Inspection approach
- Explains Supplier
Management/evaluation
- Procedures/Checklists identified/developed
- In Process QC checks identified/discussed
- Final QC checks identified/discussed
- Sampling Approach) identified
Risk
- Process developed
- Risk matrix developed
PMP includes 13 or less elements identified in the method of surveillance
PMP includes 14 elements identified in the method of surveillance
PMP includes all 15 elements identified in the method of surveillance
PMP includes all 15 elements identified in the method of
Demonstrates an innovative approach in on section
PMP includes all 15 elements identified in the method of
Demonstrates an innovative approach in two or more sections
(CPFF DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected with no additional fee
X
(CPIF DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected fee reduced by.5% for each instance
X
(FFP DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected with no change in price
X
(FPI DO/TO) REMEDY
FOR AQL PROBLEMS
Rework until corrected
CPARS Group Task Objectives Acceptable Quality Level (AQL)
Applic Y N
Method of Surveillance 1 2 3 4 5
Schedule #1
% ON TIME
PRODUCT
DELIVERY
Greater than or equal to 96% on time product delivery X
Based on meeting the milestone called out in an IMS: Number of "on time" deliveries /
Number of total deliveries
Customer requirements changes affecting schedule will prompt an acceptable schedule shift.
Contractor will be measured based on meeting the new %
ON TIME PRODUCT
DELIVERY milestone date.
In the case that a
PRODUCT DELIVERY
milestone date(s) changes due to contractor causes, the contractor will be measured against the original PRODUCT
DELIVERY milestone date(s).
Less than 90% on time product delivery
Greater than or equal to 90% on time product delivery and less than 95% on time product delivery
Greater than or equal to 95% on time product delivery and less than 96% on time product delivery
Greater than or equal to 96% on time product delivery and less than 99% on time product delivery
Greater than or equal to 99% on time product
(CPFF DO/TO) REMEDY
FOR AQL PROBLEMS
PCO to negotiate "consideration" to reduce adverse impact to mission
X
(CPIF DO/TO) REMEDY
FOR AQL PROBLEMS
PCO to negotiate "consideration" to reduce adverse impact to mission
X
(FFP DO/TO) REMEDY
FOR AQL PROBLEMS
PCO to negotiate "consideration" to reduce adverse impact to mission
X
(FPI DO/TO) REMEDY
FOR AQL PROBLEMS
PCO to negotiate "consideration" to reduce adverse impact to mission
CPARS Group Task Objectives Acceptable Quality Level (AQL)
Applic Y N
Method of Surveillance 1 2 3 4 5
Cost Control #1
OVERALL COST
VARIANCE
Less than or equal to 100% of target cost
Round to closest %
X
(Planned Material costs - Actual Material costs ) / Actual Material costs (for a reporting period)
Greater than or equal to 105% of
Greater than 100% of target cost and less than 105% of target cost
Less than or equal to 100% of
Greater than or equal to 95% target cost and less than 98%
WITH
Justification of cost-savings improvements to project
Less than 95% target
WITH
Justification of cost-savings improvements to project
(CPFF DO/TO)
(CPIF DO/TO) X
(FFP DO/TO) X
(FPI DO/TO) X
Contract Number: Date: TBD
CPARS Group Task Objectives Acceptable Quality Level (AQL)
Applic Y N
Method of Surveillance 1 2 3 4 5
Business Relations
Conformance to management system
No more than 1 minor nonconformances with the CAEI management system resulting in a corrective action
Number of nonconformances to the management system
2 or more major nonconformances with the CAEI management system
*A major non-conformance is one with systemic impact
1 major nonconformances with the CAEI
*A major non-one with systemic impact
2 or more minor nonconformances with the CAEI management system resulting in a corrective action
*A minor non-one without systemic impact
1 minor nonconformances with the CAEI management system resulting in a corrective action one without systemic impact
0 minor nonconformances with the CAEI one without systemic impact
CAEI Standard Monthly CPARS Draft Approval Document (CDAD) Contractor Number: TBD Delivery Order/Task Order Number (DO/TO): TBD
Reporting Month:
Date:
CPARS
GROUP
TASK
MONTHLY CONTRACTOR INPUT
CALCULATED
RATING
CONTRACTOR
INPUT
COR INPUT
RATIONALE COMMENTS
Quality of Product or Service
Quality of Product or Service
DEFECTS PER
MILLION
OPPORTUNITIE
S (DPMO)
DPMO greater than or equal to 3.5 Sigma
(Number of Defects x 1,000,000) / (Number of units x Number of
Opportunities)
DPMO < 2 Sigma = 1 DPMO > 2 Sigma & < 3 Sigma = 2 DPMO > 3 Sigma & < 3.5 Sigma = 3 DPMO > 3.5 Sigma & < 4 Sigma = 4 DPMO > 4 Sigma = 5
Measures final quality based on opportunities for defects identified in production planning versus findings at Government acceptance
(CPFF DO/TO) REMEDY FOR AQL
PROBLEMS Rework until corrected with no additional fee
(CPIF DO/TO) REMEDY FOR AQL
fee reduced by.5% for each instance
(FFP DO/TO) REMEDYFOR AQL
with no change in price
(FPI DO/TO) REMEDY FOR AQL
PMP
PMP includes all 15 elements identified in the method of surveillance
AND
Demonstrates an innovative approach in at least one section
(Measure based upon elements identified and innovative approach)
PMP includes <13 elements identified = 1 PMP includes <14 elements identified = 2 PMP includes <15 elements identified = 3
PMP includes all 15 elements identified & Demonstrates 1 innovative approach = 4
PMP includes all 15 elements identified & Demonstrates 1 innovative approach in 2 + approach sections = 5
Government will verify the following at project plan review:
Correct revision of PMP Referenced corporate and project documents are attached IMS is included Production Plan
‐ IDs Unit ‐ Includes layout with flow
‐ Procedures identified/developed) Quality Plan
‐ Includes FAI Approach, ‐ Includes Receipt Inspection approach
‐ Explains Supplier Management/evaluation ‐ Procedures/Checklists identified/developed ‐ In Process QC checks identified/discussed
‐ Final QC checks identified/discussed ‐ Sampling Approach) identified
Risk ‐ Process developed
‐ Risk matrix developed
(CPFF DO/TO) REMEDY FOR AQL
with no additional fee fee reduced by.5% for each instance
(FFP DO/TO) REMEDY FOR AQL
(FPI DO/TO) REMEDY FOR AQL
Documents
Weight of Documents Due Weight of Documents Delivered
% Weight of Compliant Documents
Schedule
% ON TIME
PRODUCT
DELIVERY
Greater than or equal to 96% on time product
(Measure based upon % of product delivered on time)
% OTPD < 90% = 1
% OTPD > 90% BUT < 95% = 2
% OTPD > 95% BUT < 96% = 3
% OTPD > 96% BUT < 99% = 4
% OTPD > 99% = 5
Based on meeting the milestone called out in an IMS: Number of "on time" deliveries / Number of total deliveries
Customer requirements changes affecting schedule will prompt an acceptable schedule shift. Contractor will be measured based on meeting the new % ON TIME PRODUCT DELIVERY milestone date.
In the case that a PRODUCT DELIVERY milestone date(s) changes due to contractor causes, the contractor will be measured against the original PRODUCT
DELIVERY milestone date(s).
(CPFF DO/TO) REMEDY FOR AQL
PROBLEMS PCO to negotiate "consideration" to reduce adverse impact to mission
PROBLEMS PCO to negotiate
(FFP DO/TO) REMEDY FOR AQL
(FPI DO/TO) REMEDY FOR AQL
COST
CONTROL
OVERALL COST
VARIANCE
(OCV)
Less than or equal to 100% of target cost Round to closest %
(Rounded to the closest %) CV > 105% of target cost = 1 CV > 100% BUT < 105% of target cost =2 CV < 100% of target cost =3 CV > 95% BUT < 98% of target cost WITH Justification of cost savings improvements to project =4 CV < 95% of target cost WITH Justification of cost savings improvements to project =5
(Planned Material costs ‐ Actual Material costs )
/ Actual Material costs (for a reporting period)
(CPFF DO/TO)
(CPIF DO/TO)
(FFP DO/TO)
(FPI DO/TO)
Business Relations
GOAL : No more than 1 minor nonconformance (NC) with the CAEI management system resulting in a corrective action
((Measure based upon Nonconformance(s))
Number of nonconformance (NC) to the management system
2(+) major NC with the CAEI management system =1
Conformance to management system
1 major NC with the CAEI management system =2 2(+) minor NC with the CAEI management system resulting in a corrective action (CA) =3 1 minor NC with the CAEI management system resulting in a corrective action
(CA) =4
0 minor NC with the CAEI management system =5
*A major non‐conformance is one with systemic impact