Amendment_0005_RFP_N64498-19-R-4018.pdf

PDF 161 KB Posted

Attached to
Shipboard Habitability Ship Systems Alteration Development / Installation Federal contract opportunity
Solicitation number
N64498-19-R-4018
Issued by
Department of the Navy Naval Sea Systems Command

About this file

This document is an amendment to a solicitation for shipboard habitability and ship systems alteration development and installation services. The amendment extends the response due date from April 4, 2019 to April 18, 2019 to allow offerors to adjust their technical and cost proposals based on clarifications provided. Specifically, the amendment clarifies that firm-fixed-price subcontractors are not required to provide information on accounting systems or financial data. Additionally, all contractor personnel assigned to the contract must possess a personnel security clearance of confidential level, though requirements may increase to the secret level at the task order stage. The solicitation is being conducted by the Department of the Navy Naval Sea Systems Command for shipboard habitability and ship systems alteration development and installation efforts.

Amendment 0005

View the file

Other files for this federal contract opportunity

Other files attached to Shipboard Habitability Ship Systems Alteration Development / Installation, newest first.
File Type Posted
Amendment_0004_RFP_N64498-19-R-4018.pdf PDF
DD254_rev_1_HAB_19-R-4018.pdf PDF
Amendment_0003_RFP_N64498-19-R-4018.pdf PDF
Amendment_0002_RFP_N64498-19-R-4018.pdf PDF
Amendment_0001_RFP_N64498-19-R-4018.pdf PDF
CDRL_A005_Condition_Found_Report_(Approved).pdf PDF
CDRL_A006_Contract_Delivery_Order_Status_Report_5Apr17_(Approved).pdf PDF
CDRL_A001_Contract_Status_Report_Burton_5Apr17_(Approved).pdf PDF
CDRL_A020_Red-lined_Drawings_Burton_26Apr17_(Approved).pdf PDF
CDRL_A013_Pre-Start_CFM_Warehouse_Inventory_Report_Burton_25Apr17_(Approved).pdf PDF
CDRL_A007_Visit_Clearance_Data_Burton_5Apr17_(Approved).pdf PDF
DD254_-_HAB_19-R-4018.pdf PDF
CDRL_A024_Lessons_Learned_Report_Burton_2May17_(Approved).pdf PDF
CDRL_A015_Personnel_Qualifications-Certifications_25Apr17_(Approved).pdf PDF
CDRL_A014_Gantt_Chart_Plan_of_Action__Milestones_Burton_25Apr17__(Approved).pdf PDF
CDRL_A016_Prefabrication_Schedule_Burton_25Apr17_(Approved)_rev.pdf PDF
Attachment_1_-_Direct_Labor_Rate_Substantiation_Sample_Format_Chart.xls XLS spreadsheet
CDRL_A004_Contractor_Personnel_Roster_Burton_5Apr17_(Approved).pdf PDF
CDRL_A002_Contracting_Officer's_Management_Report_Burton_2May17_(Approved).pdf PDF
CDRL_A003_Travel_Trip_Report_Burton_5Apr17_(Approved).pdf PDF
CDRL_A012_Pre-Start_GFE_Warehouse_Inventory_Report_Burton_25Apr17_(Approved).pdf PDF
CDRL_A023_Post-Project_CFM_Warehouse_Inventory_Report_Burton_2May17_(Approved).pdf PDF
Attachment_2_-Cost_Summary_Sample_Format_Chart.xls XLS spreadsheet
Attachment_3_Declaration_of_Non-Collusion_Certification.docx DOCX document
CDRL_A008_Survey_Report_Burton_5Apr17_(Approved).pdf PDF
CDRL_A009_Preliminary_CAD_Drawings_Files_Burton_5Apr17_(Approved).pdf PDF
CDRL_A010_Corrected_CAD_Drawings_Files_Burton_5Apr17_(Approved).pdf PDF
CDRL_A019_Weekly_Progress_Report_Burton_26Apr17_(Approved).pdf PDF
CDRL_A025_Financial_Completion_Report_Burton_2May17_(Approved).pdf PDF
CDRL_A022_Post-Project_GFE_Warehouse_Inventory_Report_Burton_2May17__(Approved).pdf PDF
CDRL_A017_In-Process_Control_Procedures_Burton_25Apr17_(Approved).pdf PDF
CDRL_A021_Shipboard_Industrial_Work_Completion_Report_Burton_2May17_(Approved).pdf PDF
CDRL_A011_Record_Purchase_Order_and_Delivery_Schedule_Burton_5Apr17_(Approved).pdf PDF
RFP_N64498-19-R-4018_Habitability.pdf PDF
CDRL_A018_Contractor_Quality_Assurance_Workbook_Burton_25Apr17_(Approved)_rev.pdf PDF
Show all 35

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

See description of Amendment on page 2.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Mar-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N64498-19-R-4018

X 9B. DATED (SEE ITEM 11)

08-Nov-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Mar-2019

CODE

NAVAL SURFACE WARFARE CENTER PHILA

CODE 0214, DAVID RHOADS

215-897-7702, DAVID.RHOADS@NAVY.MIL

5001 SOUTH BROAD STREET

PHILADELPHIA PA 19112

N64498 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N64498-19-R-4018

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

SUMMARY OF CHANGES

The following have been added by full text:

The purpose of Amendment 0005 is to provide Government answers to submitted questions and to extend the response due date.

As identified in Amendment 0004, the deadline for receipt of questions is 4:00PM, 22 March 2019. The Government makes no guarantee that questions received after this deadline will be answered.

The Request for Proposal (RFP) due date has been extended to no later than 4:00PM, 18 April 2019.

Questions and Answers:

Q47. NSWCPD answer A29 states the “Offeror must have one individual for each labor category that requires a current Secret Clearance …”. Answer A29 also removes the requirement for having a Security Clearance from eight (8) non-key labor categories.

The first paragraph in NSWCPD answer A30 states, “designated contractor personnel accessing classified information or material…must have and maintain a security clearance.”

The second paragraph in NSWCPD answer A30, however, conflicts with the answers in A29 because it states, “All contractor personnel assigned to this contract …shall…possess a personnel security clearance”… and that clearance requirements will be determined at the task order level. Please clarify this inconsistency. If a task order does NOT require accessing classified information or material, are contractor personnel required to have a clearance?

A47. Answer A29 provided through Amendment 0004 removed the requirement for having a current Secret Clearance, or Secret Clearance eligibility with in ninety (90) days after date of award from eight

(8) non-key labor categories. Although the Secret Clearance designation has been removed for these labor categories, as identified, in answer A30; all contractor personnel assigned to this contract and performing its required services on site shall be Unites States citizens only and possess a personnel security clearance.

A security clearance of Confidential is required for all contractor personnel. Clearance requirements will be determined at the task order level; whereas the confidential clearance may be increased to a secret clearance level.

Q48. With regard to NSWCPD answer A38 … the third paragraph of the response does not draw a distinction between firm-fixed-price (FFP) subcontractors and other subcontractor types (e.g. Cost-reimbursement, flexibly-priced, time & materials, or labor hours). Please confirm that:

N64498-19-R-4018

a. FFP subcontractors do NOT need to provide evidence of an adequate accounting system.

b. FFP subcontractors are NOT required to provide information in accordance with sub-paragraphs a) through o) of answer A38.

A48. Answer A38 provided through Amendment 0004 identifies in the first paragraph that both prime contractors and subcontractors are required to have an adequate accounting system for proposed contract types which are not firm-fixed-price.

a. FFP subcontractors do NOT need to provide evidence of an adequate accounting system is an accurate statement.

b. As FFP subcontractors are not required to provide evidence of an adequate accounting system the information in sub-paragraphs a) through o) of answer A38 is not applicable.

Q49. Additionally, with regard to the change made in the solicitation on this subject, recommend L.3.8.4, 2nd paragraph below “Approved Accounting System” be modified to add (just prior to sub-paragraphs a) through o) the following note: “These requirements to NOT apply to proposed FFP subcontractors”.

A49. As incorporated through answer A38 issued through Amendment 0004, an adequate accounting system is not required for FFP prime contractors and FFP subcontractors.

Q50. Please extend the closing date (at a minimum) from 4/4/2019 to 4/19/2019 to allow sufficient time to make Technical and Cost Proposal adjustments. Given the nature of the full scope of changes with respect to personnel security requirements and in particular the clarification of the term “major subcontractors”, and the resulting impact on Technical and Cost Proposal development – for both prime and non-FFP subcontractors.

A51. The RFP due date has been extended from 4:00PM 4/4/19 to 4:00PM 4/18/19.

Q52. Upon receiving Amendment 0004 and reviewing the answers provided, we request a 30 day extension to the submittal due date. Based on the answers concerning Accounting Systems and required Financial data, we will require additional time to compile the data from subcontractors and teaming partners.

A52. See answer 51.

(End of Summary of Changes)