This document outlines a federal solicitation for the fabrication, assembly, testing, and delivery of Vertical Launching System (VLS) Launch Control Units (LCU) MK 235 Mod 17, Mod 18, and associated equipment. Key requirements include the manufacture of LCUs according to technical drawings and specifications, as well as Maintenance Assistance Module kits, Onboard Repair Part kits, Installation and Checkout spares kits, and Depot spares kits for various LCU modifications. Offerors must submit pricing spreadsheets, past performance questionnaires, and technical proposals in response. The Naval Surface Warfare Center Port Hueneme Division will evaluate proposals and make award, with performance periods including a base year and four option years. Delivery locations are specified as destination for the hardware items.
View the file
Other files for this federal contract opportunity
Show all 26
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until 04:00 PM local time 04 Oct 2021
X
A X B X C X D
EX
X
G F 127 - 134
135 - 147 X H 148
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
DX-A3 1 154
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
N63394 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 0 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
N/A conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
1 - 4 5 - 62
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
63 - 84 85 - 87
J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
88 - 92 93 - 103
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 104 - 112 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 113 - 114 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
115 - 125
PART II - CONTRACT CLAUSES
NAVAL SURFACE WARFARE CENTER
4363 MISSILE WAY
PORT HUENEME CA 93043-4307
(805) 228-8287
805-228-6299FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.5. DATE ISSUED
18 Aug 2021
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
N6339421R0017
Section SF 30 - BLOCK 14 CONTINUATION PAGE
SOLICITATION AMENDMENT 1
The purpose of this amendment is to update the quantities required for Base Year, Option Year 1, Option Year 2, Option Year 3, and Option Year 4. As a result, attachment J-S-1 has been updated accordingly.
SOLICITATION AMENDMENT 2
Q&A
1. Question: RE: N6339421R0017_J-S-1_Pricing_Spreadsheet_Amendment+1, Page 136, “Volume I of the proposal shall include pricing spreadsheets for all CLINs, for all items (with options) as described in Section B. Spreadsheets shall be in Microsoft Excel format with cells containing working formulas that are visible for Government examination of price buildup and methodology. All pricing shall be proposed in whole dollars.” The Solicitation states suppliers are to assume there is adequate price competition and cost and/or pricing data is not required in accordance with FAR 15.403-1(b). The referenced comment seems to be in opposition to this statement. Are suppliers required to provide working excel sheets, showing the price build-up and methodology of how each CLIN’s unit price was formulated? This seems to be very similar to the requirements of cost and/or pricing data. Can’t the Government determine price reasonableness by comparing each Supplier’s proposal?
Answer: Attachment J-S-1_Pricing_Spreadsheets is to be used as a template for offerors to fill in pricing information as described in Section B. As stated in section L.2.4, on page 136, “If after receipt of proposals, the Contracting Officer determines that adequate price competition does not exist in accordance with FAR 15.403-1 or that only one offer is received, the Offeror shall provide certified cost and/or pricing data as requested by the Contracting Officer.” Certified Cost and/or pricing data is not required. Cost and pricing data, other than certified cost and pricing data is required.
2. Question: RE: Page 137, Section L.2.5., Factor 2 Past Perf (b). RFP Statement – “Include with your proposal submission a copy of the PPQ Cover Sheet.” Will the Government please exclude such pages from the page count?
Answer: The PPQ Cover Sheet will not be included in Volume II Technical (Non-Price) page count.
3. Question: RE: Pages 63 & 64, Section C.9.0 & C.12.2. SOW 12.2 Military Specifications and Standards appears to be a repeat of SOW 9.0 Technical Data Rights. Recommending removal of 12.2 and revising 9.0 to incorporate the last statement in 12.2.
Answer: SOW Section C.9.0 has been updated and SOW Section C.12.2 has been deleted to remove duplicated language. As a result, SOW Section 12 references in CDRL A005 as well as Sections L&M have been updated accordingly.
4. Question: Due to the delay in TDP release, will the Government grant a 3 week extension from receipts of the TDP for final proposal submission? (SEPT 20. 2021 + 3 weeks)
Answer: The Government grants a two-week extension for final proposal submission from 20 September 2021 to 4 October 2021.
5. Question: RE: Page 137, Section L.2.5, Factor 2 Past Perf (d). RFP Statement: “While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.” Will the Government allow the entire CPARS documentation (consisting of multiple pages) to be included as an attachment to the Vol. II Technical (Non- Price) Proposal and not included in the volume page count?
Answer: The CPARs documentation, which has been uploaded to CPARS, will not be included in Volume II, Technical (Non-Price) page count.
6. Question: RE: Page 68 Section C.16.1. If an offeror chooses to include full tabloid-size screenshots of the IMS as an attachment to the Volume II Technical, can they be excluded from the page count?
Answer: Figures and screenshots added as an attachment, will not be included in Volume II Technical (Non-Price) page count.
7. Question: RE: Page 135, Section L.2.3. The disposition of Technical Data Package and Technical Drawings paragraph states that Offerors should not transfer the data by any means to a third party.
a. Can an Offeror provide access to the TDP to its subcontractor’s with whom it is seeking quotes?
b. If an Offeror cannot provide the TDP to its subcontractors, does every subcontractor of every
Prime Offeror have to request a TDP CD from NSWWC PHD.
Answer: The Offeror can provide the TDP to subcontractors as long as the subcontractor has an active Joint Certification Program (JCP) certification. Certifications are searchable on the following DLA site:
https://public.logisticsinformationservice.dla.mil/jcp/search.aspx
8. Question: Does the solicitation TDP take into account any current waivers, NORs, deviations or variances for the current production?
Answer: The TDP provided with the solicitation is the approved TDP for this procurement. The awardee can submit any applicable waivers, deviations or variances for review and approval by the Government during post-award.
9. Question: RE: Page 135, Section L.2.3. For any solicitation sections with “Offeror Fill-Ins” or request for other information or data, should Offeror include in the Volume I Price Proposal only the specific RFP page as filled-in or the complete Section containing such RFP pages as filled in?
Answer: Specific RFP page is acceptable as long as the RFP page and corresponding clause number is clear and visible in the proposal.
10. Question: RE: GFP ATT J-3 provided in PDF does not include all of the information in the Notes column.
Please clarify statements in the Notes section for each listed item.
Answer: Attachment J-3 GFP Attachments has been updated to fully show the notes.
11. Question: RE: Pages 4-58 Section B, Pages 85-86 Section E, Pages 90-99 Section F. Section B, Section E and Section F list “Destination” as FOB, INSPECT AT and ACCEPT AT. Request all to be updated to be
ORIGIN.
Answer: The Government’s requirement is to deliver with FOB Destination terms. However, inspection and acceptance with be at orign and performed by DCMA. Inspection and Acceptance information will be updated upon award based on Contractor’s place of performance.
12. Question: RE: Page 64 Section C.12.2. SOW para 12.2 (Technical Data Rights) states “The Contractor shall prepare the updated drawings, specifications and all related documents with revisions, including the RFV.” There is also a clause C-243-H003.c that seems to align to this language. Is the Contractor expected to generate NORs and ECPs for this Build to Print contract?
Answer: No, the contractor will not be expected to generate NORs or ECPs. The contract is build-to-print.
If NORs or ECPs are required, the Government will provide them.
13. Question: Is this project considered a new requirement? If this project is not considered a new requirements, who is the incumbent? What was the contract number?
Answer: Yes, this solicitation is considered a new requirement.
14. Question: RE: TDP-MOD 18. 8652182-9 is required by the VLS LCU MOD 18 console as well as the MOD 15 and 18 kits however the provided TDP did not contain a DWG or PL for this assembly. Please provide missing files.
Answer: The Government will provide P/N 8652182-9 as Government Furnished Equipment (GFE), if needed.
15. Question: RE: TDP – MOD 17 & 18. A revision comparison between the provided MOD 17 and MOD 18 TDP folders resulted in 17 revision differences. The below table outlines these differences (revisions are base + NOR # if applicable). Are contractors expected to maintain the down revs of MOD 17 or are we expected to use the highest REV provided for both MODs?
Answer: Offerors are to use the latest MOD version.
Section B - Supplies or Services and Prices
NOTE A
Stepladder Pricing. Stepladder pricing is utilized in this solicitation to provide Offerors an opportunity to propose different pricing for separate quantity ranges within applicable Contract Line Items (CLINs). Price evaluation of step ladder CLINs will utilize a randomly selected quantity. Notwithstanding the option to propose different unit pricing for different quantities, the Offeror may propose the same unit price for all quantities.
For all option CLINs with stepladder pricing, the Government may unilaterally exercise a given line item more than once. Option CLINs with stepladder pricing may be exercised until the total quantity purchased equals the maximum quantity listed for that option CLIN in Section B.
(End of Text)
NOTE B
The following table provides the approximate timeframes that the CLINs and associated SLINs, where applicable, will be awarded or exercised. This information is provided for planning purposes only and is subject to change depending on need and funding availability.
Deliverable CLINs and Award/Option Exercise Timeframe
Award/Base Year*
Option Year 1 Option Year 2 Option Year 3 Option Year 4
VLS MK 235 LCU MOD 17 & 18 CLIN 1000 CLIN 1100 CLIN 1200 CLIN 1300 CLIN 1400
VLS MK 235 LCU MAM Components CLIN 2000 CLIN 2100 CLIN 2200 CLIN 2300 CLIN 2400
VLS MK 235 LCU OBRP Components CLIN 3000 CLIN 3100 CLIN 3200 CLIN 3300 CLIN 3400
VLS MK 235 LCU INCO Spares CLIN 4000 CLIN 4100 CLIN 4200 CLIN 4300 CLIN 4400
VLS MK 235 Depot Spares CLIN 5000 CLIN 5100 CLIN 5200 CLIN 5300 CLIN 5400
Production Readiness Review (PRR) CLIN 6000 CLIN 6100 CLIN 6200 CLIN 6300 CLIN 6400
Physical Configuration Audit (PCA) CLIN 7000 N/A N/A N/A N/A
Data Deliverables - CDRLs CLIN 8000
*CLINS 1000, 2000, 3000, 4000, 5000, and 6000 will be funded at award.
NOTE C
MAXIMUM QUANTITY MULTIPLE OPTION QUANTITY CLINS
CLINs, SLINs or other provisions in this contract set forth option quantities associated with option exercise periods.
Offerors should use those estimated quantities for planning purposes and in the preparation of its proposals including its price proposal. After award of the contract the Government may need to move quantity between these option CLINs. The contract resulting from this solicitation will have a maximum dollar value or a maximum number of units that may be purchased. The Government, may, through contract modification, move quantities of items labor or estimated costs between the option CLINs as long as the contract maximum is not exceeded.
If pricing varies by option exercise period the pricing applicable is the pricing applicable when the option is exercised. For example, items moved from option year four to option year one will be payable at the rates applicable to option year one.
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
MK 235 LCU Base Year (BY)
FFP
Procure, fabricate, assemble and conduct First Article Inspection (FAI) and Physical Configuration Audit (PCA) in accordance with (IAW) Statement of Work (SOW) sections 4.2 and 6.0 respectively. Refer to CDRLs for item and data requirements.
NET AMT
1000AA 6 Each
MK 235 MOD 17 LCU BY
FFP
Procure, fabricate, assemble and conduct FAI and PCA IAW SOW 4.2 and 6.0 respectively, Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
DWG NR: 7104280-179
PSC CD: 5999
1000AB 12 Each
MK 235 MOD 18 LCU BY
FFP
Procure, fabricate, assemble and conduct FAI and PCA IAW SOW 4.2 and 6.0 respectively, Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
DWG NR: 7104280-189
MK 235 LCU Option Year 1 (OY1)
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and Technical Data Package (TDP). Refer to CDRLs for item and data requirements.
1100AA Each
OPTION MK 235 MOD 17 LCU OY1
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
STEPLADDER PRICING
STEPLADDER NAME ITEM NO FROM QUANTITY TO QUANTITY UNIT PRICE
MK 235 MOD 17 LCU OY1 1100AA 6.00 10.00
11.00 14.00
15.00 18.00
1100AB Each
OPTION MK 235 MOD 18 LCU OY1
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
MK 235 MOD 18 LCU OY1 1100AB 6.00 10.00
MK 235 LCU Option Year 2 (OY2)
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
1200AA Each
OPTION MK 235 MOD 17 LCU OY2
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
MK 235 MOD 17 LCU OY2 1200AA 6.00 10.00
1200AB Each
OPTION MK 235 MOD 18 LCU OY2
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
MK 235 MOD 18 LCU OY2 1200AB 6.00 10.00
MK 235 LCU Option Year 3 (OY3)
FFP
1300AA Each
OPTION MK 235 MOD 17 LCU OY3
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
MK 235 MOD 17 LCU OY3 1300AA 6.00 10.00
1300AB Each
OPTION MK 235 MOD 18 LCU OY3
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
FOB: Destination
MK 235 MOD 18 LCU OY3 1300AB 6.00 10.00
MK 235 LCU Option Year 4 (OY4)
FFP
1400AA Each
OPTION MK 235 MOD 17 LCU OY4
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
MK 235 MOD 17 LCU OY4 1400AA 6.00 10.00
1400AB Each
OPTION MK 235 MOD 18 LCU OY4
FFP
Production Phase: Fabricate, assemble and deliver LCUs and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
MK 235 MOD 18 LCU OY4 1400AB 6.00 10.00
MK 235 LCU MAM Components BY
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data
2000AA 12 Set MK 235 MOD 11/12 LCU MAM Components BY
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
FOB: Destination
2000AB 8 Set MK 235 MOD 15 LCU MAM Components BY
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
2000AC 3 Set MK 235 MOD 17 LCU MAM Components BY
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
2000AD 6 Set MK 235 MOD 18 LCU MAM Components BY
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 LCU MAM Components OY1
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
2100AA Set OPTION MK 235 MOD 17 LCU MAM Components OY1
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU MAM
Components OY1
2100AA 3.00 5.00
6.00 8.00
2100AB Set OPTION MK 235 MOD 18 LCU MAM Components OY1
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU MAM
Components OY1
2100AB 3.00 5.00
6.00 9.00
MK 235 LCU MAM Components OY2
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
2200AA Set OPTION MK 235 MOD 17 LCU MAM Components OY2
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU MAM
Components OY2
2200AA 3.00 5.00
2200AB Set OPTION MK 235 MOD 18 LCU MAM Components OY2
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU MAM
Components OY2
2200AB 3.00 5.00
MK 235 LCU MAM Components OY3
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
2300AA Set OPTION MK 235 MOD 17 LCU MAM Components OY3
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU MAM
Components OY3
2300AA 3.00 5.00
2300AB Set OPTION MK 235 MOD 18 LCU MAM Components OY3
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU MAM
Components OY3
2300AB 3.00 5.00
MK 235 LCU MAM Components OY4
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
2400AA Set OPTION MK 235 MOD 17 LCU MAM Components OY4
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU MAM
Components OY4
2400AA 3.00 5.00
6.00 10.00
2400AB Set OPTION MK 235 MOD 18 LCU MAM Components OY4
FFP
Maintenance Assistance Module (MAM) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU MAM
Components OY4
2400AB 3.00 5.00
MK 235 LCU OBRP Components BY
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
3000AA 12 Set MK 235 MOD 11/12 LCU OBRP Components BY
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
3000AB 8 Set MK 235 MOD 15 LCU OBRP Components BY
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
3000AC 3 Set MK 235 MOD 17 LCU OBRP Components BY
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
3000AD 6 Set MK 235 MOD 18 LCU OBRP Components BY
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 LCU OBRP Components OY1
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
3100AA Set OPTION MK 235 MOD 17 LCU OBRP Components OY1
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU OBRP
OY1
3100AA 3.00 5.00
3100AB Set OPTION MK 235 MOD 18 LCU OBRP Components OY1
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU OBRP
OY1
3100AB 3.00 5.00
MK 235 LCU OBRP Components OY2
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
3200AA Set OPTION MK 235 MOD 17 LCU OBRP Components OY2
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU OBRP
OY2
3200AA 3.00 5.00
3200AB Set OPTION MK 235 MOD 18 LCU OBRP Components OY2
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU OBRP
OY2
3200AB 3.00 5.00
MK 235 LCU OBRP Components OY3
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
3300AA Set OPTION MK 235 MOD 17 LCU OBRP Components OY3
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU OBRP
OY3
3300AA 3.00 5.00
3300AB Set OPTION MK 235 MOD 18 LCU OBRP Components OY3
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU OBRP
OY3
3300AB 3.00 5.00
MK 235 LCU OBRP Components OY4
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated
3400AA Set OPTION MK 235 MOD 17 LCU OBRP Components OY4
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU OBRP
OY4
3400AA 3.00 5.00
3400AB Set OPTION MK 235 MOD 18 LCU OBRP Components OY4
FFP
Onboard Repair Part (OBRP) Production Phase: Fabricate, assemble and deliver LCU MAM and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU OBRP
OY4
3400AB 3.00 5.00
MK 235 INCO Spares BY
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data
4000AA 2 Set MK 235 MOD 11/12 LCU INCO Spares BY
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
4000AB 3 Set MK 235 MOD 15 LCU INCO Spares BY
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
4000AC 3 Set MK 235 MOD 17 LCU INCO Spares BY
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
4000AD 2 Set MK 235 MOD 18 LCU INCO Spares BY
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 INCO Spares OY1
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and
4100AA Set OPTION MK 235 MOD 17 LCU INCO Spares OY1
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU INCO
Spares OY1
4100AA 1.00 2.00
3.00 4.00
4100AB Set OPTION MK 235 MOD 18 LCU INCO Spares OY1
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 INCO
Spares OY1
4100AB 1.00 2.00
MK 235 INCO Spares OY2
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and
4200AA Set OPTION MK 235 MOD 17 LCU INCO Spares OY2
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU INCO
Spares OY2
4200AA 1.00 2.00
4200AB Set OPTION MK 235 MOD 18 LCU INCO Spares OY2
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 INCO
Spares OY2
4200AB 1.00 2.00
MK 235 INCO Spares OY3
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and
4300AA Set OPTION MK 235 MOD 17 LCU INCO Spares OY3
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU INCO
Spares OY3
4300AA 1.00 2.00
4300AB Set OPTION MK 235 MOD 18 LCU INCO Spares OY3
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 INCO
Spares OY3
4300AB 1.00 2.00
MK 235 INCO Spares OY4
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and
4400AA Set OPTION MK 235 MOD 17 LCU INCO Spares OY4
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU INCO
Spares OY4
4400AA 1.00 2.00
4400AB Set OPTION MK 235 MOD 18 LCU INCO Spares OY4
FFP
Installation and Checkout (INCO) spares kit.
Production Phase: Fabricate, assemble and deliver LCU INCO spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 INCO
Spares OY4
4400AB 1.00 2.00
MK 235 LCU Depot Spares BY
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and
5000AA 1 Set MK 235 Mod 11/12 LCU Depot Spares BY
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
5000AB 3 Set MK 235 Mod 15 LCU Depot Spares BY
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
5000AC 1 Set MK 235 Mod 17 LCU Depot Spares BY
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
5000AD 2 Set MK 235 Mod 18 LCU Depot Spares BY
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 LCU Depot Spares OY1
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and
5100AA Set OPTION MK 235 Mod 17 LCU Depot Spares OY1
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU Depot Spares OY1
5100AA 1.00 2.00
5100AB Set OPTION MK 235 Mod 18 LCU Depot Spares OY1
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU Depot Spares OY1
5100AB 1.00 2.00
MK 235 LCU Depot Spares OY2
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and
5200AA Set OPTION MK 235 Mod 17 LCU Depot Spares OY2
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU Depot Spares OY2
5200AA 1.00 2.00
5200AB Set OPTION MK 235 Mod 18 LCU Depot Spares OY2
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU Depot Spares OY2
5200AB 1.00 2.00
MK 235 LCU Depot Spares OY3
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and
5300AA Set OPTION MK 235 Mod 17 LCU Depot Spares OY3
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU Depot Spares OY3
5300AA 1.00 2.00
5300AB Set OPTION MK 235 Mod 18 LCU Depot Spares OY3
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU Depot Spares OY3
5300AB 1.00 2.00
MK 235 LCU Depot Spares OY4
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and
5400AA Set OPTION MK 235 Mod 17 LCU Depot Spares OY4
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 17 LCU Depot Spares OY4
5400AA 1.00 2.00
5400AB Set OPTION MK 235 Mod 18 LCU Depot Spares OY4
FFP
Depot spares kit.
Production Phase: Fabricate, assemble and deliver LCU Depot spares kit and associated equipment IAW the SOW and TDP. Refer to CDRLs for item and data requirements.
NOTE: The requirements in DFARS 252.211-7003, Item Identification and Valuation, are applicable for this line item. The contractor shall provide DoD unique identification or a DoD recognized unique identification equivalent.
MK 235 MOD 18 LCU Depot Spares OY4
5400AB 1.00 2.00
6000 4 Quarter
(Time)
Production Readiness Review BY
FFP
Production Readiness Review (PRR) Production Phase: PRR IAW SOW Paragraph 16.1
6100 4 Quarter
OPTION Production Readiness Review OY1
Production Readiness Review (PRR) Production Phase: PRR IAW SOW Paragraph 16.1
6200 4 Quarter
OPTION Production Readiness Review OY2
Production Readiness Review (PRR) Production Phase: PRR IAW SOW Paragraph 16.1
6300 4 Quarter
OPTION Production Readiness Review OY3
Production Readiness Review (PRR) Production Phase: PRR IAW SOW Paragraph 16.1
6400 4 Quarter
OPTION Production Readiness Review OY4
Production Readiness Review (PRR) Production Phase: PRR IAW SOW Paragraph 16.1
7000 1 Each OPTION Physical Configuration Audit BY
FFP
Physical Configuration Audit (PCA) MK 235 MOD 17 & 18 Production Phase: PRR IAW SOW Paragraph 6.0
Data Deliverables
Prepare, maintain, and deliver data IAW CDRLS A001 through A007 and applicable Data Item Description (DID). Government shall have unlimited rights to all data/tech data IAW DFARS 252.227-7019, unless and assertion is accepted by the Government IAW DFARS 252.227-7019. The cost for all data/tech generated by the contractor directly or indirectly in its performance of this effort is included in the price paid by the Government under CLINs 1000 through 7000
CLAUSES INCORPORATED BY FULL TEXT
B-215-H002 REFUNDS (SPARES AND SUPPORT EQUIPMENT) (NAVSEA) (OCT 2018)
(a) In the event that the price of a spare part or item of support equipment delivered under this contract significantly exceeds its intrinsic value, the Contractor agrees to refund the difference. Refunds will not be made to recoup the amount of cost decreases that occur over time due to productivity gains (excluding economic purchase quantity considerations) or changes in market conditions.
(b) For purposes of this requirement, the intrinsic value of an item is defined as follows:
(1) If the item is one which is sold or is substantially similar or functionally equivalent to one that is sold in substantial quantities to the general public, intrinsic value is the established catalog or market price, plus the value of any unique requirements, including delivery terms, inspection, packaging, or labeling.
(2) If there is no comparable item sold in substantial quantities to the general public, intrinsic value is defined as the price an individual would expect to pay for the item based upon an economic purchase quantity as defined in FAR 52.207-4, plus the value of any unique requirements, including delivery terms, inspection, packaging or labeling.
(c) At any time up to two years after delivery of a spare part or item of support equipment, the Contracting Officer may notify the Contractor that based on all information available at the time of the notice, the price of the part or item apparently exceeds its intrinsic value.
(d) If notified in accordance with paragraph (c) above, the Contractor agrees to enter into good faith negotiations with the Government to determine if, and in what amount, the Government is entitled to a refund.
(e) If agreement pursuant to paragraph (d) above cannot be reached, and the Navy's return of the new or unused item to the Contractor is practical, the Navy, subject to the Contractor's agreement, may elect to return the item to the Contractor.
Upon return of the item to its original point of Government acceptance, the Contractor shall refund in full the price paid.
If no agreement pursuant to paragraph (d) above is reached, and return of the item by the Navy is impractical, the Contracting Officer may, with the approval of the Head of the Contracting Activity, issue a Contracting Officer's final decision on the matter, subject to Contractor appeal as provided in the "Disputes" clause (FAR 52.233-1).
(f) The Contractor shall make refunds, as required under this requirement, in accordance with instructions from the Contracting Officer.
(g) The Contractor shall not be liable for a refund if the Contractor advised the…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .