This document contains an amendment to a solicitation for the manufacture and delivery of Vertical Launching System electronics boxes. The amendment extends the proposal due date from August 17, 2020 to August 31, 2020. It provides responses to questions from potential offerors to clarify requirements. The solicitation is for the production of VLS Module Electronics Boxes and Hazard Electronics Boxes in accordance with government furnished technical data packages. Drawings are available to contractors through the Department of Defense Secure Access File Exchange system. The solicitation is set aside for small businesses and is a build-to-print requirement. The Naval Surface Warfare Center Port Hueneme Division will evaluate proposals and makes the award.

View the file

Other files for this federal contract opportunity

Other files attached to Vertical Launching System (VLS) Module Electronics Box (MEB) and Hazard Electronics Box, newest first.
File Type Posted
N6339420R0033 MEB HEB Amendment 14 - Summary of Changes.pdf PDF
N6339420R0033_Attachment J-3 GFP - rev 4.xlsx XLSX spreadsheet
N6339420R0033 MEB HEB Amendment 14 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 13 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 13 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 12 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 12 - Summary of Changes.pdf PDF
N6339420R0033 Attachment J-3 GFP rev 3.xlsx XLSX spreadsheet
N6339420R0033 MEB HEB Amendment 11 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 11 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 10 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 10 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 9 - Conformed Copy.pdf PDF
N6339420R0033 Attachment J-3 rev 2.xlsx XLSX spreadsheet
N6339420R0033 MEB HEB Amendment 9 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 8 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 8 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 7 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 7 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 6 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 6 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 5 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 5 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 4 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 4 - Summary of Changes.pdf PDF
N6339420R0033 MEB HEB Amendment 3 - Conformed Copy.pdf PDF
N6339420R0033 Attachment J-3 GFP rev 1.xlsx XLSX spreadsheet
N6339420R0033 MEB HEB Amendment 2 - Conformed Copy.pdf PDF
N6339420R0033 MEB HEB Amendment 2 - Summary of Changes.pdf PDF
N6339420R0033 Attachment J-3 GFP.xlsx XLSX spreadsheet
N6339420R0033 Released Conformed Copy.pdf PDF
J-2 CDRLs and DIDs combined.pdf PDF
J-S-1 - Past Performance Questionnaire.pdf PDF
Show all 33

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

To provide responses to questions, update Attachment J-3, and extend the proposal due date from 17 August 2020 to 31 August 2020.

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 31-Jul-2020

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6339420R0033

X 9B. DATED (SEE ITEM 11)

17-Jul-2020

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

31-Jul-2020

CODE

NSWC PHD 022

4363 MISSILE WAY

PORT HUENEME CA 93043

N63394 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6339420R0033

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been modified:

Amendment 1: The purpose of this amendment is to extend the RFP due date from 08/14/2020 to 08/17/2020.

Amendment 2: Due to its size exceeding DOD SAFE limits, TDP will be shared to Offerors via FedEx. Instructions have been updated in the description of this notice available in BETA.sam.gov. Section J of this solicitation has been updated accordingly.

Amendment 3:

Q&A

1. Question: Is Attachment J-3 required to be submitted at the time of proposal submission or at time of contract award?

Response: Attachment J-3 has been revised and is for informational purposes only. A revised version has been uploaded and is named “N6339420R0033 Attachment J-3 GFP rev 1.”

2. Question: If submission of J-3 is a requirement for proposal submission, does every tab in the excel spreadsheet need to be completed and should it be an attachment to the pricing volume?

Response: Not Applicable. Attachment J-3 is for informational purposes only.

3. Question: Could you provide instructions for completion of form if required?

Response: Not Applicable. Attachment J-3 is for informational purposes only.

4. Question: Would the Government consider a four week extension to the proposal due date?

Response: At this time, the Government will extend the proposal due date by one week. The revised proposal date is 31 August 2020 and has been revised in the RFP and on beta.SAM.

5. Question: Section 4.2 of the SOW, First Article Inspection, calls out the FAI needs to be in accordance with

AS9102 Rev. A standards. If a subcontractor on the proposal can perform FAI in accordance with AS9102 standards, would the Prime Contractor be deemed as an acceptable bidder or does the Prime Contractor need to be able to perform the FAI? The proposal would clearly state that the subcontractor would be providing the FAI in accordance to AS9102 standards and provide pertinent information from the subcontractor.

Response: The Government does not dictate how the vendor conduct their business. FAI needs to be completed in accordance with AS9102 Rev A.

6. Question: The following drawings appear to be missing, along with any parts list and subcomponent drawings:

CCA CAGE ASSEMBLY, MEB 8660402

CCA CAGE ASSEMBLY, HEB 8660452-9

ANGLE, ISOLATOR, MEB/HEB ENCLOSURE 8660497-9

ASSY, HANDLE, GRAB, MEB/HEB 8660501-9

Response:

Name Part No. Response

CCA CAGE ASSEMBLY, MEB 8660402

This drawing is no longer applicable to the

MEB/HEB and was removed in subsequent revisions. Recommend vendor review all

Notice of Revision (NOR)’s to ensure latest information is included. The new equivalent drawing is 8660431-9, provided as a part of the drawing package.

CCA CAGE ASSEMBLY, HEB 8660452-9

This drawing is no longer applicable to the

MEB/HEB and was removed in subsequent revisions. Recommend vendor review all

NOR’s to ensure latest information is included. The new equivalent drawing is

8660436-9, provided as a part of the drawing package.

ANGLE, ISOLATOR, MEB/HEB ENCLOSURE 8660497-9

This drawing is applicable and was provided as a part of the original delivery.

ASSY, HANDLE, GRAB, MEB/HEB 8660501-9

This drawing is applicable and was provided as a part of the original delivery.

7. Question: Though the PL calls for 5223423-4, the drawing 5223423 itself has only -1 and -2. Requesting clarification.

Response: 5223423 NOR 004 adds the -4 configuration to the TDP. Recommend vendor review all NOR’s to ensure latest information is included.

8. Question: The following WSs are called out in the ATP for MEB/HEB; however, they are not included in the TDP. Requesting the following be provided:

WS20336

WS20339

WS20267

Response:

WS20336 - This WS will be provided via DOD Safe. Please send an email to the Contract Specialist requesting this to be sent.

WS20339 - This reference was an error in the original ATR and is not applicable. Recommend vendor review latest drawings which corrected this typo.

WS20267 - This WS will be provided via DOD Safe. Please send an email to the Contract Specialist requesting this to be sent.

9. Question: The SOW and ATP call out the first article requirement; however, there is no separate FA CLIN.

Instead, there is CLIN 0001 on the CDRLs listed as NSP. Is there supposed to be a separate CLIN for an

FAT unit? Requesting clarification as to whether a full FA is required, and whether it is to be NSP.

Response: First Article Test (FAT) is not a requirement on this solicitation.

10. Question: Para 4.2.6 calls out the Post-PET to be conducted after vibration and after final assembly into

LSEQ. Will an LSEQ be provided as part of GFE?

a. Question: Can the USG clarify and provide list of equipment and software packages that will be provided as GFE?

Response: All Test Equipment will be GFE’d. There will be not requirement to test with a LSEQ as a part of MEB/HEB production acceptance. Attachment J-3 has been revised and is for informational purposes only. A revised version has been uploaded and is named “N6339420R0033

Attachment J-3 GFP rev 1.”

11. Question: CLIN 6-29 spell out the options that may be exercised at any time within the 5 year period after award. Many CLINs call for the same item with same quantity. Clarification is requested as to whether these are to correspond to specific ordering periods.

Response: Option CLIN 6-29 are potential upcoming USN requirements. They can be exercised at any time within the 5 year period after award.

12. Question: Have these units been manufactured before, and if so, could you provide the manufacturer and unit price?

Response: These units have not been manufactured before.

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 17-Aug-2020 04:30 PM to 31-Aug-2020 04:30 PM.

(End of Summary of Changes)