This document contains a cost proposal template and schedule of total estimated prices for engineering services to provide life-cycle support for AN/UYQ-70 Advanced Display System equipment. The template includes estimated labor hours, labor rates, and material costs for each year of a potential five-year contract. Labor categories include engineers, managers, technicians, and quality control specialists. Total estimated costs are provided for direct labor, indirect labor, material, travel, and fee. The related federal contract opportunity is a synopsis for a planned solicitation seeking sources to provide engineering services, logistics, installation, procurement, and limited production of any additional equipment required to sustain the AN/UYQ-70 Advanced Display System for the Department of the Navy Naval Sea Systems Command.

Attachment J-S-2 - REVISED N6339419R0003-Amendment 0003

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Cost Proposal Template

Attachment J-S-2
Schedule of Total Estimated Price
N6339419R0003-Amendment 0003
Offeror Name:
DCAA Point of Contact Information:
Year 1Year 2Year 3Year 4Year 5Total
Cost ElementsRateHoursAmountRateHoursAmountRateHoursAmountRateHoursAmountRateHoursAmountHoursAmount
Direct Labor (eCRAFT Occupation Code)BLS Occupation CodeSCA Occupation Code
Engineering Technician II (30082)51-2098300828,000$024,000$024,000$06,000$010,000$072,000$0
Quality Control Inspector (99610)51-9061996101,822$03,910$03,910$02,160$02,157$013,959$0
Manager, Operations III (MANO3)49-1011N/A608$01,492$01,492$0972$0972$05,536$0
Manager, Program/Project II (MANP2)11-9199N/A801$0648$0648$0801$0801$03,699$0
Manager, Program/Project III (MANP3)11-9199N/A775$02,022$02,022$01,398$01,150$07,367$0
Manager, Administrative III (MANA3)43-9199N/A150$0324$0324$0216$0216$01,230$0
Specialist, Configuration Management III (SCM3)15-1141N/A200$0460$0460$0380$0200$01,700$0
Engineer, Electrical/Electronics III (EE3)17-2199N/A505$01,296$01,296$0864$0864$04,825$0
Specialist, Quality Control III (SQC3)17-2199N/A300$0460$0460$0360$0360$01,940$0
Analyst, Operations II (ANP2)43-5061N/A750$02,205$02,205$01,415$01,455$08,030$0
Analyst, Financial Systems (ANFS)13-2099N/A575$01,482$01,482$01,038$01,038$05,615$0
Acquisition Management Support II (AMS2)13-1199N/A375$0696$0696$0464$0464$02,695$0
Engineer, Design II (ED2)17-2061N/A480$01,480$01,480$0960$0960$05,360$0
Engineer, Systems II (ESY2)17-2199N/A720$01,800$01,800$01,200$01,200$06,720$0
Engineer III (E3)51-1011N/A18$054$054$036$036$0198$0
Total Direct Labor Cost16,079$042,329$042,329$018,264$021,873$0140,874$0
Indirect Labor
Overhead$0
Fringe Benefits$0
G&A$0
Total Indirect Labor Cost$0$0$0$0$0$0
Total Labor Cost$0$0$0$0$0$0
Facilities Capital Cost of Money$0
Fixed Fee$0
Total Burdened Labor (CLIN 0001)$0$0$0$0$0$0
Material Cost$1,369,950$4,612,675$4,313,413$4,394,336$3,631,162$18,321,536
Any applicable burdens on material cost such as G&A, Handling$0
Profit$0
Total Burdened Material Cost (CLIN 0002)$1,369,950$4,612,675$4,313,413$4,394,336$3,631,162$18,321,536
Travel$118,386$118,386$118,386$118,386$118,386$591,930
Any applicable burdens on travel cost such as G&A (cost only - no fee)$0
Total Burdened Travel Cost (CLIN 0003)$118,386$118,386$118,386$118,386$118,386$591,930

TOTAL $1,488,336 $4,731,061 $4,431,799 $4,512,722 $3,749,548 $18,913,466