Exhibit D Blank BOQ rev 1..xlsx
XLSX spreadsheet 46 KB Posted
- Attached to
- D/B UFC Renovate Operations Building and Transient Barracks at Basa Air Base, Floridablanca, Philippines
- Solicitation number
- N6274224R6719
About this file
This document is an Exhibit D - Blank Bill of Quantities (BOQ) related to a federal contract opportunity for the renovation of an Operations Building and Transient Barracks at Basa Air Base in the Philippines.
The BOQ provides detailed line item cost estimates for the renovation work, including repairs and repainting of walls and ceilings, plumbing upgrades, HVAC replacement, electrical work, and sitework. The total contract is broken down into 4 CLINs covering the Operations Building, Transient Barracks, Installation of a Hangar Door, and Stormwater Drainage Improvements. The BOQ includes quantity, material cost, labor cost, and total engineering estimate for each line item. The related federal contract opportunity, Solicitation N6274224R6719, is for design-build services for these renovations, with a site visit scheduled for August 8, 2024 and proposals due by August 19, 2024. The contract will be awarded by the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6274224R6719_0003 PPIs and SOW.pdf | ||
| Exhibit D Blank BOQ rev. AMD 0003.xlsx | XLSX spreadsheet | |
| N6274224R6719 _0002 released.pdf | ||
| N6274224R6719-0001_released.pdf | ||
| N6274224R6719-0001 Schedule of Prices.pdf | ||
| Exhibit D Blank BOQ.xlsx | XLSX spreadsheet | |
| N6274224R6719 Released w Attachments.pdf | ||
| EXHIBIT A-D.pdf | ||
| Exhibit A - Pre Proposal Inquiry Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
BILL OF QUANTITIES DATE PREPARED
| ACTIVITY AND LOCATION: | CONSTRUCTION CONTRACT NO. | ID NO. | |||||||
| Basa Air Base, Floridablanca, Pampanga, Philippines | N6274224R6719 | ||||||||
| ESTIMATED BY | CATEGORY CODE | ||||||||
| PROJECT TITLE: | NO | ||||||||
| D/B UFC Renovate Operations Building and Transient Barrack | STATUS OF DESIGN | JOB ORDER NO. | |||||||
| CLIN 001 Renovation of Operation Building | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| B10 | SUPERSTRUCTURE | ||||||||
| Construct new roof structure, including support for the antenna | sq.m | ||||||||
| B20 | EXTERIOR CLOSURE | ||||||||
| Repair and repaint the wall ( include removal of existing paint and finishes) | sq.m | ||||||||
| B30 | ROOFING | ||||||||
| B3010 | Roof coverings | sq.m | |||||||
| Rood insulation | sq.m | ||||||||
| Roof drains | ls | ||||||||
| C30 | INTERIOR FINISHES | ||||||||
| C3010 | Repair and repaint the wall ( include removal of existing paint and finishes) | sq.m | |||||||
| C3030 | Repair and repaint ceiling | sq.m | |||||||
| D20 | PLUMBING | ||||||||
| D2010 | Water Closet with the accessories | units | |||||||
| Lavatory with the structures, accessories, and finish | units | ||||||||
| Urinoir | units | ||||||||
| D2020 | Repair clean water distribution lines | ls | |||||||
| Elevated water tank with supporting structure | units | ||||||||
| Water pumps | units | ||||||||
| D2030 | Waste water distribution lines | ls | |||||||
| D2040 | Rainwater Drainage | ls | |||||||
| D30 | HVAC | ||||||||
| Air Conditioning | BTU | ||||||||
| D50 | ELECTRICAL | ||||||||
| D5010 | Replace Electrical Service and Distribution | ls | |||||||
| D5020 | Lighting & Branch Wiring | ls | |||||||
| Electrical wires relocation | ls | ||||||||
| F10 | SPECIAL CONSTRUCTION | ||||||||
| Project plaque | ls | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X10 | Field Requirements | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total |
| Table 2: SITEWORK | |||||||||
| CLIN 001 Renovation of Operation Building | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| G10 | SITE PREPARATION | ||||||||
| G1010 | Site Clearing | sq.m | |||||||
| G1030 | Mobilization | ls | |||||||
| De-mobilization | ls | ||||||||
| Design and drawing | ls | ||||||||
| Construction of temporary facilities | ls | ||||||||
| G30 | SITE CIVIL/ MECHANICAL UTILITIES | ||||||||
| Water supply and electricity connection | units | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total | |||||||||
| Total CLIN 001 |
| CLIN 002 Renovation of Transient Barrack and Latrine Facility | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| B20 | EXTERIOR CLOSURE | ||||||||
| Repaint the wall ( include removal of existing paint and finishes) | sq.m | ||||||||
| Repair and refinish exterior door | units | ||||||||
| C10 | INTERIOR CONSTRUCTION | ||||||||
| Repair main double doors | units | ||||||||
| Toilet doors | units | ||||||||
| C30 | INTERIOR FINISHES | ||||||||
| C3010 | Repaint the wall ( include removal of existing paint and finishes) | sq.m | |||||||
| C3030 | Repair and repaint ceiling | sq.m | |||||||
| D20 | PLUMBING | ||||||||
| D2010 | Water Closet with the accessories | units | |||||||
| Lavatory with the structures, accessories, and finish | units | ||||||||
| Urinoir | units | ||||||||
| D2020 | Repair clean water distribution lines | ls | |||||||
| D2030 | Waste water distribution lines | ls | |||||||
| D30 | HVAC | ||||||||
| Exhaust fan in the latrine facility | units | ||||||||
| Ceiling Fan | units | ||||||||
| Air Conditioning | BTU | ||||||||
| D50 | ELECTRICAL | ||||||||
| D5010 | Replace Electrical Service and Distribution | ls | |||||||
| D5020 | Lighting & Branch Wiring | ls | |||||||
| F10 | SPECIAL CONSTRUCTION | ||||||||
| Project plaque | ls | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X10 | Field Requirements | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total |
| Table 2: SITEWORK | |||||||||
| CLIN 002 Renovation of Transient Barrack and Latrine Facility | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| G10 | SITE PREPARATION | ||||||||
| G1030 | Mobilization | ls | |||||||
| De-mobilization | ls | ||||||||
| Design and drawing | ls | ||||||||
| Construction of temporary facilities | ls | ||||||||
| G30 | SITE CIVIL/ MECHANICAL UTILITIES | ||||||||
| Water supply and electricity connection | units | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total | |||||||||
| Total CLIN 002 |
| CLIN 003 Installation of Hangar Door | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| A10 | FOUNDATIONS | ||||||||
| Construct foundation for new hangar door | ls | ||||||||
| B10 | SUPERSTRUCTURE | ||||||||
| Construct new hangar door | ls | ||||||||
| D50 | ELECTRICAL | ||||||||
| New door motors including installation | unit | ||||||||
| F10 | SPECIAL CONSTRUCTION | ||||||||
| Project plaque | ls | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X10 | Field Requirements | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total |
| Table 2: SITEWORK | |||||||||
| CLIN 003 Installation of Hangar Door | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| G10 | SITE PREPARATION | ||||||||
| G1010 | Site Clearing | ls | |||||||
| G1030 | Mobilization | ls | |||||||
| Demolition: Sawcut removal of 0.3m deep exsiting concrete slab | ls | ||||||||
| De-mobilization | ls | ||||||||
| Design and drawing | ls | ||||||||
| Construction of temporary facilities | ls | ||||||||
| G30 | SITE CIVIL/ MECHANICAL UTILITIES | ||||||||
| Maintenance of existing hanger door including motors | ls | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total | |||||||||
| Total CLIN 003 |
| CLIN 004 Stormwater Drainage Improvement | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| B10 | SUPERSTRUCTURE | ||||||||
| Mark and load test existing and new aircraft tie-down points | ls | ||||||||
| D50 | ELECTRICAL | ||||||||
| Test existing tie downs for grounding and bonding compliance | ls | ||||||||
| Install grounding rods and tie them to the new tie downs | ls | ||||||||
| G30 | SITE CIVIL/MECHANICAL UTILITIES | ||||||||
| Maintenance of existing hanger door including motors | ls | ||||||||
| F10 | SPECIAL CONSTRUCTION | ||||||||
| Project plaque | ls | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X10 | Field Requirements | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total |
| Table 2: SITEWORK | |||||||||
| CLIN 004 Stormwater Drainage Improvement | QUANTITY | MATERIAL COST | LABOR COST | ENGINEERING ESTIMATE | |||||
| NUMBER | UNIT | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | UNIT COST | TOTAL ($) | ||
| G10 | SITE PREPARATION | ||||||||
| G1010 | Site Clearing | ls | |||||||
| G1030 | Mobilization | ls | |||||||
| De-mobilization | ls | ||||||||
| Construction of temporary facilities | ls | ||||||||
| G30 | SITE CIVIL/ MECHANICAL UTILITIES | ||||||||
| Stormwater Drainage Improvement | units | ||||||||
| Drainage clearing, cleaning, inspection, and reporting | units | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||
| X20 | Office Overhead | ||||||||
| X30 | Profit | ||||||||
| Total | |||||||||
| Total CLIN 004 |
Total CLIN 001+002+003+004
&"Times New Roman,Regular"&10N6274224R6719_0001 Exhibit D rev.
&P
_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED
Sheet2
_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED
Sheet3
_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED
File details come from the government source that posted it. Updated .