Exhibit D Blank BOQ.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
D/B UFC Renovate Operations Building and Transient Barracks at Basa Air Base, Floridablanca, Philippines
Solicitation number
N6274224R6719
Issued by

About this file

This document appears to be an Exhibit D - Blank Bill of Quantities (BOQ) for a federal contract opportunity to renovate the Operations Building and Transient Barracks at Basa Air Base in the Philippines. The related federal contract opportunity is solicitation N6274224R6719, posted by the Department of the Navy Naval Facilities Engineering Command, to conduct a Design-Build UFC (Unified Facilities Criteria) renovation project.

The BOQ includes detailed line items and estimated quantities, material costs, labor costs, and total engineering estimates for various construction, plumbing, HVAC, and electrical work required for the renovation of the Operations Building (CLIN 001) and the Transient Barracks and Latrine Facility (CLIN 002). A pre-solicitation site visit is scheduled for August 8, 2024, and proposal submission is due by August 19, 2024.

View the file

Other files

File Type Posted
N6274224R6719_0003 PPIs and SOW.pdf PDF
Exhibit D Blank BOQ rev. AMD 0003.xlsx XLSX spreadsheet
N6274224R6719 _0002 released.pdf PDF
N6274224R6719-0001_released.pdf PDF
N6274224R6719-0001 Schedule of Prices.pdf PDF
Exhibit D Blank BOQ rev 1..xlsx XLSX spreadsheet
N6274224R6719 Released w Attachments.pdf PDF
EXHIBIT A-D.pdf PDF
Exhibit A - Pre Proposal Inquiry Form.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

BILL OF QUANTITIES DATE PREPARED

ACTIVITY AND LOCATION:CONSTRUCTION CONTRACT NO.ID NO.
Basa Air Base, Floridablanca, Pampanga, PhilippinesN62742R246719
ESTIMATED BYCATEGORY CODE
PROJECT TITLE:NO
D/B UFC Renovate Operations Building and Transient BarrackSTATUS OF DESIGNJOB ORDER NO.
CLIN 001 Renovation of Operation BuildingQUANTITYMATERIAL COSTLABOR COSTENGINEERING ESTIMATE
NUMBERUNITUNIT COSTTOTAL ($)UNIT COSTTOTAL ($)UNIT COSTTOTAL ($)
B10SUPERSTRUCTURE
Construct new roof structure, including support for the antennasq.m
B20EXTERIOR CLOSURE
Repair and repaint the wall ( include removal of existing paint and finishes)sq.m
B30ROOFING
B3010Roof coveringssq.m
Rood insulationsq.m
Roof drainsls
C30INTERIOR FINISHES
C3010Repair and repaint the wall ( include removal of existing paint and finishes)sq.m
C3030Repair and repaint ceilingsq.m
D20PLUMBING
D2010Water Closet with the accessoriesunits
Lavatory with the structures, accessories, and finishunits
Urinoirunits
D2020Repair clean water distribution linesls
Elevated water tank with supporting structureunits
Water pumpsunits
D2030Waste water distribution linesls
D2040Rainwater Drainagels
D30HVAC
Air ConditioningBTU
D50ELECTRICAL
D5010Replace Electrical Service and Distributionls
D5020Lighting & Branch Wiringls
Electrical wires relocationls
F10SPECIAL CONSTRUCTION
Project plaquels
XFIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT
X10Field Requirements
X20Office Overhead
X30Profit
Total
Table 2: SITEWORK
CLIN 001 Renovation of Operation BuildingQUANTITYMATERIAL COSTLABOR COSTENGINEERING ESTIMATE
NUMBERUNITUNIT COSTTOTAL ($)UNIT COSTTOTAL ($)UNIT COSTTOTAL ($)
G10SITE PREPARATION
G1010Site Clearingsq.m
G1030Mobilizationls
De-mobilizationls
Design and drawingls
Construction of temporary facilitiesls
G30SITE CIVIL/ MECHANICAL UTILITIES
Water supply and electricity connectionunits
XFIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT
X20Office Overhead
X30Profit
Total
Total CLIN 001
CLIN 002 Renovation of Transient Barrack and Latrine FacilityQUANTITYMATERIAL COSTLABOR COSTENGINEERING ESTIMATE
NUMBERUNITUNIT COSTTOTAL ($)UNIT COSTTOTAL ($)UNIT COSTTOTAL ($)
B20EXTERIOR CLOSURE
Repaint the wall ( include removal of existing paint and finishes)sq.m
Repair and refinish exterior doorunits
C10INTERIOR CONSTRUCTION
Repair main double doorsunits
Toilet doorsunits
C30INTERIOR FINISHES
C3010Repaint the wall ( include removal of existing paint and finishes)sq.m
C3030Repair and repaint ceilingsq.m
D20PLUMBING
D2010Water Closet with the accessoriesunits
Lavatory with the structures, accessories, and finishunits
Urinoirunits
D2020Repair clean water distribution linesls
D2030Waste water distribution linesls
D30HVAC
Exhaust fan in the latrine facilityunits
Ceiling Fanunits
Air ConditioningBTU
D50ELECTRICAL
D5010Replace Electrical Service and Distributionls
D5020Lighting & Branch Wiringls
F10SPECIAL CONSTRUCTION
Project plaquels
XFIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT
X10Field Requirements
X20Office Overhead
X30Profit
Total
Table 2: SITEWORK
CLIN 002 Renovation of Transient Barrack and Latrine FacilityQUANTITYMATERIAL COSTLABOR COSTENGINEERING ESTIMATE
NUMBERUNITUNIT COSTTOTAL ($)UNIT COSTTOTAL ($)UNIT COSTTOTAL ($)
G10SITE PREPARATION
G1030Mobilizationls
De-mobilizationls
Design and drawingls
Construction of temporary facilitiesls
G30SITE CIVIL/ MECHANICAL UTILITIES
Water supply and electricity connectionunits
XFIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT
X20Office Overhead
X30Profit
Total
Total CLIN 002

Total CLIN 001+002

_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED

Sheet2

_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED

Sheet3

_x000D_&1#&"Calibri"&14&K000000 SENSITIVE BUT UNCLASSIFIED

File details come from the government source that posted it. Updated .