This document appears to be a Bill of Quantities (BOQ) for a Design-Build project to construct a Live Fire Shoot House facility at Fort Magsaysay (FMSS) in the Philippines. The BOQ provides a detailed breakdown of the various work items, material costs, labor costs, and total estimated costs for the project.
The key details include:
- The project is a Design-Build contract for a new 19m x 18m two-story pre-engineered metal building with a concrete slab-on-grade, to be used for live fire training.
- The project range is between $1-5 million. A pre-proposal site visit is scheduled for June-July 2024, and responses are due by May 21, 2024.
- The work items cover site preparation, foundations, superstructure, exterior and interior construction, roofing, electrical, furnishings, and other site improvements.
- The procurement is being conducted by the Department of the Navy Naval Facilities Engineering Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment 4_Revised BOQ Amendment2_6714.xlsx | XLSX spreadsheet | |
| RELEASED AMD2_6714.pdf | ||
| RELEASED_AMD1_24R6714.pdf | ||
| RELEASED_RFP 24R6714.pdf | ||
| Exhibit A_PPI_6714.docx | DOCX document | |
| PHIL_BAR_Base Access Request Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BOQ (SOF)
| BILL OF QUANTITIES | ||||||||||
| ITEM NO. | ITEM | QUANTITY | MATERIAL COST | LABOR COST | TOTAL ESTIMATE | |||||
| CLIN 0001 | BASE BID ITEM 0001 | NUMBER | UNIT | UNIT COST | TOTAL (USD) | UNIT COST | TOTAL (USD) | UNIT COST | TOTAL (USD) | |
| A10 | FOUNDATIONS | - 0 | ||||||||
| ` | Special Foundations | |||||||||
| 1 | Excavation/Backfilling/Disposal | CM | ||||||||
| 2 | Column Pedestal and Foundation (concrete) | CM | ||||||||
| 3 | Column Pedestal and Foundation (rebars) | KG | ||||||||
| Slab on Grade (cast-in-place slab-on-grade reinforced concrete slab ) | ||||||||||
| 4 | Slab (concrete) | CM | ||||||||
| 5 | Slab (rebars) | KG | ||||||||
| 6 | Slab Base Course | CM | ||||||||
| 7 | Damp Proof Membrane (for Shoothouse) | SM | ||||||||
| 8 | Geotextile Fabric (For open areas) | SM | ||||||||
| B10 | SUPERSTRUCTURE | |||||||||
| 9 | Structural steel (Includes Exterior & Interior columns, Roof Truss and Rafters) | SM | ||||||||
| B20 | EXTERIOR CLOSURE | |||||||||
| 10 | Exterior Walls (concrete) | SM | ||||||||
| 11 | Exterior Walls (rebars) | KG | ||||||||
| 12 | Bal Wall Cladding 3/8" Stl, including AR500 Steel plate, with AR 300 Z brackets. Use Hilti for anchorage of bracket to the concrete wall. Connections for the plates can be welded or bolted. | SM | ||||||||
| 13 | 2" Rubber 500mmx500mm for walls | SM | ||||||||
| Exterior Doors | ||||||||||
| 14 | Steel doors 1.80 m. width | EA | ||||||||
| B30 | ROOFING | |||||||||
| 15 | Pre-Finished Metal Roofing | SM | ||||||||
| 16 | Roofing Accessories Incl. Gutters, downspouts etc. | SM | ||||||||
| C10 | INTERIOR CONSTRUCTION | |||||||||
| Partitions | ||||||||||
| 17 | ` | Interior Walls (concrete) | SM | |||||||
| 18 | Interior Walls (rebars) | KG | ||||||||
| 19 | Bal Wall Cladding 3/8" Stl/ including AR500 Steel plate, with A300 Z brackets. Use Hilti for anchorage of bracket to the concrete wall. Connections for the plates can be welded or bolted. Consider additional area of the Ceiling at corridors and 1 m. side baffles at both sides of the catwalk. | SM | ||||||||
| 20 | 2" Rubber 500mmx500mm for walls and ceiling | SM | ||||||||
| 21 | 2" Rubber 500mmx500mm for floors | SM | ||||||||
| C30 | INTERIOR FINISHES | |||||||||
| Painting | ||||||||||
| 22 | Interior and Exterior Paint | SM | ||||||||
| 23 | Painting of all exposed steel frames | Lot | ||||||||
| D50 | ELECTRICAL | |||||||||
| Electrical service and distribution | ||||||||||
| 24 | Rough‐ins | SM | ||||||||
| 25 | Panel boards and circuit breakers | Lot | ||||||||
| 26 | Electrical Outlets | Lot | ||||||||
| 27 | Lights, fixtures and wiring devices | Lot | ||||||||
| 28 | Perimeter lighting | Lot | ||||||||
| 29 | Grounding System | EA | ||||||||
| 30 | Lightning Arrester | EA | ||||||||
| 31 | Testing | EA | ||||||||
| E20 | FURNISHINGS | |||||||||
| Fix Furnishings | ||||||||||
| 32 | Flag Pole | EA | ||||||||
| 33 | Red No Shoot Line | SM | ||||||||
| 34 | Signages & Markings | Lot | ||||||||
| 35 | Project Plaque | EA | ||||||||
| F10 | SPECIAL CONSTRUCTION | |||||||||
| 36 | Catwalk Steel Frame including handrails | Lot | ||||||||
| 37 | Catwalk Flooring | Lot | ||||||||
| 38 | Ladder | EA | ||||||||
| 39 | Ladder Cage | EA | ||||||||
| G10 | SITE PREPARATION | |||||||||
| Site Clearing | ||||||||||
| 40 | Clearing/Grubbing & Tree Cutting | SM | ||||||||
| Site Earthwork | ||||||||||
| 41 | Levelling/Cut-fill | SM | ||||||||
| 42 | Soil Treatment | SM | ||||||||
| G20 | SITE IMPROVEMENTS | |||||||||
| Gravel Cover at all open areas (30mx40m less bldg. footprint) | ||||||||||
| 43 | Gravel (4" thick) | SM | ||||||||
| 44 | Compacted base course | CM | ||||||||
| Rip-rap & Slope Protection | ||||||||||
| 45 | Construct grouted riprap | LM | ||||||||
| Landscaping | ||||||||||
| 46 | CL Fencing | LM | ||||||||
| 47 | Cl DBL Gate 6.1 M | EA | ||||||||
| Roadways | ||||||||||
| 48 | Construct compacted gravel road 6 m. wide approx. 210 LM) | SM | ||||||||
| 49 | Compacted base course | CM | ||||||||
| 50 | Geotextile Fabric | SM | ||||||||
| G40 | SITE ELECTRICAL | |||||||||
| Connection to base power | ||||||||||
| 51 | Transformer min. 25 KVA | EA | ||||||||
| 52 | Electrical Posts (Concrete) & Lights - max. 30 m. spacing | EA | ||||||||
| 53 | Cabling and other accessories | LM | ||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | |||||||||
| X10 | Field Requirements including testing | |||||||||
| 54 | Mobilization | LS | ||||||||
| 55 | Demobilization | LS | ||||||||
| 56 | Supervision, QC, Safety, Project Management | months | ||||||||
| 57 | Design and On-site project supervision of ballistic installer | LS | ||||||||
| 58 | Construction Plans, Closeout Requirements | LS | ||||||||
| 59 | Training, O&M Manuals, As-Builts | LS | ||||||||
| X20 | Office Overhead | |||||||||
| 60 | TempFacil, permits, and utilities months, , Field Office, Portalet, Environment Protection, Clean-Up, Formwork | months | ||||||||
| Total for CLIN 0001 | ||||||||||
| CLIN 0002 | OPTION ITEM 0001 | |||||||||
| E20 | FURNISHINGS (LWH = 50cmx50cmx30cm) | |||||||||
| 61 | Movable ballistic rubber blocks (8 layers high, approx. 70 LM) | EA | ||||||||
| Total for CLIN 0002 | ||||||||||
| TOTAL COST OF PROJECT (Base Bid + Option Item) |
| NOTE: | 1. Provide price only for numbered items 1-61 |
| 2. Add items as necessary after each CLIN | |
| 3. Do not change the unit of measurement |
File details come from the government source that posted it. Updated .