Attachment 4_Revised BOQ Amendment2_6714.xlsx
XLSX spreadsheet 19 KB Posted
- Solicitation number
- N6274224R6714
About this file
This document is a Bill of Quantities (BOQ) attachment related to a federal contract opportunity for the design and construction of a Live Fire Shoot House at Fort Magsaysay (FMSS) in the Philippines.
The key details are:
- The project is a Design-Build contract with an estimated value between $1,000,000 and $5,000,000.
- The work includes constructing a two-story pre-engineered metal building with reinforced concrete walls, steel plating, and anti-ricochet ballistic rubber, as well as site improvements like a gravel access road, perimeter fence, and electrical infrastructure.
- A pre-proposal site visit is tentatively scheduled for June-July 2024, and contractors must submit a Base Access Request by May 21, 2024 to attend.
- The solicitation is expected to be issued by the Department of the Navy Naval Facilities Engineering Command around June-July 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RELEASED AMD2_6714.pdf | ||
| RELEASED_AMD1_24R6714.pdf | ||
| RELEASED_RFP 24R6714.pdf | ||
| Blank BOQ 24R6714 FMSS SOF LIVE FIRE SHOOTHOUSE.xlsx | XLSX spreadsheet | |
| Exhibit A_PPI_6714.docx | DOCX document | |
| PHIL_BAR_Base Access Request Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BOQ
| BILL OF QUANTITIES | |||||||||||
| ITEM NO. | ITEM | QUANTITY | MATERIAL COST | LABOR COST | TOTAL ESTIMATE | ||||||
| CLIN 0001 | BASE BID ITEM 0001 | NUMBER | UNIT | UNIT COST | TOTAL (USD) | UNIT COST | TOTAL (USD) | UNIT COST | TOTAL (USD) | ||
| A10 | FOUNDATIONS | - 0 | |||||||||
| ` | Special Foundations | ||||||||||
| 1 | Excavation/Backfilling/Disposal | CM | |||||||||
| 2 | Column Pedestal and Foundation (concrete) | CM | |||||||||
| 3 | Column Pedestal and Foundation (rebars) | KG | |||||||||
| Slab on Grade (cast-in-place slab-on-grade reinforced concrete slab ) | |||||||||||
| 4 | Slab (concrete) | CM | |||||||||
| 5 | Slab (rebars) | KG | |||||||||
| 6 | Slab Base Course | CM | |||||||||
| 7 | Damp Proof Membrane (for Shoothouse) | SM | |||||||||
| 8 | Geotextile Fabric (For open areas) | SM | |||||||||
| B10 | SUPERSTRUCTURE | ||||||||||
| 9 | Structural steel (Includes Exterior & Interior columns, Roof Truss and Rafters) | SM | |||||||||
| B20 | EXTERIOR CLOSURE | ||||||||||
| 10 | Exterior Walls (concrete) | SM | |||||||||
| 11 | Exterior Walls (rebars) | KG | |||||||||
| 12 | Provide ballistic wall cladding, min. 3/8" Stl/ including AR500 Steel plate, min of 45 mm. thick anti ricochet panel on both sides of 104mm x 104mm x 6mm(4"x4"x1/4") tube frame OR as designed by the Ballistic expert at the interior face. | SM | |||||||||
| 13 | 2" Rubber 500mmx500mm for walls | SM | |||||||||
| Exterior Doors | |||||||||||
| 14 | Steel doors 1.80 m. width | EA | |||||||||
| B30 | ROOFING | ||||||||||
| 15 | Pre-Finished Metal Roofing | SM | |||||||||
| 16 | Roofing Accessories Incl. Gutters, downspouts etc. | SM | |||||||||
| C10 | INTERIOR CONSTRUCTION | ||||||||||
| Partitions | |||||||||||
| 17 | ` | Interior Walls (concrete) | SM | ||||||||
| 18 | Interior Walls (rebars) | KG | |||||||||
| 19 | Partition walls of training rooms - Bal Wall Cladding, min. 3/8" Stl AR500 Steel plate, min of 45 mm. thick anti ricochet panel on both sides of 104mm x 104mm x 6mm(4"x4"x1/4") tube frame OR as designed by the Ballistic expert. | ||||||||||
| Consider additional area of the Ceiling at corridors and below the catwalk frame including baffles at both sides of the catwalk. | SM | ||||||||||
| 20 | 2" Rubber 500mmx500mm for walls and ceiling. Consider 5% spare. | SM | |||||||||
| 21 | 2" Rubber 500mmx500mm for floors | SM | |||||||||
| C30 | INTERIOR FINISHES | ||||||||||
| Painting | |||||||||||
| 22 | Interior and Exterior Paint | SM | |||||||||
| 23 | Painting of all exposed steel frames | Lot | |||||||||
| D50 | ELECTRICAL | ||||||||||
| Electrical service and distribution | |||||||||||
| 24 | Rough‐ins | SM | |||||||||
| 25 | Panel boards and circuit breakers | Lot | |||||||||
| 26 | Electrical Outlets | Lot | |||||||||
| 27 | Lights, fixtures and wiring devices | Lot | |||||||||
| 28 | Perimeter lighting | Lot | |||||||||
| 29 | Grounding System | EA | |||||||||
| 30 | Lightning Arrester | EA | |||||||||
| 31 | Testing | EA | |||||||||
| E20 | FURNISHINGS | ||||||||||
| Fix Furnishings | |||||||||||
| 32 | Flag Pole | EA | |||||||||
| 33 | Red No Shoot Line | SM | |||||||||
| 34 | Signages & Markings | Lot | |||||||||
| 35 | Project Plaque | EA | |||||||||
| F10 | SPECIAL CONSTRUCTION | ||||||||||
| 36 | Catwalk Steel Frame including handrails | Lot | |||||||||
| 37 | Catwalk Flooring | Lot | |||||||||
| 38 | Ladder | EA | |||||||||
| 39 | Ladder Cage | EA | |||||||||
| G10 | SITE PREPARATION | ||||||||||
| Site Clearing | |||||||||||
| 40 | Clearing/Grubbing & Tree Cutting | SM | |||||||||
| Site Earthwork | |||||||||||
| 41 | Levelling/Cut-fill | SM | |||||||||
| 42 | Soil Treatment | SM | |||||||||
| G20 | SITE IMPROVEMENTS | ||||||||||
| Gravel Cover at all open areas (30mx40m less bldg. footprint) | |||||||||||
| 43 | Gravel (4" thick) | SM | |||||||||
| 44 | Compacted base course | CM | |||||||||
| Rip-rap & Slope Protection | |||||||||||
| 45 | Construct grouted riprap | LM | |||||||||
| Landscaping | |||||||||||
| 46 | Chain Link Fence | LM | |||||||||
| 47 | Chain Link Gate 6.1 M | EA | |||||||||
| Roadways | |||||||||||
| 48 | Construct compacted gravel road 6 m. wide approx. 210 LM | SM | |||||||||
| 49 | Compacted base course | CM | |||||||||
| 50 | Geotextile Fabric | SM | |||||||||
| G40 | SITE ELECTRICAL | ||||||||||
| Connection to base power from SOF School approximately 350 m. | |||||||||||
| 51 | Transformer min. 25 KVA | EA | |||||||||
| 52 | Electrical Posts (Concrete) & Lights - max. 30 m. spacing | EA | |||||||||
| 53 | Cabling and other accessories | LM | |||||||||
| X | FIELD REQUIREMENTS, OFFICE OVERHEAD & PROFIT | ||||||||||
| X10 | Field Requirements including testing | ||||||||||
| 54 | Mobilization | LS | |||||||||
| 55 | Demobilization | LS | |||||||||
| 56 | Supervision, QC, Safety, Project Management | months | |||||||||
| 57 | Design and On-site project supervision of ballistic installer | LS | |||||||||
| 58 | Construction Plans, Closeout Requirements | LS | |||||||||
| 59 | Training, O&M Manuals, As-Builts | LS | |||||||||
| X20 | Office Overhead | ||||||||||
| 60 | TempFacil, permits, and utilities months, Project Sign, Field Office, Portalet, Environment Protection, Clean-Up, Formwork | months | |||||||||
| Total for CLIN 0001 | |||||||||||
| CLIN 0002 | OPTION ITEM 0001 | ||||||||||
| E20 | FURNISHINGS | ||||||||||
| 61 | Movable ballistic rubber blocks/Bullet trap (Min. height of 2 meters, and min. 18 Lineal Meters) | EA | |||||||||
| Total for CLIN 0002 | |||||||||||
| TOTAL COST OF PROJECT (Base Bid + Option Item) |
| NOTE: | 1. Provide price only for numbered items 1-61 |
| 2. Add items as necessary after each CLIN | |
| 3. Do not change the unit of measurement |
File details come from the government source that posted it. Updated .