Released AMD 00005 Open Discussion and NCF 24R6708.pdf
PDF 383 KB Posted
- Attached to
- D/B AT-6 Facility, Wing 41, Chiang Mai, Thailand
- Solicitation number
- N6274224R6708
About this file
This document is Amendment 0005 to Solicitation N6274224R6708 for a Design-Build project at Wing 41, Royal Thai Air Force (RTAF) in Chiang Mai, Thailand. The key changes include:
- A discussion period is now open, and offerors must submit final proposal revisions by September 4, 2024.
- The submittal requirements for Non-Cost Factor 1 (Offeror Experience) and Non-Cost Factor 4 (Technical Solution) have been revised. The minimum project size for Offeror Experience has been reduced from $400,000 to $300,000, and the minimum building size has been reduced from 700 SM to 500 SM. The Technical Solution requirements now specify that the site layout plans must show the footprint of the existing Revetments, Egress building, Maintenance Back Shop, and access road.
- The required response date/time has been changed from July 12, 2024 to September 4, 2024.
The related federal contract opportunity is a combined synopsis/solicitation for the D/B AT-6 Facility project at Wing 41, Chiang Mai, Thailand. It provides details on the project scope, including renovating existing Revetments, constructing an Egress building and Maintenance Back Shop, and installing a wash rack. A pre-proposal site visit is tentatively scheduled for June-July 2024, and interested offerors must submit a Base Access Request by May 28, 2024.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attached Revised BOQ Amendment4.xlsx | XLSX spreadsheet | |
| RELEASED_AMD4_complete package.pdf | ||
| AMD3_24R6708.pdf | ||
| AMD2_24R6708.pdf | ||
| AMD1_24R6708.pdf | ||
| Released SOL N6274224R6708 AT6 Chiangmai THA.pdf | ||
| THA_BAR_Base Access Request Form.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ACQR6051973
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
N6274224R6708 D/B AT-6 Facility, Wing 41, Chiang Mai, Thailand
Amendment 0005 begins on the next page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 30-Aug-2024
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N6274224R6708
X 9B. DATED (SEE ITEM 11)
21-May-2024
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
29-Aug-2024
CODE
NAVFAC ROICC THAILAND (US EMBASSY)
7 SATHORN TAI ROAD
BANGKOK 10120
N62742 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N6274224R6708
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMD 5 REVISED NCF & DISCUSSION
The following changes will be considered a part of this solicitation.
a. Proposals received for the solicitation require additional information; therefore a discussion period is now open.
Please respond to individual evaluation notice with Final Proposal Revisions provided to your firm with this amendment no later than September 4, 2024 at 11:00am, Thailand Time.
b. The submittal requirements under Non-Cost Factor 1 Offeror Experience and Non-Cost Factor 4 Technical Solution are revised per the following:
Non-Cost Factor 1 - Offeror Experience:
From:
(a) Submittal Requirements: Submit a minimum of three (3) and a maximum of five (5) construction projects for the Offeror that best demonstrates Offeror experience on relevant projects that are similar size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as similar design-build construction with the following relevant characteristics:
a. Similar in Size: Design-build construction projects cost between $400,000 and
$2,500,000 in final construction. One project must be at least $1,000,000. Any project outside this range may not be considered.
b. Similar in Scope: Design-build construction of a single or more story reinforced concrete structure building with a minimum size of 700 SM.
c. Similar in Complexity: Design-build construction projects involving residential, commercial, institutional, or industrial construction performed in Southeast Asia, Nepal, the Maldives, or Timor Leste.
To:
(a) Submittal Requirements: Submit a minimum of three (3) and a maximum of five (5) construction projects for the Offeror that best demonstrates Offeror experience on relevant projects that are similar size, scope, and complexity to the RFP. For purposes of this evaluation, a relevant project is further defined as similar design-build construction with the following relevant characteristics:
a. Similar in Size: Design-build construction projects cost between $300,000 and
$2,500,000 in final construction. One project must be at least $1,000,000. Any project outside this range may not be considered.
b. Similar in Scope: Design-build construction of a single or more story reinforced concrete structure building with a minimum size of 500 SM.
c. Similar in Complexity: Design-build construction projects involving residential, commercial, institutional, or industrial construction performed in Southeast Asia, Nepal, the Maldives, or Timor Leste.
Non-Cost Factor 4 Technical Solution From:
(a) Submittal Requirements:
i. Provide a narrative describing the technical solution to the project that meets the requirements of the RFP.
Include the following:
1. Design criteria for Egress building.
2. Foreign object damage (FOD) control methodologies during construction.
3. Exterior façade describing how the proposed construction integrates with the surrounding area and existing Base facilities design or architectural theme.
Narrative shall not exceed two (2) double-sided pages (or four (4) single-sided pages.
ii. Provide the following conceptual design drawing details:
1. Site layout plan showing footprint of proposed building, perimeter fence, entrance gates and road.
2. Floor plan and roof plan of for proposed building. The drawings shall include dimensions, doors, windows, and fire exit, to illustrate understanding of the statement of requirements.
To:
(a) Submittal Requirements:
i. Provide a narrative describing the technical solution to the project that meets the requirements of the RFP.
Include the following:
1. Design criteria for Egress building.
2. Foreign object damage (FOD) control methodologies during construction.
3. Exterior façade describing how the proposed construction integrates with the surrounding area and existing Base facilities design or architectural theme.
Narrative shall not exceed two (2) double-sided pages (or four (4) single-sided pages.
ii. Provide the following conceptual design drawing details:
1. Site layout plan showing footprint of proposed building, perimeter fence, entrance gates and road. The site layout plans showing the footprint of the existing Revetments, Egress building with access road, and Maintenance Back shop.
2. Floor plan and roof plan of for proposed building. The drawings shall include dimensions, doors, windows, and fire exit, to illustrate understanding of the statement of requirements. The floor plans for the Egress building and Maintenance Back Shop.
All other paragraphs, provisions, and conditions remain unchanged.
The offeror must acknowledge receipt of this amendment.
SECTION 00 10 00 - SOLICITATION
The required response date/time has changed from 12-Jul-2024 11:00 AM to 04-Sep-2024 11:00 AM.
(End of Summary of Changes)