Attached Revised BOQ Amendment4.xlsx

XLSX spreadsheet 123 KB Posted

Attached to
D/B AT-6 Facility, Wing 41, Chiang Mai, Thailand
Solicitation number
N6274224R6708
Issued by

About this file

This document appears to be a detailed Bill of Quantities (BOQ) for a Design-Build contract to renovate and construct various facilities at Wing 41 of the Royal Thai Air Force (RTAF) in Chiang Mai, Thailand. The project includes renovating existing revetments, constructing an egress building, a maintenance back-shop, and an aircraft wash rack within an existing revetment. The BOQ provides a breakdown of the construction activities, materials, and labor costs for each CLIN.

The related federal contract opportunity solicitation number is N6274224R6708 for the "D/B AT-6 Facility, Wing 41, Chiang Mai, Thailand" project. The government plans to issue the solicitation around May or June 2024 and will conduct a Pre-Proposal Site Visit tentatively scheduled for June-July 2024. Interested contractors must submit a Base Access Request form by May 28, 2024 to attend the site visit. The project is being procured by the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

File Type Posted
Released AMD 00005 Open Discussion and NCF 24R6708.pdf PDF
RELEASED_AMD4_complete package.pdf PDF
AMD3_24R6708.pdf PDF
AMD2_24R6708.pdf PDF
AMD1_24R6708.pdf PDF
Released SOL N6274224R6708 AT6 Chiangmai THA.pdf PDF
THA_BAR_Base Access Request Form.xlsx XLSX spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY

BOQ

ACTIVITY AND LOCATION :

Chiang Mai, TH

CONSTRUCTION CONTRACT NUMBER :

N6274224R6708

PROJECT TITLE :

D/B AT-6 Facility, Wing 41, Chiang Mai, Thailand

ESTIMATED BY :

ITEM DESCRIPTION TOTAL

1CLIN 0001: RENOVATION OF THE EXISTING REVETMENTS
2CLIN 0002: CONSTRUCTION OF AN EGRESS BUILDING AND ACCESS ROAD
3CLIN 0003:CONSTRUCTION OF A MAINTENANCE BACK-SHOP MJ-1
4CLIN 0004 OPTION 0001: CONSTRUCTION OF AN AIRCRAFT WASH RACK WITHIN AN EXISTING REVETMENT
5CLIN 0005 OPTION 0002: RENOVATE SIX EXISTING TIE DOWNS AT THE EXISTING APRON
GRANDTOTAL (INCLUDED VAT)

BOQ CLIN 0001 Revetment

BOQ DATE PREPARED :

ACTIVITY AND LOCATION :

Chiang Mai, TH

CONSTRUCTION CONTRACT NUMBER :

N6274224R6708

PROJECT TITLE :
D/B AT-6 Facility, Wing 41, Chiang Mai, ThailandESTIMATED BY :
ITEMDESCRIPTIONQUANTITYMATERIAL COSTLABOR COSTTOTAL
NUMBERUNITUNIT COSTTOTAL (USD)UNIT COSTTOTAL (USD)USD
CLIN 0001: RENOVATION OF THE EXISTING REVETMENTS
B30ROOFING
- Remove existing roofingsSM
- Metal sheet roofing with PU heat insulationSM
- Stainless steel roof gutterM
- Side WallSM
- Galvanized steel wire meshSM
- MiscellaneousLot
- Other if any
Total B30
C30INTERIOR FINISHES
Painting
- Repaint roof steel structureSM
- Repair and repaint all existing steel bunkers between the existing revetment and
along the east and west sides of the existing revetmentSM
- Repair and repaint jet blast deflectorsEa
- Other if any
Total C30
D20PLUMBING
Rain Water Drainage
- Roof Drain, rainleaderLot
- MiscellaneousLot
- Other if any
Total D20
D50ELECTRICAL
Electrical Service & Distribution
- LV electrical cableEa
- 220 V Main Distribution Board with all related WorkEa
- 15 kW stepdown transformer 380V /3P to 220/110 VEa
- MiscellaneousLot
Lighting & Branch Wiring
- Weather proof LED Floodlight and AccessoriesEa
- Conduit and Wiring for Lighting and Power OutletsEA
- MiscellaneousLot
- Lightning protectionEA
- Other if any
Total D50
G10
G1010SITE PREPARATIONS
Site Clearing
- Remove all existing utilities from construction site.Lot
- Other if any
Total G10
G20SITE IMPROVEMENTS
- Remove existing paint markingSM
- Restripe guidelines and ground static symbolSM
- Building name signEa
- Dedication plaqueEa
- Other if any
Total G20
G30SITE CIVIL/MECHANICAL UTILITIES
Strom Sewer
- Concrete gutterm
- Manhole with Coversset
- Concrete pipesm
- Other if any
Total G30
TOTAL A to G
X10FIELD REQUIREMENTS
Mobilization
- Temporary FenceEa
- Project SignboardEa
- Temporary Site OfficeEa
- Temporary Site StorageEa
- Temporary ToiletsEa
- Worker CampEa
Topographic SurveyEa
Temporary UtilitiesEa
- Electrical supplyEa
- Water supplyEa
Safety ImplementationEa
TransportationEa
Repair DamagesEa
Technical Training for EnduserEa
Asbuilt Drawing, O&MNEa
Key personnel (Project manager, safety officer and QC manager)Ea
Other if any
Total X10
X20OFFICE EXPENSES
- Design FeeLot
- Home Office OperationLot
-Other if any
Total X20
X30Profit
Total X30
Total X
VATVATIncluded
TOTAL CLIN 0001

BOQ CLIN 0002 Egress

BOQ DATE PREPARED :

ACTIVITY AND LOCATION :

Chiang Mai, TH

CONSTRUCTION CONTRACT NUMBER :

N6274224R6708

PROJECT TITLE :
D/B AT-6 Facility, Wing 41, Chiang Mai, ThailandESTIMATED BY :
ITEMDESCRIPTIONQUANTITYMATERIAL COSTLABOR COSTTOTAL
NUMBERUNITUNIT COSTTOTAL
(USD)UNIT COSTTOTAL (USD)USD
CLIN 0002: CONSTRUCTION OF AN EGRESS BUILDING AND ACCESS ROAD
A10FOUNDATIONS
Geotechnical Work & ReportEa
Piling work
- Pile position marking, pile and pile head trimingEa
Earth work
- Excavation, back fill and compactionCu.m
Concrete work
- Lean concrete and structural concreteCu.m
Reinforcing Bar
- Round Bar & Deformed BarKg
- Binding wireKg
Form work
- FormworkSM
Miscellaneous
- Pile TestEa
- Other if any
Total A10
B10SUPERSTRUCTURE
Concrete work
- Lean and structural concreteCu.m
- Excavation and back fillCu.m
- Damp proof membraneSM
Reinforcing Bar
- Round Bar & Deformed BarKg
- Binding wireKg
Form work
- Falswork and FormworkSM
Miscellaneous
- Termite TreatmentSM
- Other if any
Total B10
B20EXTERIOR CLOSURE
- Concrete Gutterm
- Steel Gratingm
- Manholes and piping to collect storm sewer from both rain leaders and storm water run-off from the walkway.m
Exterior Walls
- Exterior blast-resistant wallSM
- Exterior CMU Wall 150 mm. Thk.SM
- Vertical Tie-column 100x200 mm.m
- Horizontal Lintel 100x200 mm.m
- Dia 6 mm DowelKg
- Dia 6 mm Dowel ( Plug through R.C)Ea
Plaster work
- Exterior wall plasterSM
Miscellaneous
- ScaffoldingEa
Window
- Aluminum sliding window with integral insect screen, 6 mm black tinted glass, and office style curtainEa
Exterior Door
- Double steel doorEa
- Single steel doorEa
- Blast-resistant doorEa
- Other if any
Total B20
B30ROOFING
- Roof steel structureSM
- Metal roof panel and thermal insulationSM
- Roof gutter and down spoutM
- MiscellaneousLot
- Other if any
Total B30
C10INTERIOR CONSTRUCTION
Partitions
Interior CMU Wall 100 mm. Thk.SM
- Vertical Tie-column 100x150 mm.m
- Horizontal Lintel 100x150 mm.m
Plaster work
- Interior wall plasterSM
Toilet Partition w/Door and AccessoriesEa
Interior Doors
- Single steel doorEa
- Double steel doorEa
- Master keysEa
- Other if any
Total C10
C30INTERIOR FINISHES
Wall Finishes
- Ceramic Tile WallSM
- Wall Skirting Workm
- MiscellaneousLot
Floor Finishes
- Concrete Floor with Epoxy CoatingSM
- Ceramic Floor Tile 600 x 600 MM.SM
- Ceramic Floor Tile 300 x 300 MM.SM
- MiscellaneousLot
Ceiling Finishes
- Gypsum Ceiling and Steel Frame WorkSM
Painting
- Exterior Painting WorkSM
- Interior Painting WorkSM
- Ceiling Painting WorkSM
- Other if any
Total C30
D20PLUMBING
Plumbing Fixtures
- Water ClosetEa
- Tissue HolderEa
- Rinsing SprayEa
- Urinal with partitionEa
- Sink with faucetEa
-Countertop for sinksEa
- Hose bibEa
- Mirror with its AccessoriesEa
Domestic Water Equipment
- Ground Water Storage TankEa
- Control Valve and its related WorkEa
- Water Pressure PumpEa
- Control PanelEa
- Pipe & FittingLot
- Concrete Pad & Pump Housing WorkSM
- MiscellaneousLot
Sanitary Waste & Vent
- Waste Pipe & FittingLot
- Vent Pipe & FittingLot
- Floor DrainEa
- ValveLot
- MiscellaneousLot
Rain Water Drainage
- Roof Drain, rainleaderLot
- MiscellaneousLot
- Other if any
Total D20
D30HVAC & VENTILATION
Cooling Generating Systems
-Split-type air conditioning unit with all wiring, hang
support and all accessoriesEa
Other HVAC System & Equipment
- Exhaust fan with its related workEa
- Adjustable Speed Rotation/Oscillation Fan with its related WorkEa
- Other if any
Total D30
D40FIRE PROTECTION
OTHER FIRE PROTECTION SYSTEM
- Wall mounted fire extinguisher ABC-dry chemical typeEa
Total D40
D50ELECTRICAL
Electrical Service & Distribution
- HV electrical cable, pole and other if requiredEa
- Transformer if requiredEa
- LV electrical cableEa
- kWH meterEa
Lighting & Branch Wiring
- Explosive proof LED Lighting Fixture and AccessoriesEa
- LED Lighting Fixture and AccessoriesEa
- Weather proof LED Lighting Fixture and AccessoriesEa
- Explosive proof Emergency lightEa
- Emergency lightEa
- Exit signEa
- Explosion proof exit signEa
- 220 V Receptacle Outlet, Box, Plate and AccessoriesEa
-Explosive proof 220 V Receptacle Outlet, Box, Plate and AccessoriesEa
-Explosive proof 380 V Receptacle Outlet, Box, Plate and AccessoriesEa
- Conduit and Wiring for Lighting and Power OutletsEa
- Static groundingEa
Communication and Security
- Fire Alarm Control PanelEa
-Explosion proof Manual StationEa
- Manual StationEa
- BellEa
- Explosion Proof Smoke DetectorEa
- Smoke DetectorEa
-FRC cable, THW cable and ConduitLot
- MiscellaneousLot
- LAN Outlets RJ45 CAT6Ea
- LAN cable and ConduitLot
- MiscellaneousLot
- TEL Outles 6P4CEa
- MDFEa
- TIEV Cable 4C -0.65 mmLot
- MiscellaneousLot
Lightning protectionEa
- Other if any
Total D50
E20FURNISHINGS
Fixed Furnishing
- Project RenderingEa
- Venetian blind curtainEa
- Key cabinetEa
- Commercial-grade work stationEa
- Commercial-grade chairEa
- Commercial-grade portable air compressor reciprocation nitro 250 psiEa
- Commercial-grade portable air compressor 250 psiEa
-Type 2 Explosive Storage Magazine (12’x8’x8’)Ea
- Other if any
Total E20
G10
G1010SITE PREPARATIONS
Site Clearing
- Remove all existing utilities from construction site and relocate drainage lineLot
- Other if any
Total G10
G20SITE IMPROVEMENTS
- Concrete roadSM
- Building name signEa
- Dedication plaqueEa
- Other if any
Total G20
G30SITE CIVIL/MECHANICAL UTILITIES
Water Supply
- Water Metering WorkEa
- Main Gate Valve & AccessoriesEa
- Main Pipe & FittingLot
Sanitary Sewer
- Septic TankEa
- Concrete foundationEa
- Waste Pipe & FittingEa
- Barricade for Septic TankEa
- MiscellaneousLot
Strom Sewer
- Excavation, Backfill and CompactionLot
- Manhole with CoversEa
- Concrete pipesM
- Other if any
Total G30
TOTAL A to G
X10FIELD REQUIREMENTS
Mobilization
- Temporary FenceEa
- Project SignboardEa
- Temporary Site OfficeEa
- Temporary Site StorageEa
- Temporary ToiletsEa
- Worker CampEa
Topographic SurveyEa
Temporary UtilitiesEa
- Electrical supplyEa
- Water supplyEa
Safety ImplementationEa
TransportationEa
Repair DamagesEa
Technical Training for EnduserEa
Asbuilt Drawing, O&MNEa
Key personnel (Project manager, safety officer and QC manager)Ea
Other if any
Total X10
X20OFFICE EXPENSES
- Design FeeLot
- Home Office OperationLot
-Other if any
Total X20
X30Profit
Total X30
Total X
VATVATIncluded
TOTAL CLIN 0002

BOQ CLIN 0003 Back shop

BOQ DATE PREPARED :

ACTIVITY AND LOCATION :

Chiang Mai, TH

CONSTRUCTION CONTRACT NUMBER :

N6274224R6708

PROJECT TITLE :
D/B AT-6 Facility, Wing 41, Chiang Mai, ThailandESTIMATED BY :
ITEMDESCRIPTIONQUANTITYMATERIAL COSTLABOR COSTTOTAL
NUMBERUNITUNIT COSTTOTAL (USD)UNIT COSTTOTAL (USD)USD
CLIN 0003: CONSTRUCTION OF A MAINTENANCE BACK-SHOP MJ-1
A10FOUNDATIONS
Geotechnical Work & ReportEa
Piling work
- Pile position marking, pile and pile head trimingEa
Earth work
- Excavation, back fill and compactionCu.m
Concrete work
- Lean concrete and structural concreteCu.m
Reinforcing Bar
- Round Bar & Deformed BarKg
- Binding wireKg
Form work
- FormworkSM
Miscellaneous
- Pile TestEa
- Other if any
Total A10
B10SUPERSTRUCTURE
Concrete work
- Lean and structural concreteCu.m
- Excavation and back fillCu.m
- Damp proof membraneSM
Reinforcing Bar
- Round Bar & Deformed BarKg
- Binding wireKg
Form work
- Falswork and FormworkSM
Miscellaneous
- Termite TreatmentSM
- Other if any
Total B10
B20EXTERIOR CLOSURE
- Concrete Gutterm
- Steel Gratingm
- Manholes and piping to collect storm sewer from both rain leaders and storm water run-off from the walkway.m
Exterior Walls
- Exterior CMU Wall 150 mm. Thk.SM
- Vertical Tie-column 100x200 mm.m
- Horizontal Lintel 100x200 mm.m
- Dia 6 mm DowelKg
- Dia 6 mm Dowel ( Plug through R.C)Ea
Plaster work
- Exterior wall plasterSM
Miscellaneous
- ScaffoldingEa
Window
- Aluminum sliding window with integral insect screen, 6 mm black tinted glass, and office style curtainEa
Exterior Door
- Double steel doorEa
- Single steel doorEa
- Roller shutter doorEa
Total B20
B30ROOFING
- Roof steel structureSM
- Metal roof panel and thermal insulationSM
- Roof gutter and down spoutM
- MiscellaneousLot
- Other if any
Total B30
C10INTERIOR CONSTRUCTION
Partitions
Interior CMU Wall 100 mm. Thk.SM
- Vertical Tie-column 100x150 mm.m
- Horizontal Lintel 100x150 mm.m
Plaster work
- Interior wall plasterSM
Toilet Partition w/Door and AccessoriesEa
Interior Doors
- Single steel doorEa
- Master keysEa
- Other if any
Total C10
C30INTERIOR FINISHES
Wall Finishes
- Ceramic Tile WallSM
- Wall Skirting Workm
- MiscellaneousLot
Floor Finishes
- Concrete Floor with Epoxy CoatingSM
- Ceramic Floor Tile 600 x 600 MM.SM
- Ceramic Floor Tile 300 x 300 MM.SM
- MiscellaneousLot
Ceiling Finishes
- Gypsum Ceiling and Steel Frame WorkSM
Painting
- Exterior Painting WorkSM
- Interior Painting WorkSM
- Ceiling Painting WorkSM
- Other if any
Total C30
D20PLUMBING
Plumbing Fixtures
- Water ClosetEa
- Tissue HolderEa
- Rinsing SprayEa
- Urinal with partitionEa
- Sink with faucetEa
-Countertop for sinksEa
- Hose bibEa
- Mirror with its AccessoriesEa
Domestic Water Equipment
- Ground Water Storage TankEa
- Control Valve and its related WorkEa
- Water Pressure PumpEa
- Control PanelEa
- Pipe & FittingLot
- Concrete Pad & Pump Housing WorkSM
- MiscellaneousLot
Sanitary Waste & Vent
- Waste Pipe & FittingLot
- Vent Pipe & FittingLot
- Floor DrainEa
- ValveLot
- MiscellaneousLot
Rain Water Drainage
- Roof Drain, rainleaderLot
- MiscellaneousLot
- Other if any
Total D20
D30HVAC & VENTILATION
Cooling Generating Systems
-Split-type air conditioning unit with all wiring, hang
support and all accessoriesEa
Other HVAC System & Equipment
- Exhaust fan with its related workEa
- Adjustable Speed Rotation/Oscillation Fan with its related WorkEa
- Other if any
Total D30
D40FIRE PROTECTION
OTHER FIRE PROTECTION SYSTEM
- Wall mounted fire extinguisher ABC-dry chemical typeEa
Total D40
D50ELECTRICAL
Electrical Service & Distribution
- HV electrical cable, pole and other if requiredEa
- Transformer if requiredEa
- LV electrical cableEa
- kWH meterEa
Lighting & Branch Wiring
- LED Lighting Fixture and AccessoriesEa
- Weather proof LED Lighting Fixture and AccessoriesEa
- Emergency lightEa
- Exit signEa
- 220 V Receptacle Outlet, Box, Plate and AccessoriesEa
- 380 V Receptacle Outlet, Box, Plate and AccessoriesEa
- Conduit and Wiring for Lighting and Power OutletsEa
Communication and Security
- LAN Outlets RJ45 CAT6Ea
- LAN cable and ConduitEa
- MiscellaneousLot
- TEL Outles 6P4CEa
- MDFEa
- TIEV Cable 4C -0.65 mmEa
- MiscellaneousLot
Lightning protectionEa
- Other if any
Total D50
E20FURNISHINGS
Fixed Furnishing
- Project RenderingEa
- Venetian blind curtainEa
- Key cabinetEa
- Commercial-grade work stationEa
- Commercial-grade chairEa
- Heavy duty steel shelveEa
- Commercial-grade portable air compressor 250 psiEa
- Other if any
Total E20
- Remove all existing utilities from construction site and relocate septic tanksLot
- Other if any
Total G10
G20SITE IMPROVEMENTS
- Concrete pavementSM
- FencingM
- Building name signEa
- Dedication plaqueEa
- Other if any
Total G20
G30SITE CIVIL/MECHANICAL UTILITIES
Water Supply
- Water Metering WorkEa
- Main Gate Valve & AccessoriesEa
- Main Pipe & FittingLot
Sanitary Sewer
- Septic TankEa
- Concrete foundationEa
- Waste Pipe & FittingEa
- Barricade for Septic TankEa
- MiscellaneousLot
Strom Sewer
- Excavation, Backfill and CompactionLot
- Manhole with CoversEa
- Concrete pipesM
- Other if any
Total G30
Total A to G
X10FIELD REQUIREMENTS
Mobilization
- Temporary FenceEa
- Project SignboardEa
- Temporary Site OfficeEa
- Temporary Site StorageEa
- Temporary ToiletsEa
- Worker CampEa
Topographic SurveyEa
Temporary UtilitiesEa
- Electrical supplyEa
- Water supplyEa
Safety ImplementationEa
TransportationEa
Repair DamagesEa
Technical Training for EnduserEa
Asbuilt Drawing, O&MNEa
Key personnel (Project manager, safety officer and QC manager)Ea
Other if any
Total X10
X20OFFICE EXPENSES
- Design FeeLot
- Home Office OperationLot
-Other if any
Total X20
X30ProfitProfit
Total X30
Total X
VAT
TOTAL CLIN 0003

BOQ CLIN 0004 Wash Rack

BOQ DATE PREPARED :

ACTIVITY AND LOCATION :

Chiang Mai, TH

CONSTRUCTION CONTRACT NUMBER :

N6274224R6708

PROJECT TITLE :
D/B AT-6 Facility, Wing 41, Chiang Mai, ThailandESTIMATED BY :
ITEMDESCRIPTIONQUANTITYMATERIAL COSTLABOR COSTTOTAL
NUMBERUNITUNIT COSTTOTAL (USD)UNIT COSTTOTAL (USD)USD
CLIN 0004 OPTION 0001: CONSTRUCTION OF AN AIRCRAFT WASH RACK WITHIN AN EXISTING REVETMENT
D20PLUMBING
Domestic Water Equipment
- Ground Water Storage TankEa
- Water Pressure Pump with Control PanelEa
- Pipe & FittingEa
- Concrete Pad & Pump Housing WorkEa
- MiscellaneousLot
Sanitary Waste & Vent
- Oil Water SeperatorEa
- Pipe & FittingEa
- MiscellaneousLot
- Other if any
Total D20
D50ELECTRICAL
Electrical Service & Distribution
- Power Supply for Water PumpEa
- Other if any
Total D50
F10SPECIAL CONSTRUCTION
- Aircraft Wash SystemEa
- Shipping Cost for Aircraft Wash SystemEa
Total F10
G30SITE CIVIL/MECHANICAL UTILITIES
Water Supply
- Water Metering WorkEa
- Main Gate Valve & AccessoriesEa
- Main Pipe & FittingEa
- Other if any
Total G30
TOTAL D to G
X10FIELD REQUIREMENTS
Mobilization
- Temporary FenceEa
- Project SignboardEa
- Temporary Site OfficeEa
- Temporary Site StorageEa
- Temporary ToiletsEa
- Worker CampEa
Topographic SurveyEa
Temporary UtilitiesEa
- Electrical supplyEa
- Water supplyEa
Safety ImplementationEa
TransportationEa
Repair DamagesEa
Technical Training for EnduserEa
Asbuilt Drawing, O&MNEa
Key personnel (Project manager, safety officer and QC manager)Ea
Other if any
Total X10
X20OFFICE EXPENSES
- Design FeeLot
- Home Office OperationLot
-Other if any
Total X20
X30ProfitProfit
Total X30
Total X
VATIncluded
TOTAL CLIN 0004

BOQ CLIN 0005 Tie Down

BOQ DATE PREPARED :

ACTIVITY AND LOCATION :

Chiang Mai, TH

CONSTRUCTION CONTRACT NUMBER :

N6274224R6708

PROJECT TITLE :
D/B AT-6 Facility, Wing 41, Chiang Mai, ThailandESTIMATED BY :
ITEMDESCRIPTIONQUANTITYMATERIAL COSTLABOR COSTTOTAL
NUMBERUNITUNIT COSTTOTAL (USD)UNIT COSTTOTAL (USD)USD
CLIN 0005 OPTION 0002: RENOVATE SIX EXISTING TIE DOWNS AT THE EXISTING APRON
F10SPECIAL COPNSTRUCTION
1ConcreteSQM
2SteelKg
3PaintSM
4Other (If any)
X10FIELD REQUIREMENT
X20OFFICE EXPENSE
X30PROFIT

VAT

TOTAL CLIN 0005