About this file

This document is an amendment to a request for proposals for a machine gun range project on Guam. The amendment revises the response due dates for price and non-price proposals from August 8, 2019 to August 22, 2019 and August 9, 2019 to August 23, 2019 respectively. It also updates contract drawings and specifications, revising sections related to work restrictions, exterior plants, and underground electrical distribution. The solicitation is for the Department of the Navy Naval Facilities Engineering Command for FY19 MCON Project P-735 for a machine gun range at Naval Support Activity Andersen in Guam under solicitation number N6274219R1304.

19R1304-AMD2.pdf

View the file

Other files

File Type Posted
P-735_AMD6.pdf PDF
P-735_AMD5.pdf PDF
191304-AMD4.pdf PDF
P735_AMD3.pdf PDF
19R1304-AMD1.pdf PDF
N6274219R1304_Foreign_National_Access_Req.pdf PDF
N6274219R1304_Contractor_Memo_IIILog.pdf PDF
N6274219R1304_P735_Disc_Rel_Form.pdf PDF
N6274219R1304_Affidavit_BAL.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP No. N62742-19-R-1304 Amendment No. 0002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

The following items are applicable to this modification:

DOCUMENT 00100 INSTRUCTIONS TO PROPOSERS

Paragraph 1.1 NUMBER OF COPIES/TIME OF RECEIPT

Subparagraph a. PRICE PROPOSAL (PAPER). Line 2. Delete “8 August 2019” and insert “22 August 2019”.

Subparagraph b. NON-PRICE (FACTORS 1, 2, 3, 4 AND 5) (PAPER). Line 2. Delete “8 August 2019” and insert “22 August 2019”.

Subparagraph c. SUBCONTRACTING PLAN (PAPER). Line 2. Delete “9 August 2019” and insert “23 August 2019”.

DOCUMENT 00800 SPECIAL CONTRACT REQUIREMENTS

Paragraph 1.2 ORGANIZATIONAL CONFLICTS OF INTEREST.

Delete the following:

“ORGANIZATIONAL CONFLICTS OF INTEREST. Review of FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest is encouraged. In accordance with FAR 9.507-2, the following provides the proposed “Organizational Conflicts of Interest” clause that will be included in the resultant contract. The application of FAR 9.5 and the terms of the proposed clause is non-negotiable. The restrictions described herein shall apply to the Contractor and its affiliates, consultants and subcontracts under this contract. If the Contractor under this contract prepares or assists in preparing a statement of work, specifications and plans, the Contractor and its affiliates and any subcontractors/subconsultants shall be ineligible to bid or participate, in any capacity, in any contractual effort which is based on such statement of work or specifications and plans as a prime contractor, subcontractor, consultant or in any similar capacity. The Contractor shall not incorporate its products or services in such statement of work or specification unless so directed in writing by the Contracting Officer, in which case the restriction shall not apply. This contract shall include this clause in its subcontractor's or consultants' agreements concerning the performance of this contract.”

Replace with the following:

“ORGANIZATIONAL CONFLICTS OF INTEREST. Review of FAR Subpart 9.5, Organizational and Consultant Conflicts of Interest is encouraged. The intent is to identify and evaluate potential conflicts of interest prior to contract award. Generally, if the Contractor / affiliates /subcontractors under this contract prepares or assists in preparing a statement of work, specifications and plans, the Contractor and its affiliates and any subcontractors/subconsultants may be ineligible to bid or participate, in any capacity, in any contractual effort which is based on such statement of work or specifications and plans as a prime contractor, subcontractor, consultant or in any similar capacity. In addition, the Contractor and its affiliates and/or subcontractors under this contract are ineligible to bid or participate, in any capacity, in any contractual effort which is based upon a statement of work, specifications and plans which the Contractor and its affiliates and/or subcontractors previously prepared or assisted in preparing.”

DOCUMENT 00 01 15 LIST OF DRAWINGS

1.2. CONTRACT DRAWINGS. The following drawings are revised as of July 11, 2019:

NAVFAC DWG NO. TITLE

17228572 Overall Site Improvement Plan

The following drawings are revised as of July 26, 2019:

NAVFAC DWG NO. TITLE

17228573 Fire Fuel Break Plan 17228575 Parking and Support Facilities Plan 17228578 Parking and Support Facilities Geometric Plan 17228596 Miscellaneous Details 17228601 Site Grading and Drainage Plan 17228623 Range General Arrangement Plan 17228624 Range Sight Lines Layout Plan 17228626 Range SIT and DSIT Target Details 17228627 Range SAT Target Details 17228628 Range MIT Target Details 17228629 Range Firing Mound Layout Plan 17228630 Range Earth Berm Layout Plan 17228631 Range Firing Mound Details 17228632 Range Firing Mound Typical Sections and Details - Sheet 1 of 2 17228633 Range Firing Mound Typical Sections and Details - Sheet 2 of 2 17228634 Range Earth Berm Typical Sections and Details 17228638 Range Miscellaneous Details 17228643 Range Site Layout Plan – Sheet 1 of 13 17228644 Range Site Layout Plan – Sheet 2 of 13 17228645 Range Site Layout Plan – Sheet 3 of 13 17228646 Range Site Layout Plan – Sheet 4 of 13 17228647 Range Site Layout Plan – Sheet 5 of 13 17228648 Range Site Layout Plan – Sheet 6 of 13 17228649 Range Site Layout Plan – Sheet 7 of 13 17228650 Range Site Layout Plan – Sheet 8 of 13 17228651 Range Site Layout Plan – Sheet 9 of 13 17228652 Range Site Layout Plan – Sheet 10 of 13 17228653 Range Site Layout Plan – Sheet 11 of 13 17228654 Range Site Layout Plan – Sheet 12 of 13 17228655 Range Site Layout Plan – Sheet 13 of 13 17228669 Planting Details 17228670 Plant Material Schedule

The following drawings are revised as of July 29, 2019:

NAVFAC DWG NO. TITLE

17228598 Miscellaneous Details 17228599 Miscellaneous Details

These revised drawings accompany this Amendment.

SPECIFICATION REVISIONS

SECTION 01 14 00 WORK RESTRICTIONS

1.3 SPECIAL SCHEDULING REQUIREMENTS

After subparagraph c, add the following:

“d. Schedule connections to existing utilities no earlier than 4 months prior to construction completion.”

SECTION 32 93 00 EXTERIOR PLANTS

1.3 SUBMITTALS, SD-03 Product Data

Delete “Weed Control Fabric, G.”

2.6 WEED CONTROL FABRIC

Delete this paragraph and associated subparagraph in their entirety.

3.5.4 Weed Control Fabric Installation

Delete this paragraph in its entirety.

SECTION 33 71 02 UNDERGROUND ELECTRICAL DISTRIBUTION

2.1.2 Plastic Conduit for Direct Burial

Delete “EPC-40”

File details come from the government source that posted it. Updated .