This is a Contractor Price Breakdown attachment for a Voyage Repair Availability project for the USNS YUKON (T-AO 202). The spreadsheet template is designed to capture pricing for work performed during the vessel's repair availability scheduled from November 23 through December 13, 2026, in Chinhae, South Korea. The template provides separate columns for prime contractor and subcontractor labor hours, labor rates, material costs (CFM), and other specified costs across multiple work item categories.
The work items listed under Category A (Intent and General Requirements) include ten repair and maintenance tasks: Project Management, Gas Free Certificates, Renew Containment Tub Drain Valves, NR2 CT Winch Repairs, Fabricate CFW and JW Strainer Baskets, Galley Refrigeration Service, Inspect/Test/Certify Material Handling Equipment (Aerial Work Platform), Troubleshoot and Repair Bridge AC, Reconditioning Fans and Motors, and Cargo Boom Guide Bumper Replacement. All line items in the template currently show zero hours and zero costs, indicating this is a blank pricing form awaiting contractor input. The solicitation (N6264927RK002) is issued by NAVSUP Fleet Logistics Center Yokosuka and is a competitive, firm-fixed-price single award intended only for sources authorized to operate in South Korea per DFARS requirements. Offerors must register in SAM.gov and demonstrate an executable operational plan for personnel base access credentials as a mandatory performance requirement.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| USNS YUKON VRA KR | ||||||
| 23 NOV - 13 DEC 2026 | PRIME CONTRACTOR | SUBCONTRACTOR | Prime Labor Rate : | $0.00 | ||
| Work Item No. | Title | Labor hrs. | Labor |
Price US$ Material Price
(CFM)
US$ Labor hrs. Labor Price US$ Material Price
(CFM)
US$ Other (specify in Remarks)
| US$ | Total Price | ||||||||||
| US$ | CAT | ||||||||||
| 1 | Intent and General Requirements | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 13 | Project Management | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 20 | Gas Free Certificates | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 114 | Renew Containment Tub Drain Valves | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 501 | NR2 CT Winch Repairs | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 502 | Fabricate CFW and JW Strainer Baskets | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 601 | Galley Refrigeration Service | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 666 | Inspect, Test and Certify Material Handling Equipment - Aerial Work Platform | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 801 | Troubleshoot and Repair Bridge AC | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 808 | Reconditioning Fans and Motors | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A | |
| 1002 | Cargo Boom Guide Bumper Replacement | 0 | $0 | $0 | 0 | $0 | $0 | $0 | $0 | A |
TOTAL CAT A 0 $0.00 $0.00 0 $0.00 $0.00 $0.00 $0.00
Remarks: (provide the information in space below. Use separate sheet of paper if necessary.)
N40345-17-R-0038 ATTACHMENT J-5
Sheet2
Sheet3
File details come from the government source that posted it. Updated .