This document outlines the requirements for an Indefinite Delivery/Indefinite Quantity contract to provide Architect-Engineer services for various waterfront projects under the Naval Facilities Engineering Command, Hawaii. Firms are invited to submit a Standard Form 330 by November 5, 2019 at 2:00pm Hawaii Standard Time through the DoD SAFE system. Services will include project documentation, design, cost estimating, surveys and other services for projects such as piers, wharves, bulkheads and bridges. The contract will have a one year base period and four one-year options, not to exceed $99 million total. Evaluation criteria include specialized experience, past performance, staff qualifications, quality control and small business participation. Firms must demonstrate experience in designs, cost estimates, studies and other work for waterfront projects valued over $20 million for new construction or $10 million for renovation.
N6247819R5035IDIQWATERFRONTSYNOPSIS_MOD1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N6247819R5035IDIQWATERFRONTSYNOPSIS_MOD3.doc | DOC document | |
| N6247819R5035_Q&A_MOD3.pdf | ||
| N6247819R5035IDIQWATERFRONTSYNOPSIS_MOD2.doc | DOC document | |
| N6247819R5035_Q&A_MOD2.pdf | ||
| N6247819R5035_QA_MOD1.pdf | ||
| ATTACHMENT1_PPQ-0.doc | DOC document | |
| ATTACHMENT4_SB_PARTICIP&COMMIT.docx | DOCX document | |
| N6247819R5035IDIQWATERFRONTSYNOPSIS.pdf | ||
| ATTACHMENT2_SB_SUBK_RECORD.docx | DOCX document | |
| ATTACHMENT3_SBSP.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
9 October 2019
N62478-19-R-5035 INDEFINITE DELIVERY/INDEFINITE QUANTITY CONTRACT FOR
ARCHITECT-ENGINEER SERVICES FOR VARIOUS WATERFRONT PROJECTS AND
OTHER PROJECTS PRIMARILY UNDER THE COGNIZANCE OF NAVAL FACILITIES
ENGINEERING COMMAND, HAWAII
ALL INFORMATION NEEDED FOR INTERESTED PARTIES TO SUBMIT A STANDARD
FORM SF 330, ARCHITECT ENGINEER QUALIFICATIONS IS CONTAINED HEREIN.
THERE IS NO SEPARATE REQUEST FOR PROPOSALS (RFP) PACKAGE TO
DOWNLOAD.
This procurement will result in one Indefinite Delivery/Indefinite Quantity (IDIQ) contract for multi-discipline Architect-Engineer (AE) services for waterfront projects at various locations under the cognizance of NAVFAC Hawaii. NAVFAC Hawaii AOR includes the state of Hawaii, but may also include work worldwide. These services will be procured in accordance with 40 USC Chapter 11, Selection of Architects and Engineers, as implemented by FAR Subpart 36.6. The IDIQ contract will be for a base period of one year and four one-year option periods (if exercised). The total fee for the contract term shall not exceed $99,000,000. The guaranteed minimum for the contract term (including option years) is $10,000. Firm-fixed price task orders will be negotiated for this contract. There will be no dollar limit per task order and no dollar limit per year. Estimated start date is June 2020.
This proposed contract is being solicited on an UNRESTRICTED basis. The Small Business size standard classification is North American Industrial Classification System (NAICS) Code 541330, Engineering Services. The Government seeks the most highly qualified firm to perform the required services, based on the demonstrated competence and qualifications, in accordance with the selection criteria.
The market research study Sources Sought Number ACQ33FY190002 conducted by NAVFAC Hawaii included an assessment of relevant qualifications and capabilities of potentially qualified firms. As a result of the market research analysis, a determination was made to solicit this procurement on an unrestricted basis inviting full and open competition. The NAVFAC Hawaii small business office concurs with this decision.
The type of waterfront design and engineering services expected to be performed under this contract include, but are not limited to, the execution and delivery of Military Construction (MILCON) project documentation (DD Form 1391); Functional Analysis and Concept Development (FACD) workshops, Design Charrettes; Design-Build (DB) Request for Proposal (RFP) solicitation documents; Design-Bid-Build (DBB) Design contract documents;
SPECSINTACT program; cost estimates utilizing the MII cost estimating system; technical surveys and reports including concept studies, site engineering investigation, topographical survey, geotechnical investigation, hazardous material survey, Munitions of Explosive Concern (MEC) survey, hydrographic survey, and others; Collateral Equipment (CEQ) Buy Packages;
Comprehensive Interior Design (CID) including Structural Interior Design (SID) and Furniture, Fixtures, and Equipment (FF&E); and Post Construction Award Services (PCAS). PCAS consist of technical consultation during construction, including, but not limited to, review of construction submittals, site visits, operations and maintenance support information, record drawings, and other miscellaneous services. Waterfront projects consist of, but are not limited to, new construction and/or repair/renovation of piers/wharves, bulkheads, drydocks and caissons, waterfront facilities such as warehouses or waterfront operations buildings, and bridges. Supporting facilities may include utility connections (water, sewers, electrical, telecommunications, and cable television).
All Firms/Offerors are advised that registration in System for Award Management (SAM) Database is required prior to submission of an SF330. Failure to register in the SAM Database may render your firm ineligible for award. For more information, check the SAM Web site:
https://www.sam.gov.
The awarded contract will be subject to specific provisions addressing the avoidance of organizational conflicts of interest. The prime firm for this contract will be required to perform throughout the contract term.
The selected firm and its subsidiaries or affiliates may be tasked to assist in the preparation of a statement of work, a plan, or a specification for a construction project. This includes concept design, which includes preparation of project programming documents (DD 1391), facility studies, environment assessments, or other activities that result in identification of project scope and cost. The selected firm, its subsidiaries or affiliates that design or prepare specifications for a construction contract cannot provide the construction services for the same project.
Interviews may be scheduled with firms slated as the most highly qualified. Firms slated for interviews may be asked to clarify information contained in the SF330 submittal. Elaborate presentations are not desired.
SELECTION CRITERIA
Firms/Offerors responding to this synopsis will be evaluated to determine the most highly qualified firms to perform the required services in accordance with the published selection criteria. Failure to comply with instructions, or provide complete information may affect the firm’s evaluation or disqualify the firm from further consideration. The selection criteria are in descending order of importance, with the last criterion for volume of work to serve as the tiebreaker. Specific selection criteria include:
1. Specialized Experience
2. Professional Qualifications
3. Past Performance
4. Quality Control Program
5. Program Management and Capacity
6. Sustainable Design
7. Commitment to Small Business
8. Firm Location
9. Volume of Work (tiebreaker)
Criterion 1 - Specialized Experience (SF330, Part I, Section F):
Firms/Offerors will be evaluated on specialized experience in performance of services similar to those anticipated under this contract through evaluation of experience in the following:
1. “Recent relevant projects” for new construction and/or repair/renovation in the following types of projects: piers/wharves; bulkheads; drydocks and caissons; waterfront facilities such as warehouses or waterfront operations buildings; and bridges. Each project’s estimated construction cost shall be $20 million or more for new construction projects or $10 million or more for repair/renovation projects. If the construction contract has been awarded, provide the awarded construction value per project/contract.
2. “Specified Design/Engineering Services”. Firms/Offerors must demonstrate experience in all of the following five (5) types of services:
Preparation of drawings/specifications for the purpose of a Design-Bid-Build (DBB) construction contract for “recent relevant projects” Preparation of Design-Build (DB) Request for Proposal solicitation documents utilizing the NAVFAC Design-Build RFP Six-Part Master Format for “recent relevant projects” Execution of MILCON Region/FEC Team DD 1391 project documentation or similar project programming documents for “recent relevant projects” Performing/conducting Functional Analysis Concept Development (FACD)/design charrettes for “recent relevant projects” Preparation of Mobile Crane Load Studies on piers and wharves, berthing and mooring analysis, caisson overhaul and certification and processing in-water quality permits including Best Management Practices (BMP) and applicable monitoring assessment plan
(AMAP).
Specified design/engineering services for recent relevant projects shall have been completed within the past ten (10) years immediately preceding the date of issuance of this notice.
Services that are on-going will not be considered. Completed specified design/engineering services (i.e. DBB or DB RFP) may be exclusive of Post Construction Award Services
(PCAS).
Favorable Items: Firms/Offerors may be considered more favorably by demonstrating the following, which are not listed in any order of preference:
1. Experience in new construction projects may be given more favorable consideration than experience in repair/renovation projects.
2. Experience in Department of Defense (DoD) projects (e.g. NAVFAC, USACE, Air Force, NGB, etc.) may be given more favorable consideration.
3. Experience in projects in tropical regions may be given more favorable consideration. For this acquisition, tropical is defined as being located between the Tropic of Capricorn and the Tropic of Cancer, excluding arid and high elevation areas. Tropical regions are hot and humid and require special attention in the design off shore-based facilities subject to highly corrosive environments. See UFC 3-440-05N, Change 2 (latest version).
4. Experience in more variety in the types of recent relevant projects described above may be given more favorable consideration.
5. Experience of the Firm/Offeror performed as the Prime A-E or Prime Joint Venture (JV)/ Limited Liability Company (LLC)/Limited Partnership (LP) may be given more favorable consideration than experience performed by the Firm/Offeror as a sub-consultant.
6. The Firm’s/Offeror’s experience as Prime A-E DOR for a Design-Bid-Build (DBB) contract may be given more favorable consideration than experience as the A-E Designer of Record (DOR) for a Design-Build Contractor.
7. Proposed team with a demonstrated history of firms working successfully together on prior projects as a team may be considered more favorably than those without such history.
8. Experience in cost estimates utilizing the MII cost estimating system may be given more favorable consideration.
Submission Requirements:
1. Projects shall be submitted on the SF330, Part I, Section F.
2. Provide a maximum of seven (7) recent relevant projects with design and engineering services completed. Projects with design and engineering services that are on-going will not be considered. If more than the maximum number of projects are submitted, the Government will only evaluate projects up to the maximum number authorized in the order submitted.
3. For submittal purposes, a task order on an IDIQ contract is considered a project, as is a stand-alone contract award. Do not submit an IDIQ contract as an example project. Instead, list relevant task orders or stand-alone contract awards that fit within the definition above.
The Government will not evaluate information provided for an IDIQ contract. Examples of project work submitted that do not conform to this requirement will not be evaluated.
4. For each project submitted, annotate they type(s) of “specified design/engineering services” that were included. All of the types of services need not be in one project scope, however, in order to be evaluated as having met the criteria for relevancy, the SF330 must demonstrate that the Firm/Offeror has experience in each of the five types of “specified design/ engineering services”, e.g. DBB, DB, etc.
5. Submit experience in “specified design/engineering services” from the Firm/Offeror performed as either a Prime A-E or sub-consultant. The Firm’s/Offeror’s experience as A-E Designer of Record (DOR) for a Design-Build Contractor may be submitted.
6. Do not submit experience in specified design/engineering services from the Firm’s/Offeror’s sub-consultant(s); however, experience from the Firm’s/Offeror’s sub-consultant(s) may be submitted and may be considered for preparation of Mobile Crane Load Studies on piers and wharves, berthing and mooring analysis, caisson overhaul and certification and processing in-water quality permits including Best Management Practices (BMP) and applicable monitoring assessment plan (AMAP).
7. All projects provided in the SF330 must be completed by the actual office/branch/regional office proposed to manage and perform work under this contract. Projects not meeting this requirement will be excluded from consideration in the evaluation.
8. For projects performed as a subcontractor or a JV/LLC/LP involving different partners, specifically indicate the value of the work performed as a subcontractor or by those firms proposed for this contract, and identify the specific roles and responsibilities performed as a subcontractor or by those firms on the project rather than the work performed on the project as a whole. If the project description does not clearly delineate the work performed by the entity/entities offering/teaming on this contract, the project could be eliminated from consideration.
NOTE: If the Firm/Offeror is a JV/LLC/LP, projects performed by the JV/LLC/LP should be submitted; however, if there are no projects performed by the JV/LLC/LP, such as in the case of a newly formed JV/LLC/LP, projects shall be submitted for each partner, not to exceed a total of four (4) projects for each partner. Firms/Offerors failing to provide projects from all JV/LLC/LP partners will be considered to have not met the requirements of the criterion. If more than four projects are submitted for each JV/LLC/LP partner, the Government will only evaluate the first four projects in the order submitted and disregard any other projects thereafter.
9. Special Instructions for SF330, Part I, Section F. Include the following additional information when completing Section F:
Block 21: Include Contract number or project identification number with project title/location.
Block 22: Year completed of professional services is required, and year completed of construction (if applicable). If construction is not completed, indicate status, e.g.
“estimated Jan 2020”.
Block 23(c): E-mail address and phone number for the project’s point of contact are required.
Block 24, include the following items:
a. Contract period of performance
b. Awarded contract value
c. Current contract value
d. Estimated construction cost
e. Type of professional services performed (e.g. DBB drawings/specifications as the
Prime Consultant or as a Sub-consultant; Designer of Record for Design-Build Contract as a Prime Consultant or Sub-consultant; Design-Build RFP preparation as the Prime Consultant or as a Sub-consultant; etc.)
f. Brief description of project and relevance to specialized experience as outlined above in Criteria 1.
g. For projects which the Firm/Offeror performed as a sub-consultant, indicate the value of the work performed as a sub-consultant, and identify the specific role(s) and responsibilities performed as a sub-consultant rather than the work performed on the project as a whole.
Block 25: To enable verification, list all firms (or branch offices) from Section C that were involved in the example project. Indicate each firm’s DUNS number, role on the project, whether as a Prime A-E or sub-consultant and the firm’s discipline(s). e.g.
“Structural Prime” or “Electrical sub-consultant.”
All information for Criterion 1 should be submitted in the SF330, Part I, Section F. The Government WILL NOT consider information submitted in addition to Part 1, Section F in evaluation of Criterion 1.
Criterion 2 - Professional Qualifications (SF330, Part I, Sections E & G):
Firms/Offerors will be evaluated on professional qualifications, competence, and experience of the proposed key personnel in providing services to accomplish the tasks required under this contract, including participation in example projects as outlined in the SF330, Part 1, Section G.
Key personnel are individuals who will have major contract or project management responsibilities and/or will provide unusual or unique expertise. Specific disciplines that must be included in key personnel are Structural (Principal-in-Charge, Project Structural Engineer and Project Waterfront Engineers), Civil, Architect, Mechanical, Electrical, Geotechnical, Fire Protection and Cathodic Protection.
Key personnel will be evaluated on their professional qualifications. All key personnel must be licensed in their specific discipline, with the exception of the Structural Engineer, which can be a licensed Civil Engineer if a State does not issue licenses in Structural engineering.
Key personnel will also be evaluated on their competence and experience in the performance of “recent relevant projects” and “specified design/engineering services”. See Criterion 1 for the definition of “recent relevant projects” and “specified design/engineering services”.
Favorable Items: Firms/Offerors may be given more favorable consideration for their key personnel demonstrating the following, which are not listed in any order of preference:
1. Experience in Department of Defense (DoD) projects (e.g. NAVFAC, USACE, Air Force, NGB, etc.) may be given more favorable consideration.
2. Experience in projects in tropical regions may be given more favorable consideration. For this acquisition, tropical is defined as being located between the Tropic of Capricorn and the Tropic of Cancer, excluding arid and high elevation areas. Tropical regions are hot and humid and require special attention in the design off shore-based facilities subject to highly corrosive environments. See UFC 3-440-05N, Change 2 (latest version).
3. Experience in more variety in the types of “recent relevant projects” by key personnel may be given more favorable consideration.
4. Experience in coastal engineering; tsunami design per ASCE 7-16; and seismic design of wharves by key personnel may be given more favorable consideration.
5. Demonstrated a history of key personnel working together on projects indicated in Criterion 1 may be given more favorable consideration.
1. Submit information using SF330, Part I, Section E.
2. Provide resumes for all proposed key personnel that illustrate experience in the work proposed under this contract. For this acquisition, key personnel are designated as follows, with the maximum number of key personnel annotated in parentheses:
Principal-in-Charge of the Prime A-E firm (1) Structural Engineers (5) Waterfront Engineers (2) Civil (1) Architect (1) Mechanical (1) Electrical (1) Geotechnical (1) Fire Protection (1) Cathodic Protection (1)
If more than the maximum number of resumes is submitted for each key discipline, the Government will only evaluate resumes up to the maximum number authorized in the order submitted per discipline. Resumes of disciplines that are not required, if submitted, will not be considered in the evaluation.
3. Resumes shall indicate: U.S. professional license (include State and discipline), certification, registration, license and/or accreditation in appropriate disciplines, number of years of experience, firm name and location, education; and indicate proposed role in this contract (e.g. Structural Project Engineer, Project Architect, Civil Project Engineer, etc.) Do not use other company titles or current position in the firm such as “Type I Engineer” where the discipline and role are unidentifiable.
4. Submit a maximum of five (5) recent relevant projects for each key personnel, demonstrating experience in specified design/engineering services. See Criterion 1 for the definition of “recent relevant project” and “specified design/engineering services”. Specialized experience and technical competence shall be limited to only the Structural and Waterfront disciplines. Complete Section E for each of the Structural and Waterfront disciplines, providing all requested information. For other key personnel, complete only Blocks 12 through 18; and leave Block 19, Relevant Projects, blank. Relevant project information for other key personnel is not required and if submitted, will not be considered in the evaluation.
5. Special Instructions for SF330, Part I, Section E for Structural and Waterfront Key Personnel. Include the following additional information when completing Section E:
Block 19: Submit a maximum of five (5) projects. A project is defined either as a stand-alone contract or a single task order in an IDIQ contract having the features described above. Do not submit an IDIQ contract as an example project. If more than five (5) projects are submitted, the Government will evaluate the first five (5) projects listed in Part I, Section E and disregard any other project information. Specified design/ engineering services that are on-going will not be considered. Specified design/ engineering services can be exclusive of Post Construction Award Services (PCAS).
Block 19 (2):
o Year Professional Services completed (must be within the past ten (10) years) o Year Construction completed, if applicable
Block 19 (3):
o Role and work performed by the key personnel (including the specialized design and engineering services performed) o Brief description of the “recent relevant project”, e.g. piers/wharves, etc.
o Type of “specified design/engineering” service performed, e.g. DBB, DB, etc. Also indicate if services performed as a Prime or Sub-consultant o Estimated or actual construction cost
If a project does not provide the all of the requested data, that project may be evaluated less favorably or not considered.
6. Indicate participation of key personnel in Criterion 1 example projects in the SF330, Part 1, Section G.
All information for Criterion 2 shall be submitted in the SF330, Part I, Sections E and G.
The Government WILL NOT consider information submitted in addition to the information provided in Part I, Sections E and G in evaluation of Criterion 2.
Criterion 3 - Past Performance (SF330, Part I, Section F and Attachment (1)):
Firms/Offerors will be evaluated on past performance with Government agencies and private industry in terms of work quality, compliance with schedules, cost control, and stakeholder/ customer satisfaction. Evaluating past performance and experience will include information provided in Past Performance Questionnaires (PPQs) or CPARS for Criterion 1 projects and may include customer inquiries, Government databases, and other information available to the Government including contacts with points of contact in other criteria.
PAST PERFORMANCE INFORMATION SUBMITTED BY THE FIRM/OFFEROR FOR
PROJECTS NOT LISTED UNDER CRITERION 1 WILL NOT BE CONSIDERED.
NOTE:
1. Past performance information for projects listed under Criterion 1 may be given greater weight than information obtained by the Government from customer inquiries, Government databases, and other information available to the Government.
2. Past performance information for the Firm/Offeror for services performed as a subcontractor or sub-consultant will not be given the same level of consideration as past performance performed as the Prime contractor.
Submission Requirements:
SUBMIT A COMPLETED CPARS/ACASS EVALUATION FOR EACH PROJECT UNDER
CRITERION 1. IF A COMPLETED CPARS/ACASS EVALUATION IS NOT AVAILABLE,
submit a Past Performance Questionnaire (PPQ) (Attachment (1)), which is included in this notice. Submit the PPQ to the client to complete. The PPQ must be signed by the client.
Include the evaluation immediately after each project that it is associated in Section F. The CPAR, DD2631 (ACASS) or Performance Survey provided in Section F will not be counted towards the SF330 page limitation. DO NOT SUBMIT A PPQ WHEN A COMPLETED
CPARS/ACASS IS AVAILABLE. DO NOT SUBMIT CPARS/ACASS FOR PROJECTS FOR
WHICH THE FIRM/OFFEROR WAS NOT THE PRIME. IF THE FIRM/OFFEROR WAS
THE DB DOR FOR A PROJECT, SUBMIT A PPQ FOR THE FIRM/OFFEROR AND DO
NOT SUBMIT THE CPARS/CCASS FOR THE PRIME CONSTRUCTION CONTRACTOR.
IF THE FIRM/OFFEROR WAS A SUBCONSULTANT ON A PROJECT, DO NOT SUBMIT
THE CPARS/ACASS FOR THE PRIME A-E; INSTEAD SUBMIT A PPQ FOR THE
FIRM/OFFEROR.
IF A CPARS/ACASS EVALUATION IS NOT AVAILABLE, ensure correct phone numbers and email addresses are provided for the client point of contact. Completed PPQs should be submitted with your SF330. If the Firm/Offeror is unable to obtain a completed PPQ from a client for a project(s) before the response date set forth in this notice, Firms/Offerors should complete and submit with their responses the first page of the PPQ (Attachment (1)), which will provide contract and client information for the respective project(s). Firms/Offerors may submit a PPQ previously submitted under a different Notice/RFP, such as NAVFAC or USACE Past Performance Questionnaires (legible copies are acceptable) as long as it is on the same form that is posted with this Synopsis. Firms/Offerors should follow up with clients/references to ensure timely submittal of questionnaires. If requested by the client, questionnaires may be submitted directly to the Government's point of contact, Naval Facilities Engineering Command, Hawaii, Code ACQ33, Attn: Ms. Alice Mende via email at Alice.Mende@navy.mil and Ms. Jamie Ikehara at Jamie.Ikehara@navy.mil prior to the response date. Firms/Offerors shall not incorporate by reference into their response PPQs or CPARS/ ACASS previously submitted in response to other A-E services procurements. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
Firms/Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Criterion 1, Specialized Experience. Firms/Offerors may also address any adverse past performance issues. Information shall not exceed one single-sided page in total and will not be counted towards the SF330 page limitation. Include the information immediately after each evaluation that it is associated in Section F.
The Performance Survey shall be from the contracting agent and/or their representative responsible for the construction contract administration or from the facility owner/user. It shall not be from the prime construction contractor on a design-build project, nor shall it be from a prime contractor to a subcontractor. PPQs will be considered if it is prepared and signed by the project owner’s/client’s representative, i.e. someone who is authorized to provide evaluation/ feedback on the A-E’s performance to show the client’s satisfaction. If the Firm/Offeror was hired as a subconsultant to a Prime A-E, that Prime A-E who hired you cannot provide a PPQ;
rather, that Prime A-E’s client must be the one to provide the PPQ.
Awards, letters of commendation, certificates of appreciation, etc. shall not be submitted and will not be considered in the evaluation.
Criterion 4 - Quality Control Program (SF330, Part I, Section H):
Firms/Offerors will be evaluated on the strength of the quality control program proposed by the Firm/Offeror to ensure quality products and services under this contract, and means of ensuring quality services from their consultants/subcontractors.
Submission Requirements:
Describe the quality control program that will be utilized for all deliverables of this contract and the management approach for quality control processes and procedures. The description shall:
1. Explain the quality control program including an example of how the plan has worked for one of the projects submitted as part of SF330, Section F or how the plan will work if it has not been used previously.
2. Describe specific quality control processes and procedures proposed for this contract including technical accuracy of and assurance of overall coordination of plans and specifications, and engineering and design services; incorporation of the latest criteria;
lessons learned and review comments, etc.
3. Identify the quality control manager (by his/her name and firm) and any other key personnel responsible for the quality control program and a description of their roles and responsibilities.
4. Describe how the Firm’s/Offeror’s quality control program extends to management of subcontractors to ensure design quality consistently between all design disciplines or team.
Criterion 5 - Program Management and Capacity (SF330, Part I, Section H):
Firms/Offerors will be evaluated on the Firm’s/Offeror’s ability to plan for and manage work under the contract and the capacity to accomplish the work in the required time.
1. Program Management:
a. In reference to the Section D Organizational Chart, discuss the management plan for this contract and personnel roles in the organization.
b. Describe the ability of the Firm/Offeror to manage, coordinate and work effectively with team members, both internal staff and consultants, and why it is the most efficient and effective organization structure in execution of the work.
c. Discuss the history of working relationships with team members, including JV/LLC/LP partners where applicable.
2. Capacity:
a. Describe the Firm’s/Offeror’s present workload. Indicate all existing contracts that the proposing Firm/Offeror is currently on either as prime or subcontractor. Indicate a list of existing open task orders or contracts currently being worked on, along with the total design fee for each task order or contract. Describe the Firm’s/Offeror’s present workload on other IDIQ contracts that may present conflicts with this contract.
b. Indicate the availability of the project team (including sub-consultants) for the specified contract performance period.
c. Describe the workload/availability of key personnel for the duration of the anticipated contract performance period and the ability of the Firm/Offeror to provide qualified backup staffing of key personnel to ensure continuity of services. General statements of availability/capacity may be considered less favorably.
d. Describe how the proposed team will complete several task orders concurrently requiring quick turnaround with similar deliverable due dates.
Note: General statements of availability/capacity may be considered less favorably.
Criterion 6 - Sustainable Design (SF330, Part I, Section H)
Firms/Offerors will be evaluated in terms of their knowledge and demonstrated experience in applying sustainability concepts through an integral design approach and designing in accordance with recognized sustainability rating systems or current third party certification (TPC) programs, such as U.S. Green Building Council (USGBC) LEED, Green Building Initiative (GBI) Green Globe, or GBI Guiding Principles Compliance (GPC) as required by Unified Facilities Criteria (UFC) 1-200-02 High Performance and Sustainable Building Requirements.
Certified projects will be considered more favorable than projects not yet certified. Projects submitted from the Firm’s/Offeror’s sub-consultant may be considered less favorable than projects submitted by the Firm/Offeror.
Submission Requirements:
Identify examples indicating A-E team’s (including sub-consultants) experience and concepts employed, and certification awarded. For projects certified, submit a copy of the certificate.
Certificates are not counted in the overall page count. Provide a maximum of three (3) projects that have attained or been submitted for TPC. For projects not yet certified, identify the date the project was submitted. For all projects, identify the team’s major contribution(s) (design elements, features, equipment, etc.) in attainment of the certification. If more than three projects are submitted for evaluation, the Government will evaluate the first three projects and disregard any other project information after the first three projects.
Identify accredited professionals (by his/her name and firm) proposed for this contract.
Accredited professionals do not have to be key personnel listed under Criterion 2, Professional Qualifications. Discuss key sustainable design personnel experience and qualifications.
Criterion 7 - Commitment to Small Business (SF330, Part I, Section H and Attachments (2) thru (4)):
Firms/Offerors will be evaluated in terms of the extent to which they have identified and committed to Small Business (SB), Small Disadvantaged Business (SDB), Women-Owned Small Business (WOSB), Historically Underutilized Business Zone Small Business (HUBZoneSB), Veteran-Owned Small Business (VOSB), Service Disabled Veteran Owned Small Business (SDVOSB), and if applicable, Historically Black Colleges or Universities and Minority Institutions (HBCU/MI) in performance of this contract, whether as a joint venture, teaming arrangement, or subcontractor. The Government will evaluate proposals based on: (A) Past Performance in Utilization of Small Business Concerns and (B) Participation of Small Business Concerns for this requirement.
Submission Requirements:
Subfactor (A) Past Performance in Utilization of Small Business Concerns
In support of Subfactor (A), all Firms/Offerors shall provide historical data on utilization of SB, SDB, WOSB, HUBZoneSB, VOSB, SDVOSB and HBCU/MI.
All LARGE BUSINESS Firms/Offerors shall submit “final” or “most recent” Individual Subcontracting Reports (ISRs) associated with each project submitted for consideration under Criterion 1, Specialized Experience if a small business subcontracting plan was required by the contract. If ISRs are not FINAL or MOST RECENT, they will not be considered. If subcontracting goals were not met, provide an explanation for all instances of failures to meet goals. If an ISR was not applicable to a project, (i.e. state and local government agencies or private sector projects), large businesses shall submit similar ISR documentation utilizing Attachment (2), Small Business Subcontracting Record, which shows the Firm’s/Offeror’s utilization of the various types of small business firms for that particular project.
All SMALL BUSINESS Firms/Offerors shall submit documentation which shows their utilization of the various types of small business firms associated with each project submitted for consideration under Criterion 1, Specialized Experience. Small businesses shall submit documentation similar to the ISR, utilizing Attachment (2), Small Business Subcontracting Record, which shows the Firm’s/Offeror’s utilization of the various types of small business firms for that particular project.
Notes:
(1) The Government reserves the right to consider information on other recent, relevant projects from all available sources.
(2) If the Prime is a new Joint Venture or other entity consisting of more than one firm, provide achievements information for each individual business entity that will be responsible for managing the subcontracting program and clearly describe those responsibilities.
(3) Failure to provide ISRs or any other requested information must be fully explained and may negatively impact your evaluation.
Subfactor (B) Participation of Small Business Concerns
All LARGE BUSINESS Firms/Offerors shall submit a draft Small Business Subcontracting Plan, in which they will be evaluated on the extent to which they identify and commit to the published Small Business Subcontracting Program. The Secretary of the Navy has assigned the Naval Facilities Engineering Command goals for FY2019 in terms of percentages of total planned subcontracting dollars for utilization of small businesses. FY2020 goals are currently being updated and may be provided once they are finalized. For evaluation purposes of this criterion, use FY19 goals. Demonstrate the Firm’s/Offeror’s plan to meet the following goals:
FY2019
SB 45.00%
HubZone 3.00%
SDB 5.00%
WOSB 15.00%
SDVOSB 5.00%
VOSB 5.00%
If the Prime is submitting as a Joint Venture or other entity consisting of more than one firm, identify the percentage of work each member will be responsible for and indicate the size status of each member (e.g. small business, woman-owned small business, other than small business).
If a large business firm is selected for award, a Small Business Subcontracting Plan, in accordance with FAR 19.7 and DFAR 219.7, will be required and incorporated into the contract award.
The Small Business size standard classification is NAICS 541330, Engineering Services, size standard $16.5M.
The attached Small Business Subcontracting Plan template (Attachment (3)) shall be used by large businesses to complete the draft subcontracting plan. Large business firms shall submit their “draft” Small Business Subcontracting Plans utilizing this template, and ONLY this template.
All SMALL BUSINESS Firms/Offerors are not required to submit a draft Small Business Subcontracting Plan; however, small businesses shall submit similar information on the Firm’s/Offeror’s extent to which they identify and commit to subcontracting to large business (LB), SB, SDB, WOSB, HUBZoneSB, VOSB, SDVOSB, and HBCU/MI if applicable in the performance of this contract. Submit information using Attachment (4), Small Business Participation and Commitment Strategy.
Criterion 8 - Firm Location (SF330, Part I, Section H)
Provided that the application of this criterion leaves an appropriate number of qualified firms, given the nature and size of the contract, Firms/Offerors will be evaluated on the locations of their office or offices that will be performing the work under this contract and demonstrated knowledge of the general geographic areas in which projects could be located. Evaluation of Firms/Offerors will include consideration of their location within the general geographic area of the anticipated projects, primarily NAVFAC Hawaii AOR, which is primarily the State of Hawaii.
Submission Requirements:
1. Indicate location of the office(s) that will be performing the work, including main offices, branch offices, and offices of team members.
2. Address ability of the Firm/Offeror and team to ensure timely response to requests for on-site support. If the work is to be performed from other than the local area, briefly describe the ability of the Firm/Offeror to forward deploy personnel and how the team would respond to project requirements throughout the life of the contract.
3. Provide a narrative describing the team’s knowledge of the NAVFAC Hawaii AOR, primarily the State of Hawaii, to be covered by this contract.
Criterion 9 - Volume of Work (SF330, Part 1, Section H)
Firms/Offerors will be evaluated in accordance with DoD Federal Acquisition Regulation Supplement (DFARS) Procedures, Guidance and Information (PGI) 236.602-1, from data extracted from the Federal Procurement Data System (FPDS). Firms/Offerors will be evaluated in terms of work previously awarded to the Firm/Offeror by the DoD within the past twelve months with the objective of effecting an equitable distribution of contracts among qualified A-E firms including small, disadvantaged business firms, and firms that have not had prior DoD A-E contracts.
Note: DoD A-E award information will be retrieved by the Government for the Prime A-E.
DoD A-E award information will also be retrieved for the Prime A-E with multiple offices listed.
DoD award information will also be retrieved for a JV/LLC/LP and each partner in the case of a
JV/LLC/LP.
Submission Requirements:
Firms/Offerors do not need to submit data for this factor. Only provide the DUNS and CAGE numbers for the Prime A-E, Prime JV/LLC/LP and each JV/LLC/LP partner. Provide DUNS and CAGE information under SF330, Part I, Section H.
(End of selection criteria)
SF330 SUBMISSION REQUIREMENTS
Architect-Engineer firms desiring to be considered for this contract must submit a completed SF330 package.
- The SF330 shall be typed, one sided, at least 11 point Times New Roman or larger.
- The SF330 Parts I and II pages shall be numbered sequentially.
- The SF330 Parts I and II shall not exceed 100 pages single-sided 8.5 by 11 inch pages. The page limit does not include PPQs (Attachment (1)); ISRs; Small Business Subcontracting Records (Attachment (2)); Small Business Subcontracting Plan (Attachment (3)); Small Business Participation & Commitment Strategy (Attachment (4)); certificates; licenses; cover sheets/dividers; or other requested documentation (e.g., JV agreement, proof of A-E firm registration), provided that these pages do not contain any substantive information submitted in response to the synopsis or intended to demonstrate the qualifications of the Firm/Offeror.
- The SF330, Part I, Section D organizational chart may be one page single sided 11 by 17 foldout, using 11 point font or larger (font limitations do not apply to graphics, captions or tables). Firms/Offerors must indicate non-key personnel team members, including but not limited to Cost Estimator, Surveyor and Environmental in the organization chart.
- An SF330 Part II shall be submitted for each firm identified in Part I, Section C. Please include the DUNS and CAGE numbers in Block 8(c) of the SF 330, Part II.
- Any other information submitted such as company brochures, leaflets, etc., will not be considered.
In accordance with the FAR 36.601-4(b), contracts for Architect-Engineer services may only be awarded to firms permitted by law to practice the professions of architecture or engineering.
Firms/Offerors must submit proof that they are permitted by law as required by FAR 36.601- 4(b). If a Firm/Offeror is in a jurisdiction that requires A-E firm registration, the Firm/Offeror must provide proof of registration. If a Firm/Offeror is in a jurisdiction that does not require A-E firm registration, the Firm/Offeror must provide proof eligibility to practice (e.g., a summary explaining eligibility under the laws of that jurisdiction, registration to do business in a state, etc.). Failure to submit the required proof could result in a Firm’s/Offeror’s elimination from consideration.
Firms/Offerors who are submitting as a JV, LLC, LP or other type of partnering structure shall include with their SF330 submission a copy of the signed JV/LLC/LP agreement and shall submit the following additional documentation regarding their business entity:
1. A detailed statement outlining the following in terms of percentages where appropriate:
a. The relationship of the team/partners/parties in terms of business ownership, capital contribution, profit distribution or loss sharing.
b. The management approach in terms of who will conduct, direct, supervise, and control.
c. The structure and decision-making responsibilities of the partners/parties in terms of who will control the manner and method of performance of work.
d. Identify (by name and title) the personnel having the authority to legally bind the partners/parties (including authority to execute the contract documents).
2. A list of partners/parties, to include company name, DUNS and CAGE numbers, address, point of contact, email address, phone number and facsimile number.
Failure to include the JV/LLC/LP agreement may result in the Firm’s/Offeror’s elimination from further evaluation.
Architect-Engineer firms that meet the requirements described in this announcement are invited to submit a completed SF330 to Naval Facilities Engineering Command Hawaii, Code ACQ33.
Firms responding to this announcement by Tuesday, November 5, 2019 at 2:00 p.m. Hawaii Standard Time (HST) will be considered.
Electronic proposal submissions will be required and shall be submitted utilizing DoD SAFE: https://safe.apps.mil/
Electronic submissions sent via email or facsimile are not authorized and will not be accepted. Hard copy proposal submissions that are mailed, couriered, or hand delivered, etc. are not authorized and will not be accepted. Electronic proposal of your SF330 must be submitted in Adobe PDF format, and the file size must not exceed 8GB. Submit all pages of the SF330 as one complete file (multiple files will not be accepted). See below for DoD SAFE instructions.
THIS IS NOT A REQUEST FOR PROPOSAL.
Late responses will be handled in accordance with FAR 52.215-1. The point of contact are Ms.
Alice Mende, Contracting Officer, at Alice.Mende@navy.mil or Ms. Jamie Ikehara (Alternate), Contract Specialist, at Jamie.Ikehara@navy.mil.
If an SF 254/SF 255 is submitted for this solicitation, it will not be reviewed or considered.
As required above, provide verifiable evidence that your firm is permitted by law to practice the professions of architecture or engineering (e.g., state registration number).
Inquiries concerning this procurement should include solicitation number and title and be forwarded via email to Ms. Alice Mende at Alice.Mende@navy.mil and Ms. Jamie Ikehara (Alternate). Inquiries via phone will not be entertained. Questions submitted within 10 calendar days of the closing date may not be answered by the Government.
A-E firms shall have e-mail and Internet on-line access for routine exchange of correspondence.
All potential Firms/Offerors are advised to check the Federal Business Opportunities website, https://www.fbo.gov, for any additional modifications pertaining to this notice. Failure to check these websites may affect your SF330 submission.
DoD SAFE INSTRUCTIONS
There are two options to proceed from the DoD SAFE Homepage:
- Drop off as CAC User: Select this option if you have a valid Common Access Card (CAC)
- Request a Drop-Off: Select this option if you do not have a CAC
CAC AUTHENTICATED USERS:
Creating & Submitting a Drop-off (Fill in all the required input fields):
1. Click on “Drop-Off”
2. Click on “Add Many”
- Email: Enter “Alice.Mende@navy.mil”; on the next line, enter “Jamie.Ikehara@navy.mil”
- Click on “Add & Close”
3. “Short note to the Recipient”: Enter Your Name/Title, Email, Phone, Company Name and Solicitation Number (e.g. Alice Mende/Contracting Officer, Alice.Mende@navy.mil, (808) 474-2365, NAVFAC Hawaii, SF330 for N62478-19-R-5035 IDIQ Waterfront)
4. Filename’s “Description” Field: Enter description of the file name (e.g.
N6247819R5035NAVFACHawaii)
5. Do not click on “Encrypt every file”. Leave this box unchecked.
6. Click on “Click to Add Files or Drag Them Here” to search for and select your file to upload.
Only ONE (1) complete PDF file shall be uploaded, so long as the total file size does not exceed 8GB. PDF file should be titled “N6247819R5035YourCompanyName” (e.g.
N6247819R5035NAVFACHawaii)
7. Click on “Send me an email when each recipient picks up the files” – check this box so that you (the sender) will receive an email notification when the recipient has picked up the file.
8. Click on “Drop-off Files”
9. Click “OK” on the popup to confirm that the file does NOT contain classified information.
You will see your file being uploaded. After the upload is finished, you will be redirected to the “Drop-Off Completed” webpage, indicating that your file was sent successfully.
BEFORE LEAVING THIS WEBPAGE, PRINT THIS PAGE AS RECORD OF YOUR
SUBMISSION. This webpage will indicate the date and time of your SF330 submission and will serve as the official time stamp of when your submission was received by the Government. The time will display in Coordinated Universal Time (UTC) and will be converted to Hawaii Standard Time (HST). (Note, UTC is 10 hours ahead of HST.)
10. If your file is successfully uploaded, an email is sent to the recipient(s) explaining that a drop-off has been made. Note, the recipient has 7 days to retrieve the drop-off; after that, the link will expire.
11. Check your email. You will receive an automated message from NoReplyTo@mail.mil indicating that the recipient has picked up your file. If you do not receive an automated message indicting pick-up by the recipient within 2 business days, please contact Alice Mende at Alice.Mende@navy.mil and Jamie Ikehara at Jamie.Ikehara@navy.mil.
Note: CAC Authenticated Users are also able to view drop-offs and files that have been sent.
Click on your “Outbox”. Click on a drop-off to view the information and files for that particular drop-off.
NON-CAC USERS:
Requesting a Drop-off:
In order for a non-CAC user to create a drop-off, Firms/Offerors must receive a “drop-off request” from an inside user. Send an email to Alice Mende at Alice.Mende@navy.mil and Jamie Ikehara at Jamie.Ikehara@navy.mil to request a drop-off. Your email request must be received by Friday, 18 October 2019 10:00 a.m. HST. Once a drop-off request is generated for you, you will receive an email with a link to submit your drop-off. The drop-off request is valid for 14 days. If you do not receive an automated email message for your drop-off request within 2 business days, please contact Alice Mende at Alice.Mende@navy.mil and Jamie Ikehara at Jamie.Ikehara@navy.mil.
Submitting a Drop-off (Fill in all the required input fields):
1. Click on the link provided on the email and drop off your file.
2. Click on “Drop-Off”.
3. Enter the request code (provided in the email) and click on “Next”.
4. Verify that the “To” email address is correct. Email to: Alice.Mende@navy.mil and
Jamie.Ikehara@navy.mil. Click on the green “ + ” sign if you need to add another email address. Click on “Add One” and enter a name and email. Click on “Add & Close”.
5. Follow Steps 3 – 11 above for CAC Authenticated Users.
NOTE: Forwarding recipient and sender notification emails to anyone is strictly forbidden.
File details come from the government source that posted it. Updated .