IDIQ Painting Bid Schedule

View the file

Other files

File Type Posted
AMD_0001.pdf PDF
N6247314R4405FINAL_RFP.pdf PDF
Attachment_G_IDIQ_Paint_Bid_Schedule_-_Camp_Pen.xls XLS spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY

SUMMARY
PROVIDE IDIQ PRICES TO PERFORM EXTERIOR/INTERIOR PAINTING, LEAD PAINT REMOVAL, AND MOLD REMEDIATION IN ACCORDANCE WITH CONTRACT REQUIREMENTS AND SPECIFICATIONS.
BASE YEAR$ - 0
1ST OPTION YEAR$ - 0
2ND OPTION YEAR$ - 0
3RD OPTION YEAR$ - 0
4TH OPTION YEAR$ - 0
TOTAL ALL YEARS$ - 0

BASE - EXHIBIT F IDIQ

EXHIBIT LINE ITEM NUMBERS SOLICITATION/CONTRACT NUMBER N62473-15-R- XXXX SEAL BEACH
PROVIDE IDIQ PRICES TO PERFORM EXTERIOR/INTERIOR PAINTING, LEAD PAINT REMOVAL, AND MOLD REMEDIATION IN ACCORDANCE WITH CONTRACT REQUIREMENTS AND SPECIFICATIONS.
The Contractor shall populate the "Unit Price" column and the extended "Total Amount" column for each of the IDIQ ELIN below. All work shall be performed in strict accordance with sections of this contract.
CLIENTUNIT OFUNITTOTAL
ELINDESCRIPTIONQTYISSUEPRICEAMOUNT
F001EXTERIOR PAINTING
F001AAExterior surface preparation on wood, metal, masonry and concrete substrates and components, to include sanding and scraping of loose and flakey non-Lead Based Paint, and the minor repairs specified in Section 09 99 00 "Painting and Coatings."60,000SF$ - 0
F001ABRemove deteriorated or old caulk or sealant from cracks, joints and seams. Apply caulk or sealant on cracks, joints and seams. Apply weatherproofing around doors and windows in accordance with Section 07 92 00 00 "Joint Sealants" and Section 09 99 00 "Paint and Coatings." Includes all types of caulks and sealants.3,000LF$ - 0
F001ACInstall backer rod to 3/4" diameter.200LF$ - 0
F001ADRemove deteriorated or old exterior or interior window putty. Re-putty.2,000LF$ - 0
F001AEPressure wash exterior substrates, includes all substrates types and sports courts.50,000SF$ - 0
F001AFPatch stucco; over 10% of the substrate surface in accordance with Section 09 99 00 "Paint and Coatings."1,000SF$ - 0
F001AGMasking of doors, windows and other components; Exterior or interior.15,000SF$ - 0
F002EXTERIOR PAINTING
F002AAPrime all exterior substrates (to include exposed eaves) in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat.80,000SF$ - 0
F002ABPrime exterior trim, to include casings and fascia in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat. Measure the width of a trim's exposed surfaces and multiply the total width in inches by the length and divide by 12 to sum up the SF.2,000SF$ - 0
F002ACPaint wood substrates (to include exposed eaves, but not to include trim) in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.5,000SF$ - 0
F002ADPaint stucco, masonry and concrete substrates, not to include trim, in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.60,000SF$ - 0
F002AEPaint metal siding panels (to include sliding and roll-up doors, and eaves, but not to include trim) in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.40,000SF$ - 0
F002AFApply an elastomeric coating on stucco, masonry and concrete substrates, not to include trim, in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.20,000SF$ - 0
F002AGApply waterproof sealer on masonry and concrete substrates in accordance with Section 09 99 00 "Paint and Coatings.". Apply 2 coats.40,000SF$ - 0
F002AHPaint out-board side of fascia.; to 2" x 12." Apply 1 intermediate coat and 1 top coat.5,000LF$ - 0
F002AJPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 4-steps. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0
F002AKPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 5-steps to 8-steps. Applies to single and multi-story buildings. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0
F002ALPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 9-steps to 12-steps. Applies to single and multi-story buildings. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0
F002AMPrep and paint entrance/exit wood or metal exterior doors; both sides to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat. Door size to 3'-0" x 7'-0". Prime and apply 1 intermediate coat and 1 top coat.40EA$ - 0
F002ANPrep and paint entrance/exit wood or metal exterior doors; both sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat. Door sizes over 3'-0" x 7'-0" to 4'-0" x 7'-0" (Apply 1 intermediate coat and 1 top coat)8EA$ - 0
F002APPrep and paint exterior side of window, includes frame, header, sill, sashes, mullions and other associated trim. Prime and apply 1 intermediate coat and 1 top coat). Note: Painting may have to be performed with security bars in place.3,000SF$ - 0
F002AQPrep and paint gutter and downspout, includes all associated appurtenances. Prime and apply 1 intermediate coat and 1 top coat.7,200LF$ - 0
F002ARPrep and paint metal security bars or screens in place. Prime and apply 1 intermediate coat and 1 top coat.360SF$ - 0
F002ASPrep and paint roof mounted equipment. Prime and apply 1 intermediate coat and 1 topcoat.20EA$ - 0
F003MECHANICAL
A003AAPrep and paint metal pipe surfaces to 4-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.400LF$ - 0
A003ABPrep and paint metal pipe surfaces from 4-plus inches in diameter to 12-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.400LF$ - 0
A003ACPrep and paint metal pipe surfaces from 12-plus inches in diameter to 18-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 top coat.200LF$ - 0
F003ADUnit price for surface preparation and painting of linear measured metal pipe surfaces from 18-plus inches in diameter to 24-inches in diameter; Includes identification and directional markings. (Apply spot primer, 1 intermediate coat and 1 top coat).200LF$ - 0
F003AEPrep and paint metal pipe surfaces over 24-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.200SF$ - 0
F004ELASTOMERIC COATING
F004AAPrep metal roof surface, to include pressure washing, clean, application of sealant on fasteners, seal/tape all joints, repair/patch holes and damaged roof areas to 2-sqaure feet each (unlimited quantity), and apply acrylic elastomeric weatherproof coating in accordance with Section 07 67 00 "Metal Roof Restoration" and the manufacturer's install instructions. Repairs are defined as multiple areas over the entire surface. Tint the acrylic elastomeric weatherproof coating to match Architectural Plan. Submit a 5-Year Warranty workmanship warranty at the time of the final inspection.100SY$ - 0
F005SPORTS COURT RESURFACING ON CONCRETE OR ASPHALT
F005AAPrep and apply Sport Surface Coating on Basketball, Tennis, Volleyball, Racquetball, and other sports courts in accordance with the manufacturer's installation instructions; Includes pressure washing, sealing cracks, application of herbicide, surface preparation and minor repair of asphalt or concrete surfaces, application of base coat, application of multi-colors, and layout and placement of game lines. Submit a 5-Year workmanship warranty at the time of the final inspection.144SY$ - 0
F006FLAG POLES
F006AAPrep and paint flag pole surfaces to 40-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0
F006ABPrep and paint flag pole surfaces from 40+ feet to 60-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0
F006ACPrep and paint flag pole surfaces from 60+ feet to 80-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0
F007INTERIOR PAINTING COATINGS
F007AAPrime all interior substrates in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat.45,000SF$ - 0
F007ABPrep and paint drywall, plaster, wood, concrete, or masonry walls and ceilings. Includes painting of all electrical conduit, wire mold and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.45,000SF$ - 0
F007ACPrep and paint interior wood or metal doors. Door sizes up to 3'-0" x 7'-0"; both sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat.30EA$ - 0
F007ADPrep and paint interior wood or metal doors. Door sizes over 3'-0" x 7'-0" to 4'-0" x 7'-0"; two-sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat.15EA$ - 0
F007AEPrep and paint interior trim work to include baseboard or molding up to 8-inches in wide. Spot prime and apply 1 intermediate coat and 1 top coat.2,000LF$ - 0
F007AFPrep and paint interior side of window; Includes jamb, header, sill, sashes, mullions and trim. Spot prime and apply 1 intermediate coat and 1 topcoat.1,200SF$ - 0
F007AGRepair of plaster or gypsum substrate that exceeds the limit of "Existing Coated Surfaces with Minor Defects" found in Section 09 99 00, "Paint and Coating." Includes texturing to match the existing substrate texture and spot priming.300SF$ - 0
F007AHApply splatter or knock-down texture to walls or ceilings.600SF$ - 0
F007AJApply acoustical ceiling texture.150SF$ - 0
F008INTERIOR EPOXY COATINGS
F008AAPrep wall and floor surfaces, install cant strips at floor/wall intersection where applicable, and apply epoxy coating system in accordance with Section 09 99 00 "Paint and Coatings" and in accordance with the approved manufacturer's application instructions. Submit a 5-Year workmanship warranty at the time of the final acceptance inspection.1,200SF$ - 0
F009LBP ABATEMENT AND MOLD REMDIATION
The abatement ELINs shall include all associated direct and indirect costs, supervision, quality control, labor, and engineering controls to include third party industrial hygienist, air monitoring/sampling, LBP/Mold Remediation Plan, signage, containment, personnel protection equipment, collection and disposal to include all fees, and all supporting documentation. The Government will provide the contractor with analytical reports for LBP .
F009AAAbate loose and flaky LBP to the point where the LBP is determined to be locked on to the substrate.4,500SF$ - 0
F009ABChemical removal and disposal of LBP. Applies to chemical stripping method to include neutralizing.150SF$ - 0
F009ACMold Remediation150SF$ - 0
F010RENTAL EQUIPMENT
The boom lift shall be used for painting and repair of multi-story facilities that exceeds 15-feet measured from the finished elevation. Exception: This ELIN shall not be used in conjunction with ELIN A006 "Flag Poles.".
F010AABoom lift to reach up to 60-fee high, rental per week.4EA$ - 0
F010ABBoom lift to reach above 61-feet to 80-feet, rental per week.2EA$ - 0
F010ACBoom lift to reach above 81-feet to 100-feet, rental per week.2EA$ - 0
F011LABOR FOR NORMAL WORKING HOURS: NEGOTIATED
The unit price bid by the Contractor to perform one hour of work-in-place. The unit price includes all indirect and direct costs associated with performing work. The price includes the Contractor’s hourly composite trade wage, adjusted to allow for workforce productivity; costs for union agreements, crew sizes, hand tools, payroll burdens and fringes, overtime, job (field) overhead (including clerical support, supervision, inspection, fees, taxes, licenses, permits, and insurance), general and administrative (home office) overhead, and profit. Additionally, time for job preparation, safety standby personnel, and similar indirect labor elements are included.
F011AALaborer (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per laborer at the worksite in support of requirements as specified in the task order. This ELIN may be used provide labor to move excess quantities furniture as defined by the Government, furniture in excess of 150 pounds, large pieces of equipment and appliances as defined by the Government.6HR$ - 0
F011ABCarpenter (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per carpenter at the worksite in support of requirements as specified in the task order.6HR$ - 0
F011ACElectrician (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per electrician at the worksite in support of requirements as specified in the task order.6HR$ - 0
F011ADPlumber(DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per plumber at the worksite in support of requirements as specified in the task order.6HR$ - 0
F011AESheetmetal Mechanic (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per sheetmetal mechanic at the worksite in support of requirements as specified in the task order.6HR$ - 0
F011AFRoofer (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per roofer at the worksite in support of requirements as specified in the task order.6HR$ - 0
LABOR FOR OVERTIME WORKING HOURS: NEGOTIATED
F012The unit price bid by the Contractor to perform one hour of overtime work-in-place. The unit price includes all indirect and direct costs associated with performing work. The price includes the Contractor’s hourly composite trade wage, adjusted to allow for workforce productivity; costs for union agreements, crew sizes, hand tools, payroll burdens and fringes, overtime, job (field) overhead (including clerical support, supervision, inspection, fees, taxes, licenses, permits, and insurance), general and administrative (home office) overhead, and profit. Additionally, time for job preparation, safety standby personnel, and similar indirect labor elements are included.
F012AALaborer (DBA)8HR$ - 0
F012ABCarpenter (DBA)8HR$ - 0
F012ACElectrician (DBA)8HR$ - 0
F012ADPlumber(DBA)8HR$ - 0
F012AESheetmetal Mechanic (DBA)8HR$ - 0
F012AFRoofer (DBA)8HR$ - 0
F012AGPainter (DBA): Use this ELIN for all work to be performed outside of normal working hours. Note to Contractor: All prepriced ELINs have the labor factored into the "Unit Price". The proposed pricing for this ELIN must be fair and reasonable.8HR$ - 0
MATERIALS AND EQUIPMENT: NEGOTIATED
F013Materials and equipment in support of Composite Hour Labor Rate. Materials, equipment and rental prices shall be the lowest prices available considering the availability and time constraints of the job, and shall include any discounts and/or rebates accrued to or for the Contractor. The Contractor shall provide quotations from a minimum of two suppliers of the required material/equipment. Reasonable costs for shipping may be included. Materials handling costs shall be built in the Composite Hourly Labor Rate. The direct material/equipment costs will be multiplied by the Contractors Fixed Burden Rate (FBR) to determine the total burden material/equipment cost for the job. Example: $35,000.00 (Est. Qty) +( $35,000.00 (Est. Qty) x 2% (FBR%) = $42,000.00 (total material/equipment cost.)$ 11,000.00%0.00%$ - 0
The Contractor's FBR is the sum of the prime contractor's markup plus the mark of the subcontractor. Note: The Contractor must put a percentage value in Cell E101 before submitting their proposal.
TOTAL BASE YEAR ELINS A001 THROUGH A013TOTAL$ - 0
Inches to Decimal Conversion
EA = Each1" = 0.08 inches6" = 0.50 inches
HR = Hour2" = 0.17 inches7" = 0.58 inches
LF = Linear Feet3" = 0.25 inches8" = 0.67 inches
SF = Square Feet4" = 0.33 inches9" = 0.75 inches
FBR = Fixed-Burden rate5" = 0.42 inches10" = 0.83 inches
11" = 0.92 inches

scott.tant:

2013 RS Means

LI-099103.40.0700

$0.31 x 1.04% CCI

= $0.32 SF

scott.tant:

2013 RS Means

LI - 079213.20.0080

$2.41 x 1.04% CCI

= $2.51 LF

scott.tant:

2013 RS Means Facilities Maintenance and Repair LI - B2023113.1020; pg 51 $5.30 x 1.04% CCI

= $5.51 LF

scott.tant:

2013 RS Means

LI - 079123.10.0072

$1.32 x 1.04% CCI

= $1.37 LF

scott.tant:

2013 RS Means

LI - 099103.30.0810

$0.22 x 1.04 CCI

+ $0.25 SF

scott.tant:

2013 RS Means

LI 099113.62.0390

$0.42 x 1.04% CCI

= $0.44 SF

scott.tant:

2013 RS Means

LI - 099113.62.0310

$0.92 x 1.04% CCI

= $0.96 SF

scott.tant:

2013 RS Means

LI - 099113.62.0400

$0.31 x 2 x 1.04% CCI

= $0.65 SF

scott.tant:

2013 RS Means

LI - 099113.90.0580

LI - 099113.90.0590

($0.34 + $0.25) x 1.04% CCI

= $0.61 SF

scott.tant:

2013 RS Means

LI - 099113.90.0580

Labor = 0.16 SF Material: 1 Gal Behr from home Depot (08.13.2013) @ $27.98 gallon * 8% tax = $30.22 Gal.

$30.22/100 SF = $0.30 SF

[($0.16 + $0.30) * 22% O&P] * 1.04 CCI

= $0.58 SF

scott.tant:

2013 RS Means

LI - 099113.62.0400

($0.35 x 2) x 1.04% CCI

= $0.73 SF

scott.tant:

2013 RS Means

LI - 099113.90.0600

LI - 099113.90.0610

($0.25 + $0.49)* 1.04% CCI

= $0.77 SF

scott.tant:

2013 RS Means Facilities Maintenance and Repair

LI - C3013.212.0010; PG 139

$5.05 * 1.04 CCI

= $5.25 SF

scott.tant:

2013 RS Means

LI 099103.20.0530

$0.03 * 1.04 CCI

= $0.04 SF

scott.tant:

2013 RS Means

LI 099113.80.0180

($0.85 * 2) * 1.04 CCI

$1.70 LF

scott.tant:

N62473-12-D3006 ACCU Construction historical data, Exhibit B, ELIN B002AJ $ 70.00 Each scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B002AK $ 120.00 Each scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B002AL $ 200.00 Each scott.tant:

2013 RS Means

LI 099113.70.0190

$116.00 * 1.04%

= $120.64 EA

scott.tant:

2013 RS Means

LI 099113.70.0190

$116.00 * 1.04%

= $120.64 EA

scott.tant:

2013 RS Means

LI - 099113.70.0450

$85.50 (15 SF)/15 = $5.70 SF

$5.70 * 1/04 CCI = $5.93 SF

scott.tant:

2013 RS Means

LI - 099113.80.0360

$1.63 * 1.04 CCI

= $1.70 LF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B002AR

$1.70 SF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B002AS $35.00 Each scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B003AA

$ 1.30 LF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B003AB

$ 2.00 LF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B003AC

$ 2.25 LF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B003AD

$ 1.00 LF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B004AA

$ 4.00 SF

scott.tant:

2013 RS Means

321823.531100, Color Sealer 3 coats, 2 colors at $10.25 SY

321823.531200 Prep at $0.56 SY

321823.532000 Paint markings, 2 coats at $440.00 per court. (average court size: 40' * 80' = 356 SY

356/$440.00 = $0.81 SY

($10.25 + $0.56 + $0.81) * 1.04 = $12.08 SY

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B006AA $270.00 Each scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B006AB $400.00 Each scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B006AC $500.00 Each scott.tant:

2013 RS Means

LI- 099123.72.0480

$0.28 * 1.04 CCI

= $0.29 SF

scott.tant:

2013 RS Means

LI- 099123.72.0880

$0.43 * 1.04 CCI

= $0.45 SF

scott.tant:

2013 RS Means

LI- 099123.35.0140

$115.00 * 1.04 CCI

= $119.60 Each scott.tant:

2013 RS Means

LI- 099123.35.0140

$115.00 * 1.04 CCI

= $119.60 Each scott.tant:

2013 RS Means

LI - 099123.52.7600

$1.47 * 1.04 CCI

$1.53 LF

scott.tant:

2013 RS Means

LI - 099113.70.0450

$85.50 (15 SF)/15 = $5.70 SF

$5.70 * 1/04 CCI = $5.93 SF

scott.tant:

2013 RS Means Facilities Maintenance and Repair Cost data book

C30132140010: $2.40 SF * 1.04% CCI

= $2.50 SF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B007AH

$0.98 SF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN A007AJ

$1.00 SF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B009AA

$6.00 SF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B009AB

$15.00 SF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B009AC

$8.00 SF

scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B010AA $800.00 Each scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B010AB $2000.00 Each scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B010AC $2800.00 Each scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B003AD

$2.50 LF

scott.tant:

2013 RS Means Clab: 58.15 * 1.04% CCI = $60.48 Hr scott.tant:

2013 RS Means Carp: $73.65 * 1.04% CCI = $76.60 hr scott.tant:

2013 RS Means Elec: $81.00 * 1.04% CCI = $84.24 hr scott.tant:

2013 RS Means Plum: $86.80 * 1.04% CCI = $90.27 hr scott.tant:

2013 RS Means Shee: $83.95 * 1.04% CCI = $87.31 hr scott.tant:

2013 RS Means Rofc: $68.20 * 1.04% CCI = $70.93 scott.tant:

N62473-12-D-3006 ACCU Construction historical data, Exhibit B, ELIN B008

$3.00 SF

1ST OPT - EXHIBIT G IDIQ

EXHIBIT LINE ITEM NUMBERS SOLICITATION/CONTRACT NUMBER N62473-15-R- XXXX SEAL BEACH
PROVIDE IDIQ PRICES TO PERFORM EXTERIOR/INTERIOR PAINTING, LEAD PAINT REMOVAL, AND MOLD REMEDIATION IN ACCORDANCE WITH CONTRACT REQUIREMENTS AND SPECIFICATIONS.
The Contractor shall populate the "Unit Price" column and the extended "Total Amount" column for each of the IDIQ ELIN below. All work shall be performed in strict accordance with sections of this contract.
CLIENTUNIT OFUNITTOTAL
ELINDESCRIPTIONQTYISSUEPRICEAMOUNT
G001EXTERIOR PAINTING
G001AAExterior surface preparation on wood, metal, masonry and concrete substrates and components, to include sanding and scraping of loose and flakey non-Lead Based Paint, and the minor repairs specified in Section 09 99 00 "Painting and Coatings."60,000SF$ - 0
G001ABRemove deteriorated or old caulk or sealant from cracks, joints and seams. Apply caulk or sealant on cracks, joints and seams. Apply weatherproofing around doors and windows in accordance with Section 07 92 00 00 "Joint Sealants" and Section 09 99 00 "Paint and Coatings." Includes all types of caulks and sealants.3,000LF$ - 0
G001ACInstall backer rod to 3/4" diameter.200LF$ - 0
G001ADRemove deteriorated or old exterior or interior window putty. Re-putty.2,000LF$ - 0
G001AEPressure wash exterior substrates, includes all substrates types and sports courts.50,000SF$ - 0
G001AFPatch stucco; over 10% of the substrate surface in accordance with Section 09 99 00 "Paint and Coatings."1,000SF$ - 0
G001AGMasking of doors, windows and other components; Exterior or interior.15,000SF$ - 0
G002EXTERIOR PAINTING
G002AAPrime all exterior substrates (to include exposed eaves) in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat.80,000SF$ - 0
G002ABPrime exterior trim, to include casings and fascia in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat. Measure the width of a trim's exposed surfaces and multiply the total width in inches by the length and divide by 12 to sum up the SF.2,000SF$ - 0
G002ACPaint wood substrates (to include exposed eaves, but not to include trim) in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.5,000SF$ - 0
G002ADPaint stucco, masonry and concrete substrates, not to include trim, in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.60,000SF$ - 0
G002AEPaint metal siding panels (to include sliding and roll-up doors, and eaves, but not to include trim) in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.40,000SF$ - 0
G002AFApply an elastomeric coating on stucco, masonry and concrete substrates, not to include trim, in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.20,000SF$ - 0
G002AGApply waterproof sealer on masonry and concrete substrates in accordance with Section 09 99 00 "Paint and Coatings.". Apply 2 coats.40,000SF$ - 0
G002AHPaint out-board side of fascia.; to 2" x 12." Apply 1 intermediate coat and 1 top coat.5,000LF$ - 0
G002AJPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 4-steps. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0
G002AKPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 5-steps to 8-steps. Applies to single and multi-story buildings. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0
G002ALPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 9-steps to 12-steps. Applies to single and multi-story buildings. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0
G002AMPrep and paint entrance/exit wood or metal exterior doors; both sides to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat. Door size to 3'-0" x 7'-0". Prime and apply 1 intermediate coat and 1 top coat.40EA$ - 0
G002ANPrep and paint entrance/exit wood or metal exterior doors; both sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat. Door sizes over 3'-0" x 7'-0" to 4'-0" x 7'-0" (Apply 1 intermediate coat and 1 top coat)8EA$ - 0
G002APPrep and paint exterior side of window, includes frame, header, sill, sashes, mullions and other associated trim. Prime and apply 1 intermediate coat and 1 top coat). Note: Painting may have to be performed with security bars in place.3,000SF$ - 0
G002AQPrep and paint gutter and downspout, includes all associated appurtenances. Prime and apply 1 intermediate coat and 1 top coat.7,200LF$ - 0
G002ARPrep and paint metal security bars or screens in place. Prime and apply 1 intermediate coat and 1 top coat.360SF$ - 0
G002ASPrep and paint roof mounted equipment. Prime and apply 1 intermediate coat and 1 topcoat.20EA$ - 0
G003MECHANICAL
G003AAPrep and paint metal pipe surfaces to 4-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.400LF$ - 0
G003ABPrep and paint metal pipe surfaces from 4-plus inches in diameter to 12-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.400LF$ - 0
G003ACPrep and paint metal pipe surfaces from 12-plus inches in diameter to 18-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 top coat.200LF$ - 0
G003ADUnit price for surface preparation and painting of linear measured metal pipe surfaces from 18-plus inches in diameter to 24-inches in diameter; Includes identification and directional markings. (Apply spot primer, 1 intermediate coat and 1 top coat).200LF$ - 0
G003AEPrep and paint metal pipe surfaces over 24-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.200SF$ - 0
G004ELASTOMERIC COATING
G004AAPrep metal roof surface, to include pressure washing, clean, application of sealant on fasteners, seal/tape all joints, repair/patch holes and damaged roof areas to 2-sqaure feet each (unlimited quantity), and apply acrylic elastomeric weatherproof coating in accordance with Section 07 67 00 "Metal Roof Restoration" and the manufacturer's install instructions. Repairs are defined as multiple areas over the entire surface. Tint the acrylic elastomeric weatherproof coating to match Base Architectural Plan. Submit a 5-Year Warranty workmanship warranty at the time of the final inspection.100SY$ - 0
G005SPORTS COURT RESURFACING ON CONCRETE OR ASPHALT
G005AAPrep and apply Sport Surface Coating on Basketball, Tennis, Volleyball, Racquetball, and other sports courts in accordance with the manufacturer's installation instructions; Includes pressure washing, sealing cracks, application of herbicide, surface preparation and minor repair of asphalt or concrete surfaces, application of base coat, application of multi-colors, and layout and placement of game lines. Submit a 5-Year workmanship warranty at the time of the final inspection.144SY$ - 0
G006FLAG POLES
G006AAPrep and paint flag pole surfaces to 40-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0
G006ABPrep and paint flag pole surfaces from 40+ feet to 60-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0
G006ACPrep and paint flag pole surfaces from 60+ feet to 80-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0
G007INTERIOR PAINTING COATINGS
G007AAPrime all interior substrates in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat.45,000SF$ - 0
G007ABPrep and paint drywall, plaster, wood, concrete, or masonry walls and ceilings. Includes painting of all electrical conduit, wire mold and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.45,000SF$ - 0
G007ACPrep and paint interior wood or metal doors. Door sizes up to 3'-0" x 7'-0"; both sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat.30EA$ - 0
G007ADPrep and paint interior wood or metal doors. Door sizes over 3'-0" x 7'-0" to 4'-0" x 7'-0"; two-sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat.15EA$ - 0
G007AEPrep and paint interior trim work to include baseboard or molding up to 8-inches in wide. Spot prime and apply 1 intermediate coat and 1 top coat.2,000LF$ - 0
G007AFPrep and paint interior side of window; Includes jamb, header, sill, sashes, mullions and trim. Spot prime and apply 1 intermediate coat and 1 topcoat.1,200SF$ - 0
G007AGRepair of plaster or gypsum substrate that exceeds the limit of "Existing Coated Surfaces with Minor Defects" found in Section 09 99 00, "Paint and Coating." Includes texturing to match the existing substrate texture and spot priming.300SF$ - 0
G007AHApply splatter or knock-down texture to walls or ceilings.600SF$ - 0
G007AJApply acoustical ceiling texture.150SF$ - 0
G008INTERIOR EPOXY COATINGS
G008AAPrep wall and floor surfaces, install cant strips at floor/wall intersection where applicable, and apply epoxy coating system in accordance with Section 09 99 00 "Paint and Coatings" and in accordance with the approved manufacturer's application instructions. Submit a 5-Year workmanship warranty at the time of the final acceptance inspection.1,200SF$ - 0
G009LBP ABATEMENT AND MOLD REMDIATION
The abatement ELINs shall include all associated direct and indirect costs, supervision, quality control, labor, and engineering controls to include third party industrial hygienist, air monitoring/sampling, LBP/Mold Remediation Plan, signage, containment, personnel protection equipment, collection and disposal to include all fees, and all supporting documentation. The Government will provide the contractor with analytical reports for LBP .
G009AAAbate loose and flaky LBP to the point where the LBP is determined to be locked on to the substrate.4,500SF$ - 0
G009ABChemical removal and disposal of LBP. Applies to chemical stripping method to include neutralizing.150SF$ - 0
G009ACMold Remediation150SF$ - 0
G010RENTAL EQUIPMENT
The boom lift shall be used for painting and repair of multi-story facilities that exceeds 15-feet measured from the finished elevation. Exception: This ELIN shall not be used in conjunction with ELIN B006 "Flag Poles.".
G010AABoom lift to reach up to 60-fee high, rental per week.4EA$ - 0
G010ABBoom lift to reach above 61-feet to 80-feet, rental per week.2EA$ - 0
G010ACBoom lift to reach above 81-feet to 100-feet, rental per week.2EA$ - 0
G011LABOR FOR NORMAL WORKING HOURS: NEGOTIATED
The unit price bid by the Contractor to perform one hour of work-in-place. The unit price includes all indirect and direct costs associated with performing work. The price includes the Contractor’s hourly composite trade wage, adjusted to allow for workforce productivity; costs for union agreements, crew sizes, hand tools, payroll burdens and fringes, overtime, job (field) overhead (including clerical support, supervision, inspection, fees, taxes, licenses, permits, and insurance), general and administrative (home office) overhead, and profit. Additionally, time for job preparation, safety standby personnel, and similar indirect labor elements are included.
G011AALaborer (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per laborer at the worksite in support of requirements as specified in the task order. This ELIN may be used provide labor to move excess quantities furniture as defined by the Government, furniture in excess of 150 pounds, large pieces of equipment and appliances as defined by the Government.6HR$ - 0
G011ABCarpenter (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per carpenter at the worksite in support of requirements as specified in the task order.6HR$ - 0
G011ACElectrician (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per electrician at the worksite in support of requirements as specified in the task order.6HR$ - 0
G011ADPlumber(DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per plumber at the worksite in support of requirements as specified in the task order.6HR$ - 0
G011AESheetmetal Mechanic (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per sheetmetal mechanic at the worksite in support of requirements as specified in the task order.6HR$ - 0
G011AFRoofer (DBA): The unit price bid by the Contractor to provide one performance standard hour of work-in-place per roofer at the worksite in support of requirements as specified in the task order.6HR$ - 0
LABOR FOR OVERTIME WORKING HOURS: NEGOTIATED
G012The unit price bid by the Contractor to perform one hour of overtime work-in-place. The unit price includes all indirect and direct costs associated with performing work. The price includes the Contractor’s hourly composite trade wage, adjusted to allow for workforce productivity; costs for union agreements, crew sizes, hand tools, payroll burdens and fringes, overtime, job (field) overhead (including clerical support, supervision, inspection, fees, taxes, licenses, permits, and insurance), general and administrative (home office) overhead, and profit. Additionally, time for job preparation, safety standby personnel, and similar indirect labor elements are included.
G012AALaborer (DBA)8HR$ - 0
G012ABCarpenter (DBA)8HR$ - 0
G012ACElectrician (DBA)8HR$ - 0
G012ADPlumber(DBA)8HR$ - 0
G012AESheetmetal Mechanic (DBA)8HR$ - 0
G012AFRoofer (DBA)8HR$ - 0
G012AGPainter (DBA): Use this ELIN for all work to be performed outside of normal working hours. Note to Contractor: All prepriced ELINs have the labor factored into the "Unit Price". The proposed pricing for this ELIN must be fair and reasonable.8HR$ - 0
MATERIALS AND EQUIPMENT: NEGOTIATED
G013Materials and equipment in support of Composite Hour Labor Rate. Materials, equipment and rental prices shall be the lowest prices available considering the availability and time constraints of the job, and shall include any discounts and/or rebates accrued to or for the Contractor. The Contractor shall provide quotations from a minimum of two suppliers of the required material/equipment. Reasonable costs for shipping may be included. Materials handling costs shall be built in the Composite Hourly Labor Rate. The direct material/equipment costs will be multiplied by the Contractors Fixed Burden Rate (FBR) to determine the total burden material/equipment cost for the job. Example: $35,000.00 (Est. Qty) +( $35,000.00 (Est. Qty) x 2% (FBR%) = $42,000.00 (total material/equipment cost.)$ 11,000.00%0.00%$ - 0
The Contractor's FBR is the sum of the prime contractor's markup plus the mark of the subcontractor. Note: The Contractor must put a percentage value in Cell E101 before submitting their proposal.
TOTAL 1ST OPTION YEAR ELINS B001 THROUGH B013TOTAL$ - 0
Inches to Decimal Conversion
EA = Each1" = 0.08 inches6" = 0.50 inches
HR = Hour2" = 0.17 inches7" = 0.58 inches
LF = Linear Feet3" = 0.25 inches8" = 0.67 inches
SF = Square Feet4" = 0.33 inches9" = 0.75 inches
FBR = Fixed-Burden rate5" = 0.42 inches10" = 0.83 inches
11" = 0.92 inches

2ND OPT - EXHIBIT H IDIQ

EXHIBIT LINE ITEM NUMBERS SOLICITATION/CONTRACT NUMBER N62473-15-R- XXXX SEAL BEACH
PROVIDE IDIQ PRICES TO PERFORM EXTERIOR/INTERIOR PAINTING, LEAD PAINT REMOVAL, AND MOLD REMEDIATION IN ACCORDANCE WITH CONTRACT REQUIREMENTS AND SPECIFICATIONS.
The Contractor shall populate the "Unit Price" column and the extended "Total Amount" column for each of the IDIQ ELIN below. All work shall be performed in strict accordance with sections of this contract.
CLIENTUNIT OFUNITTOTAL
ELINDESCRIPTIONQTYISSUEPRICEAMOUNT
H001EXTERIOR PAINTING
H001AAExterior surface preparation on wood, metal, masonry and concrete substrates and components, to include sanding and scraping of loose and flakey non-Lead Based Paint, and the minor repairs specified in Section 09 99 00 "Painting and Coatings."60,000SF$ - 0$ - 0
H001ABRemove deteriorated or old caulk or sealant from cracks, joints and seams. Apply caulk or sealant on cracks, joints and seams. Apply weatherproofing around doors and windows in accordance with Section 07 92 00 00 "Joint Sealants" and Section 09 99 00 "Paint and Coatings." Includes all types of caulks and sealants.3,000LF$ - 0$ - 0
H001ACInstall backer rod to 3/4" diameter.200LF$ - 0$ - 0
H001ADRemove deteriorated or old exterior or interior window putty. Re-putty.2,000LF$ - 0$ - 0
H001AEPressure wash exterior substrates, includes all substrates types and sports courts.50,000SF$ - 0$ - 0
H001AFPatch stucco; over 10% of the substrate surface in accordance with Section 09 99 00 "Paint and Coatings."1,000SF$ - 0$ - 0
H001AGMasking of doors, windows and other components; Exterior or interior.15,000SF$ - 0$ - 0
H002EXTERIOR PAINTING
H002AAPrime all exterior substrates (to include exposed eaves) in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat.80,000SF$ - 0$ - 0
H002ABPrime exterior trim, to include casings and fascia in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat. Measure the width of a trim's exposed surfaces and multiply the total width in inches by the length and divide by 12 to sum up the SF.2,000SF$ - 0$ - 0
H002ACPaint wood substrates (to include exposed eaves, but not to include trim) in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.5,000SF$ - 0$ - 0
H002ADPaint stucco, masonry and concrete substrates, not to include trim, in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.60,000SF$ - 0$ - 0
H002AEPaint metal siding panels (to include sliding and roll-up doors, and eaves, but not to include trim) in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.40,000SF$ - 0$ - 0
H002AFApply an elastomeric coating on stucco, masonry and concrete substrates, not to include trim, in accordance with Section 09 99 00 "Paint and Coatings.". Includes painting of all electrical conduit and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.20,000SF$ - 0$ - 0
H002AGApply waterproof sealer on masonry and concrete substrates in accordance with Section 09 99 00 "Paint and Coatings.". Apply 2 coats.40,000SF$ - 0$ - 0
H002AHPaint out-board side of fascia.; to 2" x 12." Apply 1 intermediate coat and 1 top coat.5,000LF$ - 0$ - 0
H002AJPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 4-steps. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0$ - 0
H002AKPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 5-steps to 8-steps. Applies to single and multi-story buildings. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0$ - 0
H002ALPrep and paint metal, wood or concrete stairs; Includes risers, treads, stringers, one landing, supports, and railing for stairs up to 8' wide by 9-steps to 12-steps. Applies to single and multi-story buildings. Spot prime and apply 1 intermediate coat and 1 top coat.5EA$ - 0$ - 0
H002AMPrep and paint entrance/exit wood or metal exterior doors; both sides to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat. Door size to 3'-0" x 7'-0". Prime and apply 1 intermediate coat and 1 top coat.40EA$ - 0$ - 0
H002ANPrep and paint entrance/exit wood or metal exterior doors; both sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat. Door sizes over 3'-0" x 7'-0" to 4'-0" x 7'-0" (Apply 1 intermediate coat and 1 top coat)8EA$ - 0$ - 0
H002APPrep and paint exterior side of window, includes frame, header, sill, sashes, mullions and other associated trim. Prime and apply 1 intermediate coat and 1 top coat). Note: Painting may have to be performed with security bars in place.3,000SF$ - 0$ - 0
H002AQPrep and paint gutter and downspout, includes all associated appurtenances. Prime and apply 1 intermediate coat and 1 top coat.7,200LF$ - 0$ - 0
H002ARPrep and paint metal security bars or screens in place. Prime and apply 1 intermediate coat and 1 top coat.360SF$ - 0$ - 0
H002ASPrep and paint roof mounted equipment. Prime and apply 1 intermediate coat and 1 topcoat.20EA$ - 0$ - 0
H003MECHANICAL
H003AAPrep and paint metal pipe surfaces to 4-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.400LF$ - 0$ - 0
H003ABPrep and paint metal pipe surfaces from 4-plus inches in diameter to 12-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.400LF$ - 0$ - 0
H003ACPrep and paint metal pipe surfaces from 12-plus inches in diameter to 18-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 top coat.200LF$ - 0$ - 0
H003ADUnit price for surface preparation and painting of linear measured metal pipe surfaces from 18-plus inches in diameter to 24-inches in diameter; Includes identification and directional markings. (Apply spot primer, 1 intermediate coat and 1 top coat).200LF$ - 0$ - 0
H003AEPrep and paint metal pipe surfaces over 24-inches in diameter; Includes identification and directional labels/markings. Spot prime and apply 1 intermediate coat and 1 topcoat.200SF$ - 0$ - 0
H004ELASTOMERIC COATING
H004AAPrep metal roof surface, to include pressure washing, clean, application of sealant on fasteners, seal/tape all joints, repair/patch holes and damaged roof areas to 2-sqaure feet each (unlimited quantity), and apply acrylic elastomeric weatherproof coating in accordance with Section 07 67 00 "Metal Roof Restoration" and the manufacturer's install instructions. Repairs are defined as multiple areas over the entire surface. Tint the acrylic elastomeric weatherproof coating to match MCB Camp Pendleton’s Base Architectural Plan. Submit a 5-Year Warranty workmanship warranty at the time of the final inspection.100SY$ - 0$ - 0
H005SPORTS COURT RESURFACING ON CONCRETE OR ASPHALT
H005AAPrep and apply Sport Surface Coating on Basketball, Tennis, Volleyball, Racquetball, and other sports courts in accordance with the manufacturer's installation instructions; Includes pressure washing, sealing cracks, application of herbicide, surface preparation and minor repair of asphalt or concrete surfaces, application of base coat, application of multi-colors, and layout and placement of game lines. Submit a 5-Year workmanship warranty at the time of the final inspection.144SY$ - 0$ - 0
H006FLAG POLES
H006AAPrep and paint flag pole surfaces to 40-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0$ - 0
H006ABPrep and paint flag pole surfaces from 40+ feet to 60-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0$ - 0
H006ACPrep and paint flag pole surfaces from 60+ feet to 80-feet high. Includes personnel lift, personal protective equipment, and precautions to protect applicable lawn surfaces. Spot prime and apply 1-intermediate coat and 1-top coat.2EA$ - 0$ - 0
H007INTERIOR PAINTING COATINGS
H007AAPrime all interior substrates in accordance with Section 09 99 00 "Paint and Coatings." Apply one coat.45,000SF$ - 0$ - 0
H007ABPrep and paint drywall, plaster, wood, concrete, or masonry walls and ceilings. Includes painting of all electrical conduit, wire mold and other surface mounted appendages. Apply 1 intermediate coat and 1 top coat.45,000SF$ - 0$ - 0
H007ACPrep and paint interior wood or metal doors. Door sizes up to 3'-0" x 7'-0"; both sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat.30EA$ - 0$ - 0
H007ADPrep and paint interior wood or metal doors. Door sizes over 3'-0" x 7'-0" to 4'-0" x 7'-0"; two-sides, to include painting of louvers, vision lite frame, door frame and trim. Prime and apply 1 intermediate coat and 1 top coat.15EA$ - 0$ - 0
H007AEPrep and paint interior trim work to include baseboard or molding up to 8-inches in wide. Spot prime and apply 1 intermediate coat and 1 top coat.2,000LF$ - 0$ - 0
H007AFPrep and paint interior side of window; Includes jamb, header, sill, sashes, mullions and trim. Spot prime and apply 1 intermediate coat and 1 topcoat.1,200SF$ - 0$ - 0
H007AGRepair of plaster or gypsum substrate that exceeds the limit of "Existing Coated Surfaces with Minor Defects" found in Section 09 99 00, "Paint and Coating." Includes texturing to match the existing substrate texture and spot priming.300SF$ - 0$ - 0
H007AHApply splatter or knock-down texture to walls or ceilings.600SF$ - 0$ - 0
H007AJApply acoustical ceiling texture.150SF$ - 0$ - 0
H008INTERIOR EPOXY COATINGS
H008AAPrep wall and floor surfaces, install cant strips at floor/wall intersection where applicable, and apply epoxy coating system in accordance with Section 09 99 00 "Paint and Coatings" and in accordance with the approved manufacturer's application instructions. Submit a 5-Year workmanship warranty at the time of the final acceptance inspection.1,200SF$ - 0$ - 0
H009LBP ABATEMENT AND MOLD REMDIATION