UFGS_01_57_23.pdf
PDF 240 KB Posted
- Solicitation number
- N6247314R0015
About this file
UFGS 01 57 23
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 14r0015_amend_0005.PDF | ||
| FINAL_PTO_0001_042114.xlsx | XLSX spreadsheet | |
| 14r0015_amend_0004.PDF | ||
| PTO_0001_rev_041814.xlsx | XLSX spreadsheet | |
| 14r0015_amend_0003.PDF | ||
| 14r0015_amend_0002.PDF | ||
| 14r0015_amend_0001.PDF | ||
| PTO_0001.xlsx | XLSX spreadsheet | |
| UFGS_01_30_00.pdf | ||
| UFGS_01_33_00.pdf | ||
| UFGS_01_14_00.pdf | ||
| UFGS_01_42_00.pdf | ||
| EXHIBIT_H_COMB_DAILY_QC1.PDF | ||
| UFGS_01_57_19.pdf | ||
| UFGS_01_45_00.pdf | ||
| Exhibit_E_Surety_Form.pdf | ||
| EXHIBIT_I_DBA_WD_FOR_METRO_SD_JOC.pdf | ||
| Exhibit_F_RFI_Form.pdf | ||
| Exhibit_D_-_Financial_Questionnaire.pdf | ||
| Exhibit_B_-_PPQ.pdf | ||
| UFGS_01_78_00.pdf | ||
| UFGS_01_75_00.pdf | ||
| Exhibit_A_-_Experience_-_Offeror.pdf | ||
| Exhibit_C_-_Safety_Data_ _Narrative.pdf | ||
| UFGS_01_62_35.pdf | ||
| UFGS_01_78_23.pdf | ||
| EXHIBIT_J_-_PTO_0001.pdf | ||
| UFGS_01_20_00.pdf | ||
| UFGS_01_35_26.pdf | ||
| EXHIBIT_G_-_FAR_52_209-7_AND_DFARS_252_209-7999.pdf | ||
| UFGS_01_50_00.pdf | ||
| N62473-14-R-0015.pdf |
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UFGS 01 57 23
SECTION 01 57 23
TEMPORARY STORM WATER POLLUTION CONTROL
04/08
1 PART 1 GENERAL
1.1 SUMMARY
The work consists of implementing the storm water pollution prevention measures to prevent sediment from entering streams or water bodies as specified in this Section in conformance with the requirements of Section 01
57 20.00 10 ENVIRONMENTAL PROTECTION, and the requirements of the National
Pollutant Discharge Elimination System (NPDES).
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM D4439 (2011) Geosynthetics
ASTM D4491 (1999a; R 2009) Water Permeability of
Geotextiles by Permittivity
ASTM D4533 (2011) Trapezoid Tearing Strength of
Geotextiles
ASTM D4632/D4632M (2008; E 2013; R 2013) Grab Breaking Load and
Elongation of Geotextiles
ASTM D4751 (2012) Determining Apparent Opening Size of a
Geotextile
ASTM D4873 (2002; R 2009) Identification, Storage, and
Handling of Geosynthetic Rolls and Samples
U.S. ENVIRONMENTAL PROTECTION AGENCY (EPA)
EPA 832-R-92-005 (1992) Storm Water Management for
Construction Activities Developing Pollution
Preventions and Plans and Best Management
Practices
U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)
file:///D:/Documents%20and%20Settings/bradley.CRAWFORD/My%20Documents/01%2057%2020.00%2010.doc file:///D:/Documents%20and%20Settings/bradley.CRAWFORD/My%20Documents/01%2057%2020.00%2010.doc
40 CFR 122.26 Storm Water Discharges (Applicable to State
NPDES Programs, see section 123.25)
1.3 EROSION AND SEDIMENT CONTROLS
The controls and measures required of the Contractor are described below.
1.3.1 Stabilization Practices
The stabilization practices to be implemented include temporary seeding, mulching, geotextiles, sod stabilization, vegetative buffer strips, erosion control matts, protection of trees, preservation of mature vegetation, etc.
On the daily CQC Report, record the dates when the major grading activities occur, (e.g., clearing and grubbing, excavation, embankment, and grading);
when construction activities temporarily or permanently cease on a portion of the site; and when stabilization practices are initiated. Except as provided in paragraphs UNSUITABLE CONDITIONS and NO ACTIVITY FOR LESS THAN
21 DAYS, initiate stabilization practices as soon as practicable, but no more than 14 days, in any portion of the site where construction activities have temporarily or permanently ceased.
1.3.1.1 Unsuitable Conditions
Where the initiation of stabilization measures by the fourteenth day after construction activity temporarily or permanently ceases or is precluded by unsuitable conditions caused by the weather, initiate stabilization practices as soon as practicable after conditions become suitable.
1.3.1.2 No Activity for Less Than 21 Days
When the total time period in which construction activity is temporarily ceased on a portion of the site is 21 days minimum, stabilization practices do not have to be initiated on that portion of the site until 14 days have elapsed after construction activity temporarily ceased.
1.3.1.3 Burnoff
Burnoff of the ground cover is not permitted.
1.3.1.4 Protection of Erodible Soils
Immediately finish the earthwork brought to a final grade, as indicated or specified, and protect the side slopes and back slopes upon completion of rough grading. Plan and conduct earthwork to minimize the duration of exposure of unprotected soils.
1.3.2 Erosion, Sediment and Stormwater Control
Submit "Erosion and Sediment Controls" (E&S) (form provided at the pre-construction conference) and Storm Water Inspection Reports for General
Permit to the Contracting Officer once every seven (7) calendar days and within 24 hours of a storm event that produces 0.5 inch or more of rain.
1.3.3 Stormwater Drainage
There will be no discharge of excavation ground water to the sanitary sewer, storm drains, or to the river without prior specific authorization of the
Environmental Programs Division in writing. Discharge of hazardous substances will not be permitted under any circumstances. Construction site runoff will be prevented from entering any storm drain or the river directly by the use of straw bales or other method suitable to the Environmental
Programs Division of the Shipyard. Provide erosion protection of the surrounding soils.
1.3.4 Structural Practices
Implement structural practices to divert flows from exposed soils, temporarily store flows, or otherwise limit runoff and the discharge of pollutants from exposed areas of the site. Implement structural practices in a timely manner, during the construction process, to minimize erosion and sediment runoff.
1.3.5 Vegetation and Mulch
a. Provide temporary protection on sides and back slopes as soon as rough grading is completed or sufficient soil is exposed to require erosion protection. Protect slopes by accelerated growth of permanent vegetation, temporary vegetation, mulching, or netting. Stabilize slopes by hydroseeding, anchoring mulch in place, covering with anchored netting, sodding, or such combination of these and other methods necessary for effective erosion control.
b. Seeding: Provide new seeding where ground is disturbed. Include topsoil or nutriment during the seeding operation necessary to reestablish a suitable stand of grass.
1.4 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Storm Water Pollution Prevention Plan
Storm Water Notice of Intent
SD-06 Test Reports file:///D:/Documents%20and%20Settings/bradley.CRAWFORD/My%20Documents/01%2033%2000.doc
Storm Water Inspection Reports for General Permit
Erosion and Sediment Controls
SD-07 Certificates
Mill Certificate or Affidavit
1.5 DELIVERY, STORAGE, AND HANDLING
Identify, store and handle filter fabric in accordance with ASTM D4873.
2 PART 2 PRODUCTS
2.1 COMPONENTS FOR SILT FENCES
2.1.1 Filter Fabric
Provide geotextile that complies with the requirements of ASTM D4439, and consists of polymeric filaments which are formed into a stable network such that filaments retain their relative positions. The filament shall consist of a long-chain synthetic polymer composed of at least 85 percent by weight of ester, propylene, or amide, and contains stabilizers and/or inhibitors added to the base plastic to make the filaments resistant to deterioration due to ultraviolet and heat exposure. Provide synthetic filter fabric that contains ultraviolet ray inhibitors and stabilizers to assure a minimum of six months of expected usable construction life at a temperature range of 0 to 120 degrees F. The filter fabric shall meet the following requirements:
FILTER FABRIC FOR SILT SCREEN FENCE
PHYSICAL PROPERTY TEST PROCEDURE STRENGTH REQUIREMENT
Grab Tensile Elongation (percent) ASTM D4632/D4632M 445 N100 lbs. min. 30 percent max.
Trapezoid Tear ASTM D4533 245 N min.55 lbs. min.
Permittivity ASTM D4491 0.2 sec-1
AOS (U.S. Std Sieve) ASTM D4751 20-100
2.1.2 Silt Fence Stakes and Posts
Use either wooden stakes or steel posts for fence construction. Wooden stakes utilized for silt fence construction, shall have a minimum cross section of 2 by 2 inches when oak is used and 4 by 4 inches when pine is used, and have a minimum length of 5 feet. Steel posts (standard "U" or "T" section) utilized for silt fence construction, shall have a minimum weight of 1.33 pounds/linear foot and a minimum length of 5 feet.
2.1.3 Mill Certificate or Affidavit
Provide a mill certificate or affidavit attesting that the fabric and factory seams meet chemical, physical, and manufacturing requirements specified above. Specify in the mill certificate or affidavit the actual
Minimum Average Roll Values and identify the fabric supplied by roll identification numbers. Submit a mill certificate or affidavit signed by a legally authorized official from the company manufacturing the filter fabric.
2.2 COMPONENTS FOR STRAW BALES
The straw in the bales shall be stalks from oats, wheat, rye, barley, rice, or from grasses such as byhalia, bermuda, etc., furnished in air dry condition. Provide bales with a standard cross section of 14 by 18 inches.
Wire-bound or string-tie all bales. Use either wooden stakes or steel posts to secure the straw bales to the ground. Wooden stakes utilized for this purpose, shall have a minimum dimensions of 2 by 2 inches in cross section and have a minimum length of 3 feet. Steel posts (standard "U" or "T" section) utilized for securing straw bales, shall have a minimum weight of
1.33 pounds/linear foot and a minimum length of 3 feet.
3 PART 3 EXECUTION
3.1 INSTALLATION OF SILT FENCES
Extend silt fences a minimum of 16 inches above the ground surface without exceeding 34 inches above the ground surface. Provide filter fabric from a continuous roll cut to the length of the barrier to avoid the use of joints.
When joints are unavoidable, splice together filter fabric at a support post, with a minimum 6 inch overlap, and securely sealed. Excavate trench approximately 4 inches wide and 4 inches deep on the upslope side of the location of the silt fence. The 4 by 4 inch trench shall be backfilled and the soil compacted over the filter fabric. Remove silt fences upon approval by the Contracting Officer.
3.2 INSTALLATION OF STRAW BALES
Place the straw bales in a single row, lengthwise on the contour, with ends of adjacent bales tightly abutting one another. Install straw bales so that bindings are oriented around the sides rather than along the tops and bottoms of the bales in order to prevent deterioration of the bindings.
Entrench and backfill the barrier. Excavate a trench the width of a bale and the length of the proposed barrier to a minimum depth of 4 inches.
After the bales are staked and chinked (gaps filled by wedging with straw), backfill the excavated soil against the barrier. Conform the backfill soil with the ground level on the downhill side and build up to 4 inches against the uphill side of the barrier. Scatter loose straw over the area immediately uphill from a straw bale barrier to increase barrier efficiency.
Securely anchor each bale by at least two stakes driven through the bale.
Drive the first stake or steel post in each bale toward the previously laid bale to force the bales together. Drive stakes or steel pickets a minimum
18 inches deep into the ground to securely anchor the bales.
3.3 FIELD QUALITY CONTROL
Maintain the temporary and permanent vegetation, erosion and sediment control measures, and other protective measures in good and effective operating condition by performing routine inspections to determine condition and effectiveness, by restoration of destroyed vegetative cover, and by repair of erosion and sediment control measures and other protective measures. Use the following procedures to maintain the protective measures.
3.3.1 Silt Fence Maintenance
Inspect the silt fences in accordance with paragraph, titled "Inspections," of this section. Any required repairs shall be made promptly. Pay close attention to the repair of damaged silt fence resulting from end runs and undercutting. Should the fabric on a silt fence decompose or become ineffective, and the barrier is still necessary, replace the fabric promptly. Remove sediment deposits when deposits reach one-third of the height of the barrier. Remove a silt fence when it is no longer required.
The immediate area occupied by the fence and any sediment deposits shall be shaped to an acceptable grade. The areas disturbed by this shaping shall receive erosion control.
3.3.2 Straw Bale Maintenance
Inspect straw bale barriers in accordance with paragraph, titled
"Inspections". Pay close attention to the repair of damaged bales, end runs and undercutting beneath bales. Accomplish necessary repairs to barriers or replacement of bales in a promptly manner. Remove sediment deposits when deposits reach one-half of the height of the barrier. At the each end of each row turn bales uphill when used to retain sediment. Remove a straw bale barrier when it is no longer required. The immediate area occupied by the bales and any sediment deposits shall be shaped to an acceptable grade.
Seed the areas disturbed by this shaping in accordance with Section 32 92 19
SEEDING.
3.3.3 Diversion Dike Maintenance
Inspect diversion dikes in accordance with paragraph, titled "Inspections," of this section. Pay close attention to the repair of damaged diversion dikes and accomplish necessary repairs promptly. When diversion dikes are no longer required, shape to an acceptable grade. Seed the areas disturbed by this shaping in accordance with Section 32 92 19 SEEDING.
file:///D:/Documents%20and%20Settings/bradley.CRAWFORD/My%20Documents/32%2092%2019.doc file:///D:/Documents%20and%20Settings/bradley.CRAWFORD/My%20Documents/32%2092%2019.doc
3.4 INSPECTIONS
3.4.1 General
Inspect disturbed areas of the construction site, areas that have not been finally stabilized used for storage of materials exposed to precipitation, stabilization practices, structural practices, other controls, and area where vehicles exit the site at least once every seven (7) calendar days and within 24 hours of the end of any storm that produces 0.5 inches or more rainfall at the site. Conduct inspections at least once every month where sites have been finally stabilized.
3.4.2 Inspections Details
Inspect disturbed areas and areas used for material storage that are exposed to precipitation for evidence of, or the potential for, pollutants entering the drainage system. Observe erosion and sediment control measures identified in the Storm Water Pollution Prevention Plan to ensure that they are operating correctly. Inspect discharge locations or points to ascertain whether erosion control measures are effective in preventing significant impacts to receiving waters. Inspect locations where vehicles exit the site for evidence of offsite sediment tracking.
3.4.3 Inspection Reports
For each inspection conducted, prepare a report summarizing the scope of the inspection, name(s) and qualifications of personnel making the inspection, the date(s) of the inspection, major observations relating to the implementation of the Storm Water Pollution Prevention Plan, maintenance performed, and actions taken. Furnish the report to the Contracting Officer within 24 hours of the inspection as a part of the Contractor's daily CQC
REPORT. A copy of the inspection report shall be maintained on the job site.
-- End of Section --