RFI_MEP_RESPONSES_1.pdf
PDF 6 KB Posted
- Solicitation number
- N62473-14-R-0013
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFI_RESPONSES_42_thru_44.pdf | ||
| RFI_RESPONSES_20_thru_41.pdf | ||
| RFI_RESPONSES_17-19.pdf | ||
| RFI_RESPONSES_16.pdf | ||
| MEP_AE_IDIQ_SB_SA_Solicitation_Amend_01_27_February_2014.pdf | ||
| RFI_RESPONSES_8_thru_15.pdf | ||
| RFI_RESPONSES_2 7.pdf | ||
| MEP_14R0013_AE_IDIQ_SB_SA__Solicitation.pdf | ||
| PPQ_rev_dec_2011.docx | DOCX document | |
| SF_330_form.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFI Questions and Responses
N62473-14-R-0013 AE IDIQ MECHANICAL, ELECTRICAL AND PLUMBING (MEP)
SMALL BUSINESS SET-ASIDE, NAVFAC SW
Question #1: The solicitation states that the minimum value of individual task orders executed under this contract is $200,000 and the maximum value of individual task orders executed under this contract is $2,500,000. Are the values stated above for the estimated construction cost of a project, or are they for the A&E fee?
Response #1:
The task order minimum and maximum amounts are for the A&E fee.