This document is a final amendment to the solicitation for N6247023R9006, which is for Professional Services for Mission Assurance Assessments of Installation/Facilities Infrastructure and Facility-Related Control Systems (FRCS) for the Department of the Navy (DON) worldwide. The amendment revises Sections J and L, disseminates pre-award inquiries, and provides updates to Attachment B - Schedule of Services. Key details include:

The solicitation is for highly specialized technical, analytical, and investigative support services to develop and conduct comprehensive assessments of DoN installations, facilities, and supporting utility infrastructure and Facility-Related Control Systems. The work will primarily be performed within the NAVFAC Atlantic and Pacific areas of responsibility, both CONUS and OCONUS. The period of performance is a base period plus four option years, with a total not-to-exceed value of $95,000,000. Proposals are due by 2:00 PM local time on April 18, 2024. The solicitation includes requirements for specific key personnel, clearances, and a subcontracting plan.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

N6247023R9006: PROFESSIONAL SERVICES FOR MISSION ASSURANCE ASSESSMENTS OF INSTALLATION/FACILITIES INFRASTRUCTURE AND FACILITY-RELATED CONTROL SYSTEMS (FRCS) FOR THE DEPARTMENT OF THE NAVY (DON), WORLDWIDE

This final amendment is issued to provide revisions to Section J and L and disseminate pre-aw ard inquires.

(SEE CONTINUATION PAGE)

1. CONTRACT ID CODE PAGE OF PAGES

J 1 24

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 28-Mar-2024

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N6247023R9006

X 9B. DATED (SEE ITEM 11)

13-Mar-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

28-Mar-2024

CODE

COMNAVFACSYSCOM ATLANTIC

6506 HAMPTON BLVD

NORFOLK VA 23508-1278

N62470 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N6247023R9006

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMENDMENT 0003

The purpose of this amendment is to disseminate the below information.

1. All pre-award inquires being addressed are included in this final amendment. The proposal due date remains unchanged.

2. Section J – Revisions are made to Section J Table of Contents. Amendment 0003 pre-award inquiry responses are provided and the following attachment. See note below.

Attachment B - Schedule of Services (Amendment 0003)

3. Section L – Revisions are made to item L.6, see note below.

NOTE: Revisions are provided by the use of red font; deletions are indicated by the use of red strikethrough font.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been added by full text:

AMEND 0003 PRE-AWARD INQUIRIES

REFERENCE QUESTION GOVERNMENT

RESPONSE Page Section Para.

46 of

L.6 (a) (1)

1 Requirement: "Offerors shall provide one (1) electronic copies of the price proposal on a non-rewritable CD in Microsoft Office Excel format and shall be Microsoft Office Version 2016 compatible" Question: Will the Government confirm that this requirement is an oversight/obsolete, and that the offeror needs to provide only hard copy submission (i.e no electronic copy on CD or otherwise needs to be submitted)?

Amendment 0003 revises Section L.6 (a) Volume I — Price Proposal, 1) Solicitation Submittal Requirements of the solicitation stating, “Offerors shall provide one (1) electronic copy of the price proposal on a non-rewritable CD in Adobe PDF format and shall be Microsoft Office Version 2016 compatible."

49 of

Tab K 4 Requirement: "A list of the cleared personnel (Full Name and SSN) who are proposed to work on this effort with their clearance level" Question: In order to safeguard Personal Identifable Information (PII), will the Government amend this requirement to include Full Name and only last four (4) digits of the SSN, instead of requiring the complete

SSN?

Information with proper markings should be submitted in accordance with Section L.6, Tab K.

NAVFAC Security will be responsible for the contents and proper disposal. Security needs full social security numbers for verification of clearances.

47 of

Tab G (f) Requirement: Subcontractor costs will be negotiated at TO Level. Question: Please confirm that subcontractors do not need to submit any price lists, attachment b-schedules, or sealed envelopes directly to the Govt. for this proposal submission?

Confirmed.

5 C, 1.1 First Para.

Background: Section 1.1 Mission states:

"The Navy and Marine Corps Mission Assurance (MA) Program and FRCS Program requires highly specialized technical, analytical, and investigative support services to develop and conduct comprehensive assessments of an Installation and/or Facility critical infrastructure, utility infrastructure, and operational utility technology, which includes FRCS as it relates to the warfighter’s risk."

Question: Would the government provide the number of assessments required per year?

Number of assessments not available at this time.

11 C, 2.5 Third full Para., third sentence

Background: 2.5 Specific Personnel Requirements, third full paragraph, Technical Specialist (Program Analyst), third sentence states: "The Program Analyst assists in leading and participates in teams . . . " Question: Would the government provide the number of assessment teams required per year?

The number of assessment teams required are not available at this time.

46 L.6 L.6 (a) (1)

First Para., second sentence

Background: Section L.6 (a) (1) Submittal Requirement, second sentence states that:

"Non-price proposals shall be submitted on 8 ½ x 11 paper with a font no smaller than 10 point."

Question: Would the government confirm that the offeror may use any font type (e.g., Times New Roman, Arial, or other)?

Please follow instructions in Section L.6 (a) of the solicitation.

5 C, 1.2 Fourth Para.

Background: Section C, 1.2 Background, fourth paragraph states: "All work shall be performed in accordance with individual task order performance work statements."

Question: How will the government award these task orders (by region, by site, etc.)?

Locations are determined on each task order.

9 C, 2.5 Third Para., fourth sentence

Background: Section C, 2.5 Specific Personnel Requirements, third paragraph Program Manager, fourth sentence states "The Program Manager shall have a minimum of a Bachelor’s degree and shall have at least 10 years of full-time professional experience in management, mission assurance inspections, and/or risk mitigation of military installations/missions, and shall have a minimum of 5 years of experience as a project principal or project director."

Question: Would the government be willing to substitute knowledge, skills, and experience in lieu of formal education requirements?

No.

9 C, 2.5 Third Para., fourth sentence

Background: Section C, 2.5 Specific Personnel Requirements, third paragraph Program Manager, fourth sentence states "The Program Manager shall have a minimum of a Bachelor’s degree and shall have at least 10 years of full-time professional experience in management, mission assurance inspections, and/or risk mitigation of military installations/missions, and shall have a minimum of 5 years of experience as a project principal or project director."

Question: Would the government state the number of years of experience in the mission assurance field of work are required to substitute for education requirements?

No.

13 C, 2.5 Second and

Third Paras.

Background: Section C, 2.5 Specific Personnel Requirements, page 13, second and third paragraphs: Technical/Writer/Editor and Administrative Assistant.

Question: Would the Government please confirm Clearance requirements for all Labor Categories as interaction between SMEs may be limited due to conflict (lack of TS clearances for several LCATs).

Please refer to Section C, 2.5 Specific Personnel Requirements and Section I, Contract Clauses including FAR 52.204-2 Security Requirements.

6 to 7 C, 1.3 All outline elements

Background: Section C, 1.3 Scope provides requirements for assessments: "The Contractor shall be able provide services in accordance with DoN assessment program guides and benchmarks . . ."

Question: Would the Government further define the scope of each assessment in the task orders / PWS?

The Government is unable to further define the scope of individual task orders that will be issued at this time.

6 C, 1.3 All outline elements

Background: Section C, 1.3 Scope provides requirements for assessments: "The Contractor shall be able provide services in accordance with DoN assessment program guides and benchmarks . . ."

Question: Will schedule execution be prioritized by geographic region, facility type, or vulnerability level?

No.

8 C, 2.5 Second Para. and

All

Background: Section C, 2.5 Specific Personnel Requirements states: " Agencies, institutions, corporations, associations, or individuals will be considered qualified when they meet the criteria given below. If, during the performance of this contract, the contractor must utilize personnel other than those identified in the technical proposal, such substitution shall not be made without written approval of the KO."

Question: Are all positions in paragraph 2.5 considered key requiring Government approval?

Please refer to Section C, 2.5 Specific Personnel Requirements of the solicitation.

18 F.1 One Para., All

Background: Section F, F.1 Location states:

"Work will be performed within DoN’s Area of Responsibility (AOR) with a concentration of work within the Continental United States, the Pacific, Far East, Europe, Africa, and South Western Asia. Each task order will provide the specific location for the work to be performed under it."

Question: Where does the government expect that contractor personnel will need to be co-located with the government customer to perform all assessment activities, admin, research, report writing, etc.?

Deliverables will be coordinated on each issued task order.

46-47 Tab G;

Attachme nt B

Para. e.

(page 47)

Background: In Tab G. Completed Attachment B- Schedule of Services, Paragraph e. (on page 47) the verbiage states "The multiplier percentage proposed shall include all handling fees, indirect costs, i.e., overhead and general and administrative costs, and profit applicable to “other direct costs.”" conflicts with "Attachment B - Schedule of services", where "The multiplier percentage proposed shall include all handling fees and indirect costs, i.e., overhead and general and administrative costs, applicable to travel, ODCs, and Subcontractor labor. No additional indirect costs or profit will be applied."

Question: Will the government confirm that the multiplier percentage shall include an applied profit?

Please see this Amendment, Amendment 0003, which revises Attachment B - Schedule of Services, Notes:

#5 for the Base Year and all Option Years Labor Categories and Rates.

46-47 and All

Tab G;

Attachme nt B

All Background: In Tab G. Completed Attachment B- Schedule of Services: The Level of Effort, ODCs, and Travel all appear to decrease, year over year.

Question: Is the government anticipating decreased Level of Effort as the contract progresses?

Please refer to Attachment B

- Schedule of Services and follow instruction in Section L.6(a), Tab G of the solicitation.

45-46 L.6, a. First Para.

(page 46)

Background: Section L.6, (a) Volume I — Price Proposal, (1) Solicitation Submittal Requirements (page 46) First Paragraph states: "Submit one (1) “Original” and two (1) copies of the price proposal in three-ring binders clearly marked as the Price Proposal.

Non-price proposals shall be submitted on 8 ½ x 11 paper with a font no smaller than 10 point. In addition to providing hard copies of the price proposal offerors shall provide one

(1) electronic copies of the price proposal on a non-rewritable CD in Microsoft Office Excel format and shall be Microsoft Office Version 2016 compatible."

Question: Would the government confirm that the Government will provide a price proposal template in Microsoft Excel format for the Volume I - Price Proposal?

Amendment 0003 revises Section L.6 (a) Volume I — Price Proposal, 1) Solicitation Submittal Requirements of the solicitation stating, “Offerors shall provide one (1) electronic copy of the price proposal on a non-rewritable CD in Adobe PDF format and shall be Microsoft Office Version 2016 compatible."

L. L.1 & L.6

Will the Government extend the proposal due date by two weeks? The requirement to deliver hard copy proposals by express mail carrier means that bidders will need an extension for hard copy proposal production, express mail carrier verification, and shipping/enroute time.

The Government is not extending the solicitation due date at this time.

L. L.1 & L.6

We have numerous employees with CAC cards who are capable of delivering hardcopy proposals to the Government. Will the Government reconsider the requirement to ship hard copies by express mail carrier? If so, will the Government allow hardcopy proposals to be delivered by hand by those offerors having a CAC holder in the customer's vicinity who can make a hand delivery?

Per L.1, Submitting Your Proposal, of the solicitation states: “NO HAND OR

ELECTRONIC DELIVERY

OF PROPOSALS WILL BE

ACCEPTED.”

n/a n/a n/a May offerors make fillable versions of Solicitation attachments J-1 to J-5? This will make it much easier to add information to these attachments.

Please refer to Section J of the solicitation for associated attachments. The Government is not providing additional versions of attachments at this time.

2 IDIQ

Solicitatio n

A

Third Heading (page 2)

Background: Section A, Third Heading, NOTICE (page 2) states: "PROPOSALS ARE

DUE BY 2:00 P.M. NORFOLK, VA LOCAL

TIME ON 18 APRIL 2024".

Question: To ensure sufficient time for compliant responses that incorporate the Government's answers to questions from industry, and time required for hardcopy production and delivery of proposals, would the Government extend the proposal due date

The Government is not extending the solicitation due date at this time.

to Thursday, 2 May 2024 at 2:00 PM local time?

5 IDIQ

C, 1.1

First Para.

Background: Section C, Section 1.1 Mission states: "The Navy and Marine Corps Mission Assurance (MA) Program and FRCS Program requires highly specialized technical, analytical, and investigative support services to develop and conduct comprehensive assessments of an Installation and/or Facility critical infrastructure, utility infrastructure, and operational utility technology, which includes FRCS as it relates to the warfighter’s risk."

Question: Would the Government provide the number of assessments required per year?

The number of assessments required per year are not available at this time.

5 IDIQ

C, 1.2

Fourth Para.

Background: Section C, Section 1.2 Background, fourth paragraph states: "All work shall be performed in accordance with individual task order performance work statements (PWS)."

Question: How will the Government award these task orders (by region, by site, etc.)?

Locations are determined on each task order.

6 to 7 IDIQ

C, 1.3

All outline elements

Background: Section C, Section 1.3 Scope provides requirements for assessments: "The Contractor shall be able provide services in accordance with DoN assessment program guides and benchmarks . . ."

Question: Will the Government further define the scope of each assessment in the future task orders / PWS?

The Government is unable to further define the scope of individual task orders that will be issued at this time.

6 to 7

IDIQ

C, 1.3 outline elements

Background: Section C, Section 1.3 Scope provides requirements for assessments: "The Contractor shall be able provide services in accordance with DoN assessment program guides and benchmarks . . ."

Question: Will the Government provide the schedule of the future task orders / PWS and will it be prioritized by geographic region, facility type, or criticality?

Schedules and deliverables will be provided in each task order.

9 IDIQ

C, 2.5

Second Para. and

All

Background: Section C, Section 2.5 Specific Personnel Requirements states: "Agencies, institutions, corporations, associations, or individuals will be considered qualified when they meet the criteria given below. If, during the performance of this contract, the contractor must utilize personnel other than those identified in the technical proposal, such substitution shall not be made without written approval of the KO."

Question: Are all positions in Section 2.5 considered Key; therefore, requiring Government approval?

Please refer to Section C, 2.5 Specific Personnel Requirements of the solicitation.

9 IDIQ

Para., fifth sentence

Background: Section C, Section 2.5 Specific Personnel Requirements, Program Manager, third paragraph, fifth sentence states: "The Program Manager shall have a minimum of a Bachelor’s degree and shall have at least 10 years of full-time professional experience in management, mission assurance inspections, and/or risk mitigation of military installations/missions, and shall have a minimum of 5 years of experience as a project principal or project director."

Question: Would the Government be willing to substitute knowledge, skills, and experience in lieu of formal education requirements?

No.

9 IDIQ

Para., fifth sentence

Background: Section C, Section 2.5 Specific Personnel Requirements, Program Manager, third paragraph, fifth sentence states: "The Program Manager shall have a minimum of a Bachelor’s degree and shall have at least 10 years of full-time professional experience in management, mission assurance inspections, and/or risk mitigation of military installations/missions, and shall have a minimum of 5 years of experience as a project principal or project director."

Question: Would the Government state the number of years of experience in the mission assurance field of work are required to substitute for education requirements?

No.

11 IDIQ

Third full Para., fourth sentence

Background: Section C, Section 2.5 Specific Personnel Requirements, Technical Specialist (Program Analyst), third full paragraph (on page 11), fourth sentence states: "The Program Analyst assists in leading and participates in teams . . . "

Question: Would the Government provide the number of assessment teams required per year?

The number of assessment teams required are not available at this time.

13 IDIQ

Second and

Third Paras.

Background: Section C, Section 2.5 Specific Personnel Requirements, Technical/Writer/Editor and Administrative Assistant, second and third paragraphs (page

13) do not reference personnel security clearance requirements.

Question: Would the Government please confirm Clearance requirements for all Labor Categories as interaction between SMEs may be limited due to conflict (variance between Top Secret, Secret and no clearance requirement noted).

Please refer to Section C, 2.5 Specific Personnel Requirements and Section I, Contract Clauses including FAR 52.204-2 Security Requirements.

18 IDIQ

F.1

One Para., All

Background: Section F, Section F.1 LOCATION states: "Work will be performed within DoN’s Area of Responsibility (AOR) with a concentration of work within the Continental United States, the Pacific, Far East, Europe, Africa, and South Western Asia.

Each task order will provide the specific location for the work to be performed under it."

Question: Where does the Government expect that contractor personnel will need to be co-located with the Government to perform all assessment activities, admin, research, report writing, etc.?

Deliverables will be coordinated on each issued task order.

44 IDIQ

L.1

First Para.

(page 44)

Background: Section L, Section L.1 SUBMITTING YOUR PROPOSAL (page 44) first paragraph states: "Proposals must be submitted via express mail carriers to the address immediately below this paragraph;

NO HAND OR ELECTRONIC DELIVERY

OF PROPOSALS WILL BE ACCEPTED."

Question: Would the Government allow electronic submission using an industry portal such as the Procurement Integrated Enterprise Environment (PIEE) utility for submission and delivery of proposals?

Please follow instructions in Section L.1, Submitting Your Proposal of the solicitation.

45-46 IDIQ

L.6, (a), (1)

First Para.

(page 46)

Background: Section L, Section L.6, (a) Volume I — Price Proposal, (1) Solicitation Submittal Requirements, first paragraph (page

46) states: "Submit one (1) “Original” and two

(1) copies of the price proposal in three-ring binders clearly marked as the Price Proposal.

Non-price proposals shall be submitted on 8 ½ x 11 paper with a font no smaller than 10 point. In addition to providing hard copies of the price proposal offerors shall provide one

(1) electronic copies of the price proposal on a non-rewritable CD in Microsoft Office Excel format and shall be Microsoft Office Version

Amendment 0003 revises Section L.6 (a) Volume I — Price Proposal, 1) Solicitation Submittal Requirements of the solicitation stating: “Offerors shall provide one (1) electronic copy of the price proposal on a non-rewritable CD in Adobe PDF format and shall be Microsoft Office Version 2016 compatible."

2016 compatible."

Question: Will the Government provide a price proposal template in Microsoft Excel format for the Volume I - Price Proposal? Will the Government clarify whether one or two copes (not "Original" version) of the price proposal are to be provided in the three-ring binders?

46 IDIQ

L.6, (a), (1)

First Para.

(page 46), second sentence

Background: Section L, Section L.6, (a) Volume I — Price Proposal, (1) Solicitation Submittal Requirements, first paragraph, second sentence (page 46) states: "Non-price proposals shall be submitted on 8 ½ x 11 paper with a font no smaller than 10 point."

Question: Would the Government confirm that the offeror may use any font type (e.g., Times New Roman, Arial, or other)?

Please follow instructions in Section L.6 (a) of the solicitation.

46-47 Attachme nt B -

Schedule of

Services

IDIQ

Colicitati on

L.6, Tab G

(Attachm ent B), e

Para. e.

(page 47)

Background: In the IDIQ Solicitation, Section L, Section L.6, Tab G. Completed Attachment B- Schedule of Services, Paragraph e. (on page 47) the verbiage states:

"The multiplier percentage proposed shall include all handling fees, indirect costs, i.e., overhead and general and administrative costs, and profit applicable to “other direct costs.”"

In the file "Attachment B - Schedule of Services" (Note #5 for the Base Year on page 2 for example) states: "The multiplier percentage proposed shall include all handling fees and indirect costs, i.e., overhead and general and administrative costs, applicable to travel, ODCs, and Subcontractor labor. No additional indirect costs or profit will be applied."

These statements appear to conflict between documents.

Question: Will the Government confirm that the multiplier percentage shall include an applied profit?

Please see this Amendment, Amendment 0003, which revises Attachment B - Schedule of Services, Notes:

#5 for the Base Year and all Option Years Labor Categories and Rates.

46-47 and All

Attachme nt B -

Schedule of

Services

IDIQ

Colicitati on

L.6, Tab G

(Attachm ent B)

46/47

Background: In Tab G. Completed Attachment B- Schedule of Services: The Level of Effort, ODCs, and Travel all appear to decrease, year over year.

Question: Is the Government anticipating decreased Level of Effort as the contract progresses?

Please refer to Attachment B

- Schedule of Services and follow instruction in Section L.6(a), Tab G of the solicitation.

The following have been modified:

SECTION J

DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

TABLE OF CONTENTS

NOTE: The individual files for Section J are attached separately. (Note: The documents are provided in www.SAM.gov under the solicitation number with their corresponding attachment numbers.)

This contract incorporates by reference the following attachments as if they were fully set forth herein. Please see the following attachments as part of this solicitation:

DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS

TABLE OF CONTENTS

ATTACHMENT

NUMBER

ATTACHMENT TITLE

Attachment B Schedule of Services (Amendment 0003) J-1 Past Performance Questionnaire (PPQ) J-2 Corporate Experience Project Data Sheet J-3 Historical Small Business Utilization J-4 Small Business Participation Commitment Document (SBPCD) J-5 Small Business Subcontracting Plan (SBSP) Template J-6 Pre-Award Inquiry Form J-7 DD254 Form Solicitation N6247023R9006 MAR 2024

The following references are not provided as attachments but are incorporated by reference as providing guidance for the work to be performed under this contract.

Reference Documents

Reference TITLE

DoDI 3020.45 Mission Assurance (MA) Construct

DoD Instruction O-2000.16 DoD Antiterrorism (AT) Standards

SECNAVINST 3501.2 Department of the Navy Mission Assurance Program

OPNAVINST 3502.8 Navy Mission Assurance Program

MCO 3058.1 Marine Corps Mission Assurance

DoDI 8510.01 Risk Management Framework (RMF) for DoD Information Technology (IT)

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

The following have been modified:

SECTION L

L.1 SUBMITTING YOUR PROPOSAL

Proposals must be submitted via express mail carriers to the address immediately below this paragraph; NO HAND

OR ELECTRONIC DELIVERY OF PROPOSALS WILL BE ACCEPTED.

Proposal Delivery Address:

Naval Facilities Engineering Systems Command (NAVFAC), Atlantic Attn: Barkley Brown, Code CON36 Building A – Mail Room 6506 Hampton Blvd Norfolk, Virginia 23508-1278

The signature of the Offeror provided in Box 17 of the SF33 agrees, if this offer is accepted within 180 calendar days from the date of receipt of offers specified as the due date in Box 9 of the SF33 or any extended due date, to furnish any or all items upon which the prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

Annotate solicitation number N6247023R9006 on the bottom of the envelope or box. Proposals must be received and date stamped at the stated address above no later than the date and time identified in block 9 on the SF33.

Express mail carriers Security Information:

Commercial couriers such as FEDEX, DHL, or UPS must follow visitor procedures and are required to have a background check if they do not have a CAC badge. Commercial couriers must also have their vehicle inspected following LRA commercial vehicle inspection procedures prior to accessing the LRA. The Commercial Vehicle Inspection location for vehicles coming to NAVFAC Atlantic on the Lafayette River Annex (LRA) is located at Naval Support Activity (NSA) Hampton Roads at the Meredith Street gate off of Terminal Boulevard.

Firms should check with their intended courier to ensure they have the proper identification credentials to access the

LRA.

DBIDS passes must be picked up by the approved visitor from the Naval Station Pass and ID Office located at the following address prior to visiting NAVFAC Atlantic on LRA:

Naval Station Pass and ID Office

9040 Hampton Blvd Building #CD9 Norfolk, VA 23505 Telephone Number: 757-322-2975 Hours of Operation: 0700 – 1530 Monday through Friday

NOTE: This is not the address for proposal delivery. Proposals mailed to this address may not be received by NAVFAC prior to the deadline.

All potential Offerors must adhere to this notice in order to avoid delay in submitting your proposal. The level of security at Lafayette River Annex may change at any time. As the level of security heightens, the amount of time required to gain access to the Lafayette River Annex also increases.

L.2 PRE-AWARD INQUIRIES/REQUEST FOR PROPOSALS (RFP) INFORMATION/

CLARIFICATIONS/QUESTIONS

Contractors are required to review the entire solicitation package before submitting questions. Submit all questions via one document using Attachment J-6, Pre-award Inquiry Form, by E-mail to Barkley Brown (barkley.k.brown.civ@us.navy.mil) no later than no later than 2:00 P.M. Norfolk, VA local time on 26 MARCH 2024. The Government does not intend to respond to any pre-proposal inquiries submitted after 2:00 P.M. Norfolk, VA local time on 26 MARCH 2024 order to permit adequate time to reply to the inquiries. This is the most efficient way to ensure all questions are addressed in a timely manner.

L.3 REQUEST FOR PROPOSAL (RFP) FILES

Solicitations are posted to the Opportunities (https://www.sam.gov) website. By necessity, these files are protected to prevent unauthorized editing. It is the sole responsibility of the Offeror to obtain the RFP files, along with any amendments, from the Opportunities Website.

L.4 GENERAL PROPOSAL REQUIREMENTS

The price proposal and non-price proposals shall be submitted in separate three-ring binders and tabbed appropriately. Binders must be marked as “Volume I: Price Proposal” and “Volume II: Non-Price Proposal”. Should there be a discrepancy between paper and electronic information, the paper copies shall govern.

Elaborate brochures or other presentations beyond that sufficient to present a complete and effective proposal are not desired. Elaborate artwork and expensive visual or other presentation aids are not necessary. Organization, clarity, accuracy of information, relevance, and completeness are of prime importance.

L.5 EVALUATION FACTORS

1. The solicitation requires the evaluation of price and the following non-cost/price factors:

Factor 1 - Corporate Experience Factor 2 - Technical/Management Approach Factor 3 - Safety Factor 4 - Small Business Utilization and Participation Factor 5 - Past Performance

The distinction between experience and past performance is that experience pertains to the volume of work completed by a contractor that are comparable to the types of work described under the definition of recent, relevant projects, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.

2. The relative order of importance of the non-price evaluation factors is the technical factors, Factors 1, 2, 3, and 4, are of equal importance to each other and, when combined are equal in importance to the past performance evaluation/performance confidence assessment factor, Factor 5. When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-cost/price evaluation factors) are approximately equal to price.

The importance of price will increase if the Offerors’ non-cost/price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-cost/price proposal’s superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.

3. Basis of Evaluation and Submittal Requirements for Each Factor.

L.6 PRICE AND NON-PRICE PROPOSAL SUBMITTAL REQUIREMENTS

(a) Volume I — Price Proposal:

(1) Solicitation Submittal Requirements: Submit one (1) “Original” and one (1) copy of the price proposal in three-ring binders clearly marked as the Price Proposal. Non-price proposals shall be submitted on 8 ½ x 11 paper with a font no smaller than 10 point. In addition to providing hard copies of the price proposal offerors shall provide one (1) electronic copy of the price proposal on a non-rewritable CD in Adobe PDF Microsoft Office Excel format and shall be Microsoft Office Version 2016 compatible. Offerors are advised that, in the event of a discrepancy between pricing information contained on the CD and the hard copy proposal, the original hard copy will govern. There is no page limit for Volume 1. Each copy of the price proposal shall include a separate tab for each item specified below:

Tab A. Identify the Company profile to include, the Offeror’s name, address, names of two (2) points of contact (including title, phone number and email address), the Unique Entity ID (UEI) Number and CAGE code;

Tab B. Completed and signed Standard Form 33 (SF-33)

Tab C. Acknowledgement of all solicitation amendment(s) (SF-30’s) related to this RFP.

Tab D. CONTRACTOR PROPOSAL CERTIFICATION:

____________________________________________ (Name of Offeror) warrants that its proposal _____________________________ (of date or other identifier) incorporated herein by reference, including, but not limited to, proposed approaches, staffing, methodology, or work plans, will meet the performance objectives set forth in this contract during the execution thereof. The contractor is not excused from meeting such performance objectives in the event such proposal proves inadequate as conceived or executed to meet such performance objectives. The contractor understands that it bears all of the cost and performance risk associated with adopting acceptable additional (and/or alternative) means or methods of meeting the performance objectives.

Tab E. Representations and Certifications (ref: https://www.sam.gov).

Tab F. Any offeror proposing as a partnership, joint venture, other teaming arrangement, or resource of a parent company/subsidiary/affiliate shall submit the following information:

i. Provide a listing of the team members’ corporate name (no abbreviations), address, point of contact, phone number, UEI Number, and CAGE Code.

ii. Submit signed letters of commitment from the team members. The commitment letter shall clearly identify the expected relationship, role and responsibility of the team member.

iii. If proposing as a Joint Venture, submit a signed copy of the Joint Venture Agreement.

When proposing as a joint venture, all members of the joint venture shall sign the SF33 unless a written agreement by the joint venture is furnished with the proposal designating that one firm with the authority to bind the other member(s) of the joint venture. In addition, a signed copy of the joint venture agreement shall be submitted with the proposal. Failure to comply with the foregoing requirement may eliminate the proposal from further consideration. If the joint venture is subject to the SBA Mentor-Protégé Program, a copy of the SBA approval of the joint venture arrangement shall be included. In addition, Joint Ventures shall specify if they are populated or unpopulated.

Tab G. Completed Attachment B- Schedule of Services for the base and all option years in U.S. Dollars.;

Note: Firm fixed-price task orders will be negotiated for the services required under this contract using the fully burdened labor rates and percent mark-ups for travel and other direct costs proposed under Attachment B- Schedule of Services, for the base year and each option year (if exercised). However, the quantities listed in Attachment B- Schedule of Services are estimates only and will not be ordered with the award of the basic contract. Actual quantities ordered over the duration of the contract are expected to vary and are not limited to those estimated in Attachment B- Schedule of Services of Services and shall not exceed the total contract not-to-exceed amount of $95,000,000.00 (base period and all option years).

Attachment B- Schedule of Services shall be completed as follows (items a-e):

a. Offerors shall enter unit prices, percent mark-ups, extended prices and total amounts as indicated on Attachment B- Schedule of Services, for the base period and all option years. All labor rates and extended prices shall be rounded to two (2) decimal places and the rounded prices will be used for evaluation purposes.

b. In the event there is a difference between a labor rate and the extended total amount (i.e. Hourly labor rate x estimated hours = extended total) the labor rate will be held to be the intended offer and the extended price and total price will be recomputed accordingly. If the offeror provides a total amount for a labor category(s) listed in Attachment B- Schedule of Services, but fails to enter the unit price, the extended price divided by the estimated labor hours will be held to the intended unit price or labor rate.

c. Proposed burdened labor rates shall reflect composite fully burdened hourly labor rates for prime/Joint Venture contractor, as applicable, performing work under the contract. Burdened hourly labor rates shall include the following costs: direct labor, fringe benefits, overhead, phone service (cellular and landline), all computer charges for computer workstations and laptops including standard software packages, general and administrative costs, and profit. Additionally, administrative costs for contract management, invoicing and other task order administrative tasks will not be separately negotiated, and shall be incorporated in the indirect costs included in the fully burdened hourly labor rates. Additional burdened labor classifications for the prime/JV will not be added to the contract or negotiated under individual task orders.

d. Applicable travel costs will be negotiated under individual task orders. Travel, subsistence and per diem costs negotiated under task orders shall be in compliance with current Joint Travel Regulation rates. The estimated travel costs listed in Attachment B are for proposed costs to be directly incurred by the prime/JV under task orders issued under the contract. The prime/JV travel costs will be multiplied by the percentage shown on the schedule for direct costs and profit applied to travel. The multiplier percentage proposed shall include all handling fees, indirect costs, i.e., overhead and general and administrative costs, and profit applicable to travel. No additional indirect costs or profit will be applied to the prime contractor’s travel except as included in the multiplier percentage listed in the Attachment B- Schedule of Services.

e. Supplies/equipment/other direct costs will be negotiated under individual task orders. The estimated supplies/equipment/other direct costs listed in Attachment B - Schedule of Services are for proposed costs to be directly incurred by the prime/JV under task orders issued under the contract. These costs include, but are not limited, to equipment, supplies, material, reproduction, and shipping. The prime/JV/subcontractor “other direct costs” will be multiplied by the percentage shown on the schedule for indirect costs and profit applied to “other direct costs.” The multiplier percentage proposed shall include all handling fees, indirect costs, i.e., overhead and general and administrative costs, and profit applicable to “other direct costs.” No additional indirect costs or profit will be applied to the prime contractor’s “other direct costs’ except as included in the multiplier percentage listed in the schedule.

f. Subcontractor costs will be negotiated under individual task orders. The estimated subcontractor costs listed in Attachment B- Schedule of Services are for proposed costs to be directly incurred by the prime/JV under task orders issued under the contract. The prime/joint venture subcontractor costs will be multiplied by the percentage shown on the schedule for indirect costs and profit applied to subcontractor costs. The multiplier percentage includes all handling fees, indirect costs, i.e., overhead and general and administrative costs, and profit applicable to subcontractor costs. No additional indirect costs or profit will be applied to the prime contractor’s subcontractor costs, except as included in the multiplier percentage listed in the schedule.

Tab H. Please submit the below items (a through c) with your price proposal in a SEALED envelope labeled “TAB H”. Although this information is required to be submitted with your firm’s price proposal, this information will not be evaluated as part of the price proposal. This information forms the basis of your firm’s responsibility determination should your firm be considered for award. In order to be eligible for award, your firm must be determined responsible in accordance with FAR Part 9, specifically 9.104-1, General Standards.

a. Provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or at least by an authorized officer of the organization.

Submit evidence of availability of working/operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements submit the latest three complete fiscal year financial statements for each Joint Venture company and discuss the financial responsibilities among the companies. The Government may also utilize Dun & Bradstreet reports to evaluate the financial capacity of the offeror.

b. One (1) signed Bank Reference demonstrating adequate financial resources. If your firm has a line of credit, provide information on how many figures can your firm borrow against the line of credit (i.e.

“medium 6 figures”,-exact line of credit is not required).

c. Three (3) signed credit references. Credit references must verify that your firm pays its creditors timely and in accordance with the terms negotiated with the creditor.

d. The Government may request additional information if needed to determine responsibility.

Tab I. Compensation Plan for Professional Employees. Provide a total compensation plan in accordance with FAR 52.222-46, Evaluation of Compensation for Professional Employees (FEB 1993), setting forth salaries and fringe benefits proposed for the professional employees who will work under the contract. Advise if you have different compensation plans for various skill levels. Although this information is required to be submitted with your firm’s price proposal, this information will not be evaluated as part of the price proposal. This information will be utilized as additional basis of your responsibility determination should your firm be considered for award.

Tab J. SMALL BUSINESS SUBCONTRACTING PLAN

In accordance with FAR 19.7, all other than small businesses shall submit a Small Business Subcontracting Plan (SBSP) utilizing the template provided as Attachment J-5. Acceptability of the SBSP will be considered a responsibility matter. The SBSP will not be evaluated or rated by the SSEB, but reviewed by a Small Business Professional/Authorized Representative and the Contracting Officer for acceptability. The SBSP shall be negotiated and/or accepted within the time specified by the Contracting Officer. Failure to negotiate an acceptable subcontracting plan within the time limit prescribed by the Contracting Officer will render the offeror ineligible for award of the contract. The SBSP will be incorporated into the resulting contract.

NAVFAC’s command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent realistic, challenging, small business subcontracting goals for this acquisition consistent with efficient and effective performance of the contract. These targets are based on a percentage of total planned subcontract dollars.

Small Business (SB) 40% Small Disadvantaged Business (SDB) 5% HUBZone SB 3% Woman-Owned Small Business (WOSB) 9% Service-Disabled Veteran-Owned Small Business (SDVOSB) 5%

The SBSP shall be consistent with the commitments offered in the Small Business Participation Commitment Document (Attachment J-4). In accordance with DFARS 215.304(c)(i), when an evaluation assesses the extent that small businesses are specifically identified in proposals, those small businesses considered in the evaluation shall be listed in the SBSP.

Please note that SBSP goals and the small business participation requirements provided in the Small Business Participation Commitment Document (SBPCD) WILL NOT be the same. The small business participation requirements within the SBPCD are provided as percentages of the total contract value; subcontract plan goals are provided as a percentage of planned subcontracting dollars. While the percentages will differ, the types of products/services identified in the SBSP, should be the same as those products/services identified in the SBPCD.

Likewise, the planned small business subcontract dollars in the SBSP will be equal to (or in some cases greater than) the extent of small business participation identified in the SBPCD.

Tab K. Please submit the below information, on your firm’s official letterhead, with your price proposal in a SEPARATE SEALED envelope, labeled “TAB K”, and marked as “CONTROLLED UNCLASSIFIED

INFORMATION”.

The letter shall contain the following:

Controlled By: U.S. NAVY Controlled By: [Company Name] CUI Category: OPSEC / PRIVACY Limited Dissemination Control: FEDCON POC: [Company – Facility Security Officer (Name/phone #)]

A statement regarding your firm’s possession of a Top Secret Facility Clearance, your firm’s CAGE Code information, and your firm’s Facility Address. This information is required to confirm your firm’s ability to meet the required Facility Clearance and Safeguarding capability for work under this contract.

A list of the cleared personnel (Full Name and SSN) who are proposed to work on this effort with their clearance level.

This data is NOT to be included on the electronic copies you will provide via a non-rewritable CD. Although this information is required to be submitted with your firm’s price proposal, this information will not be evaluated as part of the price proposal. This information allows the verification of your firm’s possession of the required security clearances. In order to be eligible for award, your firm must possess a Top Secret Facility Clearance.

(b) Volume II — Non-Price Proposal:

(1) Solicitation Submittal Requirements: Submit one (1) “Original” and four (4) copies of the non-price proposal in three-ring binders, clearly marked as Volume II: Non-Price Proposal and tabbed appropriately.

Non-price proposals shall be submitted on 8 ½ x 11 paper with a font no smaller than 10 point. In addition to providing hard copies of the non-price proposal, offerors shall provide one (1) electronic copy of the non-price proposal on a non-rewriteable CD that shall be Microsoft Office 2016 compatible. Failure to provide an electronic copy and/or Adobe PDF loaded on the non-rewritable CD may be cause to render the offeror non-responsive. The non-price proposal shall not exceed 50 single-sided or 25 double-sided pages. Pages exceeding the 50 single-sided / 25 double-sided page limitations shall not be evaluated. Note: The page limit count does not include the following:

Blank tab dividers and cover pages, Tab A, B, and C documents (including commitment letters from team members/subcontractors or Joint Venture agreements), Attachment J-1 Past Performance Questionnaires (PPQs), CPARS, Attachment J-4 – Small Business Participation Commitment Document (SBPCD), and Attachment J-5 – Small Business Subcontracting Plan (SBSP). Offerors may submit the organizational chart using 11 x 17 size paper and it will count as one (1) page towards the overall page limit listed above. Only the organization chart may be presented on 11 x 17 size paper. Each copy of the non-price proposal shall include a separate tab for each item specified below:

Tab A- Offerors shall include a cover page that provides: name and address of the prime contractor, UEI number, Cage Code and the name, title, email, phone and fax number of two (2) authorized representatives.

Tab B- Any offeror proposing as a partnership, joint venture, other teaming arrangement, or resource of a parent company/subsidiary/affiliate shall submit the following information:

I. Provide a listing of the team members’ corporate name (no abbreviations), address, point of contact, phone number, UEI Number, and CAGE Code.

II. Submit a signed letter of commitment from the team members. The commitment letter shall clearly identify the expected relationship, role and responsibility of the team member.

III. If proposing as a Joint Venture, provide the UEI Number; CAGE Code and a signed copy of the Joint Venture Agreement.

Tab C- Non-Price Factors.

(Tab 1) Factor 1 - Corporate Experience

(i) Solicitation Submittal Requirements: The Offeror shall provide a minimum of two

(2) and a maximum of three (3) examples of recent and relevant contracts to be documented through use of Corporate Experience Project Data Sheet (Attachment J-2). The Offeror shall clearly demonstrate recent and relevant experience on contracts similar in size, scope, and complexity to the requirements described in the Performance Work Statement (PWS).