Q&A_17-R-0001_2017_01_05.docx

DOCX document 22 KB Posted

Attached to
Small Craft Repairs Federal contract opportunity
Solicitation number
N62306-17-R-0001
Issued by
Department of the Navy Naval Meteorology and Oceanography Command

About this file

Q&A_17-R-0001_2017_01_05

View the file

Other files for this federal contract opportunity

Other files attached to Small Craft Repairs, newest first.
File Type Posted
Q&A_17-R-0001_2016_12_22.docx DOCX document
Site_Visit_Attendance_Sheet_2016_12_21.pdf PDF
PreProposal_Conference_Small_Craft_Repairs_2016_12_21.pdf PDF
Q&A_17-R-0001_2016_12_20.docx DOCX document
Attachment_4_SCA_05-2301.pdf PDF
Attachment_1_Navoceano_Small_Craft_Specification_Sheet.pdf PDF
Attachment_3_PRS_Matrix_2016_06_21.pdf PDF
Attachment_C_Seed_Task_Order_RFP.pdf PDF
Attachment_2__Navoceano_List_of__Equipment.pdf PDF
Attachment_B_Questions_Request_Form.docx DOCX document
Attachment_D_Seed_Task_Order_RFP_Price_Schedule.xlsx XLSX spreadsheet
Attachment_5_ELIN_Schedule.xlsx XLSX spreadsheet
Attachment_A_RFP_Small_Craft_Repair.pdf PDF
Show all 13

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment B

Questions Request Form

RFP/RFQ:
N62306-17-R-0001
Project Title
Small Craft Repair and Maintenance
#
SOW/PWS Reference
Question
Answer
1.
N62306-17-R-0001-Restoration and Upgrade of HSL’s 8 and 15 Part 1
Section 2. Can you please provide the Launch Information Book for 34 Foot Hydrographic Survey Launch?
Document is only for the awarded contractor. It is not needed for proposal purposes. It is mainly for operation of the boat
2.
N62306-17-R-0001-Restoration and Upgrade of HSL’s 8 and 15 Part 1
Section 2.2 Enclosures. Can you please provide each of the enclosures for 2.2.1 through 2.2.26 referenced here?
Documents are available through FBO sensitive site.

Note that these are controlled documents as noted on the drawings for use by the government and its contractors.

3.
General
Regarding the base contract, how do you estimate the materials given that is a very broad description of maintenance of 22 boats
It is up to the offeror to determine how to propose materials. The solicitation provides estimates for repairs and Seed Task Order to assist in the proposal process. The total price of estimated labor rates, travel and material is used for evaluation purposes only.
4.
Attachment C Seed Task Order RFP 5.1.4
Pease provide model # and or size/type of stripping pump to be replaced per 5.1.4
TAT Engineering Stripping Pump Model 650

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

20.

File details come from the government source that posted it. Updated .