J-5_Execution_Milestones_and_Key_Event_Dates Rev-2.xlsx

XLSX spreadsheet 11 KB Posted

Attached to
USS PORTLAND (LPD-27) FY23 Selected Restricted Availability (SRA)
Solicitation number
N55236-22-R-0012
Issued by

About this file

This document contains a federal solicitation for ship repair and maintenance services. The solicitation is seeking proposals to execute the USS PORTLAND (LPD-27) Selected Restricted Availability for fiscal year 2023, scheduled from December 14, 2022 to November 8, 2023. Offerors must have the capability to complete all necessary labor, supervision, production, testing and quality assurance to prepare and accomplish the availability. The work will require coordination and integration of multiple maintenance, repair and modernization areas. The Naval Sea Systems Command will make a single award by October 2022 on a coast-wide basis without limiting performance to the ship's homeport. Offerors must be registered in the System for Award Management and include their Unique Entity Identifier with any request for verification of Department of Defense contractor status. References containing limiting distribution statements will require coordination with the technical librarian point of contact to arrange access.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Exec Milestones (Contractual) USS PORTLAND LPD-27 FY23 SRA These milestones are calculated or fixed

Milestone NameMilestone DateNOTES
Avail StartWednesday, December 14, 2022
Crew Move AshoreWednesday, December 28, 2022
Move to KTR Facility

20% Open and Inspect Reports due Sunday, February 12, 2023

25% CONFERENCEWednesday, March 01, 2023Conference to be held on the next Wednesday following the date in Column C
50% CONFERENCEWednesday, May 17, 2023Conference to be held on the next Wednesday following the date in Column C
PCD TO SUPPORT CSELOWednesday, June 28, 2023
Command, Control, Communications, Computer, Combat (C5ILO)Tuesday, July 11, 2023
75% CONFERENCEWednesday, July 26, 2023Conference to be held on the next Wednesday following the date in Column C
Crew Move AboardMonday, August 07, 2023
Production Completion Date (PCD)Monday, August 14, 2023
Fuel ShipTBD
Light Off Assessment (Ship's Force) BeginTuesday, September 19, 2023
Light Off Assessment (Ship's Force) CompleteFriday, September 22, 2023
Work CompleteMonday, September 25, 2023
Dock TrialsThursday, September 28, 2023
Fast CruiseFriday, September 29, 2023
SEA TRIALS Start DateMonday, October 02, 2023
SEA TRIALS Completion DateFriday, October 06, 2023
Avail CertificationFriday, October 13, 2023
"Contract Complete" No Later than DateWednesday, November 08, 2023