This document contains a federal solicitation for ship repair and maintenance services. The solicitation is seeking proposals to execute the USS PORTLAND (LPD-27) Selected Restricted Availability for fiscal year 2023, scheduled from December 14, 2022 to November 8, 2023. Offerors must have the capability to complete all necessary labor, supervision, production, testing and quality assurance to prepare and accomplish the availability. The work will require coordination and integration of multiple maintenance, repair and modernization areas. The Naval Sea Systems Command will make a single award by October 2022 on a coast-wide basis without limiting performance to the ship's homeport. Offerors must be registered in the System for Award Management and include their Unique Entity Identifier with any request for verification of Department of Defense contractor status. References containing limiting distribution statements will require coordination with the technical librarian point of contact to arrange access.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Exec Milestones (Contractual) USS PORTLAND LPD-27 FY23 SRA These milestones are calculated or fixed
| Milestone Name | Milestone Date | NOTES |
| Avail Start | Wednesday, December 14, 2022 | |
| Crew Move Ashore | Wednesday, December 28, 2022 | |
| Move to KTR Facility |
20% Open and Inspect Reports due Sunday, February 12, 2023
| 25% CONFERENCE | Wednesday, March 01, 2023 | Conference to be held on the next Wednesday following the date in Column C |
| 50% CONFERENCE | Wednesday, May 17, 2023 | Conference to be held on the next Wednesday following the date in Column C |
| PCD TO SUPPORT CSELO | Wednesday, June 28, 2023 | |
| Command, Control, Communications, Computer, Combat (C5ILO) | Tuesday, July 11, 2023 | |
| 75% CONFERENCE | Wednesday, July 26, 2023 | Conference to be held on the next Wednesday following the date in Column C |
| Crew Move Aboard | Monday, August 07, 2023 | |
| Production Completion Date (PCD) | Monday, August 14, 2023 |
| Fuel Ship | TBD |
| Light Off Assessment (Ship's Force) Begin | Tuesday, September 19, 2023 |
| Light Off Assessment (Ship's Force) Complete | Friday, September 22, 2023 |
| Work Complete | Monday, September 25, 2023 |
| Dock Trials | Thursday, September 28, 2023 |
| Fast Cruise | Friday, September 29, 2023 |
| SEA TRIALS Start Date | Monday, October 02, 2023 |
| SEA TRIALS Completion Date | Friday, October 06, 2023 |
| Avail Certification | Friday, October 13, 2023 |
| "Contract Complete" No Later than Date | Wednesday, November 08, 2023 |