About this file

This document contains pricing tables for a five-year indefinite delivery, indefinite quantity contract for marine boatyard services and industrial support. The tables provide estimated pricing for labor, materials, storage, transportation and "over and above work" for boats up to 50 feet in length for base years one through five. The total estimated contract value is $12,403,295. Offerors are instructed to include material handling fee rates.

The related solicitation is for follow-on IDIQ contract N5523619R0008 to provide marine boatyard services and industrial support less than 50 feet for the Department of the Navy Naval Sea Systems Command. Services include maintenance, repair and overhaul of boats, boat trailers, craft, lighterage and service equipment.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SUMMARY

Marine Boatyard Services Lot 1 Summary
BASE YEAR 1$ 2,251,059.00
BASE YEAR 2$ 2,351,059.00
BASE YEAR 3$ 2,451,059.00
BASE YEAR 4$ 2,591,059.00
BASE YEAR 5$ 2,759,059.00
TOTAL$ 12,403,295.00

ORDERING PERIOD 1

APPENDIX APrime Contractor
Supplies/ServicesEstimated QuantityUnitUnit
PriceAmount
A001LABOR & MATERIALS
LABOR87,337MH$0.00
MATERIALS1,251,059U.S. DOLLARS$1,251,059.00
A002Boat Storage up to 30 feet or 9 meter in length50DAYS$0.00
A003Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length40DAYS$0.00
A004Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter50EA$0.00
A005Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter40EA$0.00
A006Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter50EA$0.00
A007Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter40EA$0.00
A008OVER AND ABOVE WORK - LOT 1, BASE YEAR 1
LABOR12,500MH$0.00
OT LABOR11,250MH$0.00
MATERIALS1,000,000U.S. DOLLARS$1,000,000.00
Total Estimate for Base Year 1$2,251,059.00
OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes.

ORDERING PERIOD 2

APPENDIX BPrime Contractor
Supplies/ServicesEstimated QuantityUnitUnit
PriceAmount
B001LABOR & MATERIALS
LABOR87,337MH$0.00
MATERIALS1,251,059U.S. DOLLARS$1,251,059.00
B002Boat Storage up to 30 feet or 9 meter in length50DAYS$0.00
B003Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length40DAYS$0.00
B004Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter50EA$0.00
B005Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter40EA$0.00
B006Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter50EA$0.00
B007Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter40EA$0.00
B008OVER AND ABOVE WORK - LOT 1, BASE YEAR 2
LABOR14,500MH$0.00
OT LABOR12,000MH$0.00
MATERIALS1,100,000U.S. DOLLARS$1,100,000.00
Total Estimate for Base Year 2$2,351,059.00
OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes.

ORDERING PERIOD 3

APPENDIX CPrime Contractor
Supplies/ServicesEstimated QuantityUnitUnit
PriceAmount
C001LABOR & MATERIALS
LABOR87,337MH$0.00
MATERIALS1,251,059U.S. DOLLARS$1,251,059.00
C002Boat Storage up to 30 feet or 9 meter in length50DAYS$0.00
C003Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length40DAYS$0.00
C004Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter50EA$0.00
C005Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter40EA$0.00
C006Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter50EA$0.00
C007Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter40EA$0.00
C008OVER AND ABOVE WORK - LOT 1, BASE YEAR 3
LABOR16,900MH$0.00
OT LABOR14,400MH$0.00
MATERIALS1,200,000U.S. DOLLARS$1,200,000.00
Total Estimate for Base Year 3$2,451,059.00
OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes.

ORDERING PERIOD 4

APPENDIX DPrime Contractor
Supplies/ServicesEstimated QuantityUnitUnit
PriceAmount
D001LABOR & MATERIALS
LABOR87,337MH$0.00
MATERIALS1,251,059U.S. DOLLARS$1,251,059.00
D002Boat Storage up to 30 feet or 9 meter in length50DAYS$0.00
D003Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length40DAYS$0.00
D004Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter50EA$0.00
D005Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter40EA$0.00
D006Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter50EA$0.00
D007Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter40EA$0.00
D008OVER AND ABOVE WORK - LOT 1, BASE YEAR 4
LABOR19,780MH$0.00
OT LABOR17,280MH$0.00
MATERIALS1,340,000U.S. DOLLARS$1,340,000.00
Total Estimate for Base Year 4$2,591,059.00
OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes.

ORDERING PERIOD 5

APPENDIX EPrime Contractor
Supplies/ServicesEstimated QuantityUnitUnit
PriceAmount
E001LABOR & MATERIALS
LABOR87,337MH$0.00
MATERIALS1,251,059U.S. DOLLARS$1,251,059.00
E002Boat Storage up to 30 feet or 9 meter in length50DAYS$0.00
E003Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length40DAYS$0.00
E004Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter50EA$0.00
E005Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter40EA$0.00
E006Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter50EA$0.00
E007Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter40EA$0.00
E008OVER AND ABOVE WORK - LOT 1, BASE YEAR 5
LABOR23,236MH$0.00
OT LABOR20,736MH$0.00
MATERIALS1,508,000U.S. DOLLARS$1,508,000.00
Total Estimate for Base Year 5$2,759,059.00
OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes.

File details come from the government source that posted it. Updated .