This document contains pricing tables for a five-year indefinite delivery, indefinite quantity contract for marine boatyard services and industrial support. The tables provide estimated pricing for labor, materials, storage, transportation and "over and above work" for boats up to 50 feet in length for base years one through five. The total estimated contract value is $12,403,295. Offerors are instructed to include material handling fee rates.
The related solicitation is for follow-on IDIQ contract N5523619R0008 to provide marine boatyard services and industrial support less than 50 feet for the Department of the Navy Naval Sea Systems Command. Services include maintenance, repair and overhaul of boats, boat trailers, craft, lighterage and service equipment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N5523619R0008 RFP Conformed - Amend 0002.docx | DOCX document | |
| N55236-19-R-0008 Amend 0002.pdf | ||
| N5523619R0008 RFP Conformed - Amend 0002.docx | DOCX document | |
| N55236-19-R-0008 Amend 0001.pdf | ||
| MBS LOT 1 FINAL CDRLS.pdf | ||
| Exhibit A-E - Supplies or Services and Prices.xls | XLS spreadsheet | |
| Attachment J-1.docx | DOCX document | |
| Attachment S2 - Request for Specification Clarification Form.doc | DOC document | |
| Attachment S1 - Reference Information Sheet.docx | DOCX document | |
| N5523619R0008 MBS LOT I RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY
| Marine Boatyard Services Lot 1 Summary | |
| BASE YEAR 1 | $ 2,251,059.00 |
| BASE YEAR 2 | $ 2,351,059.00 |
| BASE YEAR 3 | $ 2,451,059.00 |
| BASE YEAR 4 | $ 2,591,059.00 |
| BASE YEAR 5 | $ 2,759,059.00 |
| TOTAL | $ 12,403,295.00 |
ORDERING PERIOD 1
| APPENDIX A | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| A001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| A002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| A003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| A004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| A005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| A006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| A007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| A008 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 1 | |||||
| LABOR | 12,500 | MH | $0.00 | |||
| OT LABOR | 11,250 | MH | $0.00 | |||
| MATERIALS | 1,000,000 | U.S. DOLLARS | $1,000,000.00 | |||
| Total Estimate for Base Year 1 | $2,251,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
ORDERING PERIOD 2
| APPENDIX B | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| B001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| B002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| B003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| B004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| B005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| B006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| B007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| B008 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 2 | |||||
| LABOR | 14,500 | MH | $0.00 | |||
| OT LABOR | 12,000 | MH | $0.00 | |||
| MATERIALS | 1,100,000 | U.S. DOLLARS | $1,100,000.00 | |||
| Total Estimate for Base Year 2 | $2,351,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
ORDERING PERIOD 3
| APPENDIX C | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| C001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| C002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| C003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| C004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| C005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| C006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| C007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| C008 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 3 | |||||
| LABOR | 16,900 | MH | $0.00 | |||
| OT LABOR | 14,400 | MH | $0.00 | |||
| MATERIALS | 1,200,000 | U.S. DOLLARS | $1,200,000.00 | |||
| Total Estimate for Base Year 3 | $2,451,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
ORDERING PERIOD 4
| APPENDIX D | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| D001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| D002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| D003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| D004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| D005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| D006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| D007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| D008 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 4 | |||||
| LABOR | 19,780 | MH | $0.00 | |||
| OT LABOR | 17,280 | MH | $0.00 | |||
| MATERIALS | 1,340,000 | U.S. DOLLARS | $1,340,000.00 | |||
| Total Estimate for Base Year 4 | $2,591,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
ORDERING PERIOD 5
| APPENDIX E | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| E001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| E002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| E003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| E004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| E005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| E006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| E007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| E008 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 5 | |||||
| LABOR | 23,236 | MH | $0.00 | |||
| OT LABOR | 20,736 | MH | $0.00 | |||
| MATERIALS | 1,508,000 | U.S. DOLLARS | $1,508,000.00 | |||
| Total Estimate for Base Year 5 | $2,759,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |