Exhibit A-E - Supplies or Services and Prices.xls
XLS spreadsheet 63 KB Posted
- Solicitation number
- N5523619R0008
About this file
This document contains pricing tables for a multiple award indefinite delivery/indefinite quantity contract for marine boatyard services and industrial support. The tables provide estimated pricing for labor, materials, boat storage, transportation, travel expenses, and over and above work for five base ordering periods. The work will involve services for boats, boat trailers, craft, lighterage, service craft, or ancillary support equipment less than 15 meters or 50 feet in length for the Department of the Navy Naval Sea Systems Command. Offerors are instructed to include their material handling fee rates in highlighted cells.
The related federal contract opportunity is a follow-on IDIQ solicitation for the same marine boatyard services and industrial support work. The solicitation number is N5523619R0008 and it is being issued by the Department of the Navy Naval Sea Systems Command.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N5523619R0008 RFP Conformed - Amend 0002.docx | DOCX document | |
| N55236-19-R-0008 Amend 0002.pdf | ||
| N5523619R0008 RFP Conformed - Amend 0002.docx | DOCX document | |
| Exhibit A-E - Supplies or Services and Prices - Amendment 2.xls | XLS spreadsheet | |
| N55236-19-R-0008 Amend 0001.pdf | ||
| MBS LOT 1 FINAL CDRLS.pdf | ||
| Attachment J-1.docx | DOCX document | |
| Attachment S2 - Request for Specification Clarification Form.doc | DOC document | |
| Attachment S1 - Reference Information Sheet.docx | DOCX document | |
| N5523619R0008 MBS LOT I RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SUMMARY
| Marine Boatyard Services Lot 1 Summary | |
| BASE YEAR 1 | $ 2,376,059.00 |
| BASE YEAR 2 | $ 2,476,059.00 |
| BASE YEAR 3 | $ 2,576,059.00 |
| BASE YEAR 4 | $ 2,716,059.00 |
| BASE YEAR 5 | $ 2,884,059.00 |
| TOTAL | $ 13,028,295.00 |
ORDERING PERIOD 1
| APPENDIX A | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| A001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| A002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| A003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| A004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| A005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| A006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| A007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| A008 | Travel/Per Diem (for bidding purposes only) | 125,000 | U.S. DOLLARS | $125,000.00 | ||
| A009 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 1 | |||||
| LABOR | 12,500 | MH | $0.00 | |||
| OT LABOR | 11,250 | MH | $0.00 | |||
| MATERIALS | 1,000,000 | U.S. DOLLARS | $1,000,000.00 | |||
| Total Estimate for Base Year 1 | $2,376,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
ORDERING PERIOD 2
| APPENDIX B | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| B001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| B002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| B003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| B004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| B005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| B006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| B007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| B008 | Travel/Per Diem (for bidding purposes only) | 125,000 | U.S. DOLLARS | $125,000.00 | ||
| B009 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 2 | |||||
| LABOR | 14,500 | MH | $0.00 | |||
| OT LABOR | 12,000 | MH | $0.00 | |||
| MATERIALS | 1,100,000 | U.S. DOLLARS | $1,100,000.00 | |||
| Total Estimate for Base Year 2 | $2,476,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
ORDERING PERIOD 3
| APPENDIX C | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| C001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| C002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| C003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| C004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| C005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| C006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| C007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| C008 | Travel/Per Diem (for bidding purposes only) | 125,000 | U.S. DOLLARS | $125,000.00 | ||
| C009 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 3 | |||||
| LABOR | 16,900 | MH | $0.00 | |||
| OT LABOR | 14,400 | MH | $0.00 | |||
| MATERIALS | 1,200,000 | U.S. DOLLARS | $1,200,000.00 | |||
| Total Estimate for Base Year 3 | $2,576,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
ORDERING PERIOD 4
| APPENDIX D | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| D001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| D002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| D003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| D004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| D005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| D006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| D007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| D008 | Travel/Per Diem (for bidding purposes only) | 125,000 | U.S. DOLLARS | $125,000.00 | ||
| D009 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 4 | |||||
| LABOR | 19,780 | MH | $0.00 | |||
| OT LABOR | 17,280 | MH | $0.00 | |||
| MATERIALS | 1,340,000 | U.S. DOLLARS | $1,340,000.00 | |||
| Total Estimate for Base Year 4 | $2,716,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
ORDERING PERIOD 5
| APPENDIX E | Prime Contractor | |||||
| Supplies/Services | Estimated Quantity | Unit | Unit | |||
| Price | Amount | |||||
| E001 | LABOR & MATERIALS | |||||
| LABOR | 87,337 | MH | $0.00 | |||
| MATERIALS | 1,251,059 | U.S. DOLLARS | $1,251,059.00 | |||
| E002 | Boat Storage up to 30 feet or 9 meter in length | 50 | DAYS | $0.00 | ||
| E003 | Boat Storage 30 feet or 9 meter up to 50 feet or 15 meter in length | 40 | DAYS | $0.00 | ||
| E004 | Trailer/Haul boat/trailer from San Diego area to contractor's facility, shorter than 30 ft. or 9 meter | 50 | EA | $0.00 | ||
| E005 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, shorter than 30 ft. or 9 meter | 40 | EA | $0.00 | ||
| E006 | Trailer/Haul boat/trailer from San Diego area Naval Facilities area to contractor's facility, 30 ft. or 9 meter to 50 ft. or 15 meter | 50 | EA | $0.00 | ||
| E007 | Trailer/Haul boat/trailer from contractor's facility to San Diego area Naval Facilities area, 30 ft. or 9 meter to 50 ft. or 15 meter | 40 | EA | $0.00 | ||
| E008 | Travel/Per Diem (for bidding purposes only) | 125,000 | U.S. DOLLARS | $125,000.00 | ||
| E010 | OVER AND ABOVE WORK - LOT 1, BASE YEAR 5 | |||||
| LABOR | 23,236 | MH | $0.00 | |||
| OT LABOR | 20,736 | MH | $0.00 | |||
| MATERIALS | 1,508,000 | U.S. DOLLARS | $1,508,000.00 | |||
| Total Estimate for Base Year 5 | $2,884,059.00 | |||||
| OFFEROR: Please be sure to include your Material Handling Fee Rate in the Orange, Highlighted boxes. |
File details come from the government source that posted it. Updated .