N5523617R0012B
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
REF: FACILITIES SUPPORT SERVICES
The purpose of this modif ication is to answ er pre-proposal questions.
SEE CONTINUATION PAGE
1. CONTRACT ID CODE PAGE OF PAGES
1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Aug-2017
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N5523617R0012
X 9B. DATED (SEE ITEM 11)
02-Aug-2017
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Aug-2017
CODE
SOUTHWEST REGIONAL MAINTENANCE CENTER
CODE 410 3755 BRINSER STREET, STE 1
SAN DIEGO CA 92136-5205
N55236 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N5523617R0012
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
The following have been added by full text:
REQUESTS FOR SPECIFICATION CLARIFICATION
1) QUESTION: Volume II of the proposal instructions seeks only past performance on 6 SOW key areas of only one section (CNC, as part of the 3.4 Facilities Mechanical Support) of the entire scope. Is this the only portion of the scope that requires past experience?
RESPONSE: Section L, 2.0 Volume II, section 2.2 seeks past performance information for references identified on the Experience Matrix (Attachment S-2). Additionally, the six (6) SOW key areas address more than just one section of the SOW.
2) QUESTION: Is the prime required to have experience in all 6 of the specified key areas or can it be a combination of prime, sub, consultant that meets all 6 areas with past performance?
RESPONSE: It could be a combination; however, individual references may not be evaluated as equal in importance. For example, an offer with only one reference evaluated as being of the highest relevance, full breadth of experience across the entire spectrum of the specified SOW key areas, and very significant depth of experience with multiple work opportunities may receive an outstanding rating as compared to an offer with multiple references of lesser relevance which collectively demonstrate less breadth and depth of experience.
3) QUESTION: What are the DOL codes for the 6 areas pertaining to CNCs?
RESPONSE: Section L, 1.0 Volume I – Offer, section 1.1 provides required hours by labor categories.
However, in the event that an offeror's labor category designations do not align precisely with the
Government labor category designations, it may use its own labor category designations and provide a cross reference to the Government-defined labor categories.
4) QUESTION: How is the entire SOW to be addressed in the proposal?
RESPONSE: An offeror’s capability will be assessed using the submissions required by Section L.
5) QUESTION: How many parts will be manufactured each contract year utilizing the CNC?
RESPONSE: This contract is for the provision of hours as stated in Section B. The number of parts manufactured per year is not relevant.
(End of Summary of Changes)