J-3 Commencement and Completion Milestones USNS NARRAGANSETT (TSV-4) Revised.pdf

PDF 347 KB Posted

Attached to
NARRAGANSETT (TSV-4).
Solicitation number
N5005422R0001
Issued by

About this file

This document outlines the commencement and completion milestones for the NARRAGANSETT (TSV-4) availability. Key details include commencement on July 11, 2022 with completion scheduled for April 6, 2023. Specific milestones are defined such as 20% open and inspect by September 16, 2022, undocking by February 24, 2023, and production complete by March 27, 2023. The solicitation requests proposals for a fixed-price contract to complete the FY22 docking phased maintenance availability for NARRAGANSETT (TSV-4) with the intent to award to the best value offer. This is a small business set-aside with a NAICS code of 336611. The vessel will be available for inspection January 3-15, 2022. Questions regarding inspections should be directed to the listed Navy contacts.

View the file

Other files

File Type Posted
N5005422R0001 Amendment 10 Conformed Copy.pdf PDF
N5005422R0001 Amendment 10.pdf PDF
N5005422R0001_Amendment 9_conformed.pdf PDF
N5005422R0001 Amendment 9.pdf PDF
S_7_Request_for_Specification_Clarification_Q 1-100.xlsx XLSX spreadsheet
S_7_Request_for_Specification_Clarification_Q 1-96.xlsx XLSX spreadsheet
N5005422R0001_Amendment 8_conformed.pdf PDF
N5005422R0001 Amendment 8.pdf PDF
N5005422R0001 Amendment 7.pdf PDF
N5005422R0001_Amendment 7_conformed.pdf PDF
N5005422R0001_Amendment 6 _conformed.pdf PDF
S_7_Request_for_Specification_Clarification_Q 1-93 rev.xlsx XLSX spreadsheet
N5005422R0001 Amendment 6.pdf PDF
N5005422R0001 Amendment 5.pdf PDF
N5005422R0001 Amendment 4.pdf PDF
S_7_Request_for_Specification_Clarification_Q 1-63.xlsx XLSX spreadsheet
N5005422R0001 Amendment 0003.pdf PDF
S_7_Request_for_Specification_Clarification_Q 1-45 Rev.xlsx XLSX spreadsheet
S_7_Request_for_Specification_Clarification_Q 1-45.xlsx XLSX spreadsheet
NARRAGANSETT Amendment 0001.pdf PDF
NARRAGANSETT Amendment 0002.pdf PDF
Attachment S-8 DBIDS.pdf PDF
Attachment S-10 SHIP ACCESS FORM.xlsx XLSX spreadsheet
NARRAGANSETT (TSV-4) SOLICITATION N5005422R0001.pdf PDF
J-5 Quality Assurance Surveillance Plan (QASP) USNS NARRAGANSETT (TSV-4) DPMA update.docx DOCX document
Attachment S-6 - Annual Representations and Certifications.pdf PDF
Attachment S-9 Ship Access Request Instructions.docx DOCX document
Attachment S-2_Past Performance_CPARS_Reference_List.docx DOCX document
Attachment S-3_Past_Performance_Questionnaire.docx DOCX document
Attachment S-4 Pier_and_Drydock_Graphical_Representation_Template.xlsx XLSX spreadsheet
Attachment S-11 FORM 889.pdf PDF
Attachment S-1 Manpower_Utilization_Data_Sheet.xlsx XLSX spreadsheet
Attachment S-7 Request for Specification Clarification.xlsx XLSX spreadsheet
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment J-3 Commencement & Completion Dates and Milestones

CLIN VESSEL COMMENCEMENT COMPLETION

USNS HUNTERNARRAGANSETT 07/11/2022 04/06/2023

USNS HUNTER

MILESTONE DATE REVISED

Avail Start 507/1119/2022

07/18/20221

Defuel 07/13/ 5/21/20221 07/20/2022

Start Crew Move Ashore 07/13/5/21/20221

07/20/2022

Docking 08/055/28/2022

08/12/20220

20% Open and Inspect 609/09/03/20221

09/16/2022

25% Conference 09/166/7/20221

09/23/2022

50% Conference 611/22/25/20212

11/22/2022

Combat Systems Suit Equipment Light Off (CSSELO) N/A N/A

C5ILO (AEGIS LIGHT-OFF) N/A N/A

Undocking 7/1302/17/2023

02/24/20231

Production Complete Date (PCD) 03/20/7/20/2023

03/27/20231

75% Conference 7/1403/27//2023

04/03/20231

Start Crew Move Aboard 7/2303/27/2023

04/03/20231

Refuel 03/227/21/2023 03/29/2023

Work Complete 03/27/2023 04/03/2023

Start and Completion of Propulsion System Light Off 7/2303/30/2023 04/06/2023

Formatted: Underline

Formatted: Highlight

Formatted: Highlight

Formatted: Highlight

Formatted: Highlight

Attachment J-3 Commencement & Completion Dates and Milestones

Start and Completion of Dock Trials 7/2704/03/20213 04/10/2023

Start and Completion of Fast Cruise 704/03/27/2023 04/10/20231

Crew Rest

Start and Completion of Sea Trials 04/057/30/2023 04/12/20231

Availability completion 804/06/2/2023

04/13/20231