Exhibits_A-E.xlsx

XLSX spreadsheet 44 KB Posted

Attached to
Fire Watch and Tank Watch Solicitation
Solicitation number
N5005414R0006
Issued by

About this file

Subject document is the Conformed Exhibits A-E spreadsheet as detailed in the Bidder's Questions within Amendment 0005.

View the file

Other files

File Type Posted
FIRETANKWATCH_CONFORMED_AMEND0006.docx DOCX document
FIRETANKWATCH_AMEND0006.docx DOCX document
FIRETANKWATCH_CONFORMED_AMEND0005.doc DOC document
FIRETANKWATCH_AMEND0005.doc DOC document
FIRETANKWATCH_AMEND0004.doc DOC document
FIRETANKWATCH_AMEND0003.docx DOCX document
Attachment J14 - PPI Rev.doc DOC document
FIRETANKWATCH_AMEND0002.docx DOCX document
J-14 Past Performance Info Survey.REV.docx DOCX document
J-1 CDRLs.pdf PDF
FIRETANKWATCH_AMEND0001.docx DOCX document
FIRETANKWATCH_SOLIT_AMEND0001.docx DOCX document
J-16 DD254.pdf PDF
ATTACH 1- Fire-Tank Watch Timesheet_Form.pdf PDF
J-12 Capacity Eval Form.doc DOC document
Exhibits A-E.xlsx XLSX spreadsheet
J-5 042-007 - 16 JUN 14.pdf PDF
N50054-14-R-0006.docx DOCX document
J-10 042-037 - 16 JUN 14.pdf PDF
J-7 042-011 - 16 JUN 14.pdf PDF
J-15 Bidders' Questions Form.doc DOC document
J-3 042-005 - 16 JUN 14.pdf PDF
J-9 042-026 - 16 JUN 14.pdf PDF
J-13 PastPerformanceReferenceList.doc DOC document
J-14 Past Performance Info Survey.doc.docx DOCX document
J-8 042-022 - 16 JUN 14.pdf PDF
J-6 042-008 - 16 JUN 14.pdf PDF
J-4 042-006 - 16 JUN 14.pdf PDF
J-2 042-002 - 16 JUN 14.pdf PDF
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Base Year Effort

Contractor Name
Supplies/ServicesEst QtyUnitUnit
PriceAmount

A 101 Composite labor rate for fire watch/tank watch support (non-red badge) 88,596 HR $0.00

A 102 Composite labor rate for fire watch/tank watch support (non-red badge) (OT) 11,216 HR $0.00

A 103 Composite labor rate for fire watch/tank watch support (red badge) 115,972 HR $0.00

A 104 Composite labor rate for fire watch/tank watch support (red badge) (OT) 8,446 HR $0.00

A 105 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) 10,098 HR $0.00

A 106 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) (OT) 2,842 HR $0.00

A 107 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) 21,692 HR $0.00

A 108 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) (OT) 5,161 HR $0.00

A 109 Adjustment for fire watch/tank watch work to be accomplished outside of Norfolk Naval Shipyard (NNSY). Offeror to submit a percentage. (See Note 6) 300,000 U.S. DOLLARS $0.00

A 110 Material (for bidding purposes only) (See Note 7) 4,500 U.S. DOLLARS $1.00 $4,500.00

A111Material G&A Handling (Contractor to submit a percentage.) (See Note 8)$4,500X$0.00
In negotiating the fixed price for materials, the contractor shall submit quotes or invoics for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the material G&A/Handling ELIN. All material handling charges are included in the material G&A/Handling ELIN.

A 112 Contract Data Requirements (Form DD-1423) NSP

Total Estimate for Base Year No Bid

NOTE 1: Proposed prices for each line item are to be fully burdened to include all direct and indirect costs, labor, program management, subcontractors, services, overhead, material (except consumable material in ELIN 110), holidays, profit, and to include work and costs to implement Cat I and II NAVSEA Standard Items (NSIs), Local Work Templates (LWTs), Standard Work Templates (SWTs), and CDRLs.

NOTE 2: Subcontract effort shall not be priced as material or considered as part of the material pools.

NOTE 3: Overtime is due after 40 hours per week.

NOTE 4: The composite labor rate covers work performed on 1st, 2nd, or 3rd shift. It is anticipated that approximately 60% of the work will be on 1st shift, 30% on 2nd shift, and 10% on third shift.

NOTE 5: On-site supervision is to include only the direct on-site supervision. It is not to include any program management or supervision above the direct on-site supervision level.

NOTE 6: Offerors are to submit a percentage for ELIN 109. ELIN 109 will only be used on individual task orders when work is required outside NNSY. NSSA will use the submitted percentage rate and apply it to the applicable ELIN prices which will represent the additional cost associated with performing work outside NNSY.

NOTE 7: ELIN 110 is to include only consumable material. It is not to include the materials listed in Section C, Paragraph C.2.4 - Contractor Proivded Materials.

NOTE 8: In negotiating the cost for materials, the contractor shall submit quotes or invoices for the material required. The negotiated cost for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN.

&"Arial,Bold" SOLICITATION N50054-14-R-0006

EXHIBIT A

&"Arial,Regular" &"Arial,Bold"SUPPLIES OR SERVICES AND PRICES

BASE YEAR EFFORT

Second Yr (Option I)

Contractor Name
Supplies/ServicesEst QtyUnitUnit
PriceAmount

B 101 Composite labor rate for fire watch/tank watch support (non-red badge) 73,830 HR $0.00

B 102 Composite labor rate for fire watch/tank watch support (non-red badge) (OT) 9,347 HR $0.00

B 103 Composite labor rate for fire watch/tank watch support (red badge) 96,644 HR $0.00

B 104 Composite labor rate for fire watch/tank watch support (red badge) (OT) 7,038 HR $0.00

B 105 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) 8,415 HR $0.00

B 106 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) (OT) 2,369 HR $0.00

B 107 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) 18,077 HR $0.00

B 108 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) (OT) 4,301 HR $0.00

B 109 Adjustment for fire watch/tank watch work to be accomplished outside of Norfolk Naval Shipyard (NNSY). Offeror to submit a percentage. (See Note 6) 300,000 U.S. DOLLARS $0.00

B 110 Material (for bidding purposes only) (See Note 7) 3,750 U.S. DOLLARS $1.00 $3,750.00

B111Material G&A Handling (Contractor to submit a percentage.) (See Note 8)$3,750X$0.00
In negotiating the fixed price for materials, the contractor shall submit quotes or invoics for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the material G&A/Handling ELIN. All material handling charges are included in the material G&A/Handling ELIN.

B 112 Contract Data Requirements (Form DD-1423) NSP

Total Estimate for Second Year (Option I) No Bid

NOTE 1: Proposed prices for each line item are to be fully burdened to include all direct and indirect costs, labor, program management, subcontractors, services, overhead, material (except consumable material in ELIN 110), holidays, profit, and to include work and costs to implement Cat I and II NAVSEA Standard Items (NSIs), Local Work Templates (LWTs), Standard Work Templates (SWTs), and CDRLs.

NOTE 2: Subcontract effort shall not be priced as material or considered as part of the material pools.

NOTE 3: Overtime is due after 40 hours per week.

NOTE 4: The composite labor rate covers work performed on 1st, 2nd, or 3rd shift. It is anticipated that approximately 60% of the work will be on 1st shift, 30% on 2nd shift, and 10% on third shift.

NOTE 5: On-site supervision is to include only the direct on-site supervision. It is not to include any program management or supervision above the direct on-site supervision level.

NOTE 6: Offerors are to submit a percentage for ELIN 109. ELIN 109 will only be used on individual task orders when work is required outside NNSY. NSSA will use the submitted percentage rate and apply it to the applicable ELIN prices which will represent the additional cost associated with performing work outside NNSY.

NOTE 7: ELIN 110 is to include only consumable material. It is not to include the materials listed in Section C, Paragraph C.2.4 - Contractor Proivded Materials.

NOTE 8: In negotiating the cost for materials, the contractor shall submit quotes or invoices for the material required. The negotiated cost for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN.

EXHIBIT B

SUPPLIES OR SERVICES AND PRICES

SECOND YEAR EFFORT (OPTION I)

Third Yr (Option II)

Contractor Name
Supplies/ServicesEst QtyUnitUnit
PriceAmount

C 101 Composite labor rate for fire watch/tank watch support (non-red badge) 73,830 HR $0.00

C 102 Composite labor rate for fire watch/tank watch support (non-red badge) (OT) 9,347 HR $0.00

C 103 Composite labor rate for fire watch/tank watch support (red badge) 96,644 HR $0.00

C 104 Composite labor rate for fire watch/tank watch support (red badge) (OT) 7,038 HR $0.00

C 105 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) 8,415 HR $0.00

C 106 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) (OT) 2,369 HR $0.00

C 107 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) 18,077 HR $0.00

C 108 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) (OT) 4,301 HR $0.00

C 109 Adjustment for fire watch/tank watch work to be accomplished outside of Norfolk Naval Shipyard (NNSY). Offeror to submit a percentage. (See Note 6) 300,000 U.S. DOLLARS $0.00

C 110 Material (for bidding purposes only) (See Note 7) 3,750 U.S. DOLLARS $1.00 $3,750.00

C111Material G&A Handling (Contractor to submit a percentage.) (See Note 8)$3,750X$0.00
In negotiating the fixed price for materials, the contractor shall submit quotes or invoics for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the material G&A/Handling ELIN. All material handling charges are included in the material G&A/Handling ELIN.

C 112 Contract Data Requirements (Form DD-1423) NSP

Total Estimate for Third Year (Option II) No Bid

NOTE 1: Proposed prices for each line item are to be fully burdened to include all direct and indirect costs, labor, program management, subcontractors, services, overhead, material (except consumable material in ELIN 110), holidays, profit, and to include work and costs to implement Cat I and II NAVSEA Standard Items (NSIs), Local Work Templates (LWTs), Standard Work Templates (SWTs), and CDRLs.

NOTE 2: Subcontract effort shall not be priced as material or considered as part of the material pools.

NOTE 3: Overtime is due after 40 hours per week.

NOTE 4: The composite labor rate covers work performed on 1st, 2nd, or 3rd shift. It is anticipated that approximately 60% of the work will be on 1st shift, 30% on 2nd shift, and 10% on third shift.

NOTE 5: On-site supervision is to include only the direct on-site supervision. It is not to include any program management or supervision above the direct on-site supervision level.

NOTE 6: Offerors are to submit a percentage for ELIN 109. ELIN 109 will only be used on individual task orders when work is required outside NNSY. NSSA will use the submitted percentage rate and apply it to the applicable ELIN prices which will represent the additional cost associated with performing work outside NNSY.

NOTE 7: ELIN 110 is to include only consumable material. It is not to include the materials listed in Section C, Paragraph C.2.4 - Contractor Proivded Materials.

NOTE 8: In negotiating the cost for materials, the contractor shall submit quotes or invoices for the material required. The negotiated cost for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN.

EXHIBIT C

THIRD YEAR EFFORT (OPTION II)

Fourth Yr (Option III)

Contractor Name
Supplies/ServicesEst QtyUnitUnit
PriceAmount

D 101 Composite labor rate for fire watch/tank watch support (non-red badge) 88,596 HR $0.00

D 102 Composite labor rate for fire watch/tank watch support (non-red badge) (OT) 11,216 HR $0.00

D 103 Composite labor rate for fire watch/tank watch support (red badge) 115,972 HR $0.00

D 104 Composite labor rate for fire watch/tank watch support (red badge) (OT) 8,446 HR $0.00

D 105 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) 10,098 HR $0.00

D 106 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) (OT) 2,842 HR $0.00

D 107 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) 21,692 HR $0.00

D 108 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) (OT) 5,161 HR $0.00

D 109 Adjustment for fire watch/tank watch work to be accomplished outside of Norfolk Naval Shipyard (NNSY). Offeror to submit a percentage. (See Note 6) 300,000 U.S. DOLLARS $0.00

D 110 Material (for bidding purposes only) (See Note 7) 4,500 U.S. DOLLARS $1.00 $4,500.00

D111Material G&A Handling (Contractor to submit a percentage.) (See Note 8)$4,500X$0.00
In negotiating the fixed price for materials, the contractor shall submit quotes or invoics for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the material G&A/Handling ELIN. All material handling charges are included in the material G&A/Handling ELIN.

D 112 Contract Data Requirements (Form DD-1423) NSP

Total Estimate for Fourth Year (Option III) No Bid

NOTE 1: Proposed prices for each line item are to be fully burdened to include all direct and indirect costs, labor, program management, subcontractors, services, overhead, material (except consumable material in ELIN 110), holidays, profit, and to include work and costs to implement Cat I and II NAVSEA Standard Items (NSIs), Local Work Templates (LWTs), Standard Work Templates (SWTs), and CDRLs.

NOTE 2: Subcontract effort shall not be priced as material or considered as part of the material pools.

NOTE 3: Overtime is due after 40 hours per week.

NOTE 4: The composite labor rate covers work performed on 1st, 2nd, or 3rd shift. It is anticipated that approximately 60% of the work will be on 1st shift, 30% on 2nd shift, and 10% on third shift.

NOTE 5: On-site supervision is to include only the direct on-site supervision. It is not to include any program management or supervision above the direct on-site supervision level.

NOTE 6: Offerors are to submit a percentage for ELIN 109. ELIN 109 will only be used on individual task orders when work is required outside NNSY. NSSA will use the submitted percentage rate and apply it to the applicable ELIN prices which will represent the additional cost associated with performing work outside NNSY.

NOTE 7: ELIN 110 is to include only consumable material. It is not to include the materials listed in Section C, Paragraph C.2.4 - Contractor Proivded Materials.

NOTE 8: In negotiating the cost for materials, the contractor shall submit quotes or invoices for the material required. The negotiated cost for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN.

EXHIBIT D

FOURTH YEAR EFFORT (OPTION III)

Fifth Yr (Option IV)

Contractor Name
Supplies/ServicesEst QtyUnitUnit
PriceAmount

E 101 Composite labor rate for fire watch/tank watch support (non-red badge) 59,064 HR $0.00

E 102 Composite labor rate for fire watch/tank watch support (non-red badge) (OT) 7,477 HR $0.00

E 103 Composite labor rate for fire watch/tank watch support (red badge) 77,315 HR $0.00

E 104 Composite labor rate for fire watch/tank watch support (red badge) (OT) 5,630 HR $0.00

E 105 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) 6,732 HR $0.00

E 106 Composite labor rate for fire watch/tank watch on-site supervisor (non-red badge) (OT) 1,895 HR $0.00

E 107 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) 14,461 HR $0.00

E 108 Composite labor rate for fire watch/tank watch on-site supervisor (red badge) (OT) 3,440 HR $0.00

E 109 Adjustment for fire watch/tank watch work to be accomplished outside of Norfolk Naval Shipyard (NNSY). Offeror to submit a percentage. (See Note 6) 300,000 U.S. DOLLARS $0.00

E 110 Material (for bidding purposes only) (See Note 7) 3,000 U.S. DOLLARS $1.00 $3,000.00

E111Material G&A Handling (Contractor to submit a percentage.) (See Note 8)$3,000X$0.00
In negotiating the fixed price for materials, the contractor shall submit quotes or invoics for the material required. The negotiated price for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the material G&A/Handling ELIN. All material handling charges are included in the material G&A/Handling ELIN.

E 112 Contract Data Requirements (Form DD-1423) NSP

Total Estimate for Fifth Year (Option IV) No Bid

Total Estimate - All Years No Bid

NOTE 1: Proposed prices for each line item are to be fully burdened to include all direct and indirect costs, labor, program management, subcontractors, services, overhead, material (except consumable material in ELIN 110), holidays, profit, and to include work and costs to implement Cat I and II NAVSEA Standard Items (NSIs), Local Work Templates (LWTs), Standard Work Templates (SWTs), and CDRLs.

NOTE 2: Subcontract effort shall not be priced as material or considered as part of the material pools.

NOTE 3: Overtime is due after 40 hours per week.

NOTE 4: The composite labor rate covers work performed on 1st, 2nd, or 3rd shift. It is anticipated that approximately 60% of the work will be on 1st shift, 30% on 2nd shift, and 10% on third shift.

NOTE 5: On-site supervision is to include only the direct on-site supervision. It is not to include any program management or supervision above the direct on-site supervision level.

NOTE 6: Offerors are to submit a percentage for ELIN 109. ELIN 109 will only be used on individual task orders when work is required outside NNSY. NSSA will use the submitted percentage rate and apply it to the applicable ELIN prices which will represent the additional cost associated with performing work outside NNSY.

NOTE 7: ELIN 110 is to include only consumable material. It is not to include the materials listed in Section C, Paragraph C.2.4 - Contractor Proivded Materials.

NOTE 8: In negotiating the cost for materials, the contractor shall submit quotes or invoices for the material required. The negotiated cost for materials shall be the quote or invoice price submitted by the contractor for actual materials plus transportation charges, both subject to verification by the Government as to reasonableness. The Government will not pay any material handling charges under the material ELIN. All material handling charges are included in the Material G&A/Handling ELIN.

EXHIBIT E

FIFTH YEAR EFFORT (OPTION IV)

Totals

Contractor Name
Supplies/ServicesEst QtyUnitUnit
PriceAmount
1001BASE YEAR EFFORT
REFERENCE EXHIBIT A - BASE YEAR EFFORTNo BidUS DOLLARS$1.00No Bid
100101As a matter of Navy Accounting
100102As a matter of Navy Accounting
2001OPTION I - SECOND YEAR EFFORT
REFERENCE EXHIBIT B - OPTION 1 - SECOND YEAR EFFORTNo BidUS DOLLARS$1.00No Bid
200101As a matter of Navy Accounting
200102As a matter of Navy Accounting
3001OPTION II - THIRD YEAR EFFORT
REFERENCE EXHIBIT C - OPTION 2 - THIRD YEAR EFFORTNo BidUS DOLLARS$1.00No Bid
300101As a matter of Navy Accounting
300102As a matter of Navy Accounting
4001OPTION III - FOURTH YEAR EFFORT
REFERENCE EXHIBIT D - OPTION 3 - FOURTH YEAR EFFORTNo BidUS DOLLARS$1.00No Bid
400101As a matter of Navy Accounting
400102As a matter of Navy Accounting
5001OPTION IV - FIFTH YEAR EFFORT
REFERENCE EXHIBIT E - OPTION 4 - FIFTH YEAR EFFORTNo BidUS DOLLARS$1.00No Bid
500101As a matter of Navy Accounting
500102As a matter of Navy Accounting
NOTE: SUBCLINs added for purposes of Navy accounting are included to accommodate electronic contracting system. Contractors are to disregard for pricing purposes.

TOTAL $0.00

SOLICITATION N50054-14-R-0006

Page B-&P

SECTION B SUPPLIES OR SERVICES AND PRICES

File details come from the government source that posted it. Updated .