Questions and Answers 6.15.2023.pdf
PDF 242 KB Posted
- Attached to
- District Craft Preservation IDIQ-MAC Federal contract opportunity
- Solicitation number
- N4523A-23-R-0308
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Questions and Answers 6.20.2023.pdf | ||
| IDIQ 5 Year Boat delivery Plan.xlsx | XLSX spreadsheet | |
| Questions and Answers 6.9.2023.pdf | ||
| C04.0 Attachment J-1 Revision 1 STATEMENT OF WORK IDIQ 2023.pdf | ||
| C06.0 Solicitation N4523A23R0308.pdf | ||
| Attachment J-3 Request for Clarification Form.doc | DOC document | |
| Attachment J-7 QASP.pdf | ||
| Attachment J-4 Contract Performance Data Sheet.docx | DOCX document | |
| Attachment J-5 Boat Specs.pdf | ||
| Attachment J-1 Statement of Work.pdf | ||
| Attachment J-2 Corporate Experience Data Sheet.docx | DOCX document | |
| Attachment J-6 Data Item Description CFR DI-MGMT-81648.pdf | ||
| Exhibit A CDRL A001 CFR DI-MGMT-81648 Signed.pdf |
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions & Answers Revision #2
Question #1 (Received 07 June 2023) - Can we request the drawings referenced in TABLE 1 - CONSOLIDATED LIST OF REFERENCES in the statement of work?
Answer #1 (Provided 09 June 2023) – Table 1 - CONSOLIDATED LIST OF REFERENCES contained three (3) incorrect line items (see below).
Line items 21, 22, and 23 listed above do not apply and have been removed from the Statement of Work. Please visit SAM.Gov to view the revised Statement of Work.
Question #2 (Received 07 June 2023) - CLIN 0047 identifies the vessel #32OP9401 (UB-14). Can the Government confirm that this vessel is to be classified as a Utility Boat for pricing purposes?
Answer #2 (Provided 09 June 2023) - This boat is classified by our TYCOM as a Utility Boat IAW our current SABAR (Service Craft and Boat Allowance Report) report as noted below.
Question #3 (Received 13 June 2023) - If using sub-contractors for all work under contract, does the prime have sub-contractors fill out J-2 and J-4 sheets as well as the prime contractor?
Answer #3 (Provided 15 June 2023) – No, It is not necessary to have subcontractors fill out additional J-2 and J-4 sheets.
Continued
Question #4 (Received 13 June 2023) - Can the Government specify which boats will be worked on in Year 1, Year 2, Year 3, Year 4, & Year 5? For bidding purposes, we need to account for inflation on all Year 2 – Year 5 work.
If this is not possible, please advise how you would like to see the added cost identified for Year 2 – Year 5.
Answer #4 (Provided 15 June 2023) - Please visit Sam.Gov to view uploaded file for 5 year delivery plan.
Question #5 (Received 13 June 2023) - Can the Government provide photos of the various sizes / configurations of the vessels for pricing purposes?
Answer #5 (Provided 15 June 2023) – Steps are being taken to release photos. All offerors will be updated promptly once photos have been vetted through our Public Affairs Office. Once released, photos will be posted to SAM.Gov.
Photo
Continued