REQUEST FOR SPECIFICATION CLARIFICATION
DATE OF REQUEST: 12/19/18 QUESTION NO: 005
REQUIREMENT: Price Proposal Breakdown REQUISITION NO.: N4523A19R1067
ITEM NO: N/A
TITLE: N/A
ISSUING OFFICE POC (CODE 440.22):
Brittany Chartier:
Brittany.chartier@navy.mil
PARA. NO: PAGE NO: CONTRACTOR
PLANNER’S NAME: ATTACH. NO: J-2 CONTRACTOR POC & PHONE:
CONTRACTOR QUESTION:
The revised Price Proposal Breakdown for this project includes a line for 3.2.8 Skeg Inspection/ Repairs.
We cannot seem to locate this item in the SOW. Are we to complete this work item? If so, can you provide a description for work?
DO NOT WRITE BELOW THIS LINE
SPEC CHG: Y/N DWG/REF CHG. Y/N RQMTS CHG: Y/N MAT'L CHG: Y/N
TECHNICAL REVIEW: BESAW SERIAL NO:
Skeg inspections/repairs are no longer a work item and line item “3.2.8” has been removed from the price proposal breakdown. An amendment with a revised J-2 is forthcoming.
ALL REQUESTS FOR CLARIFICATION MUST BE RECEIVED BY THE ISSUING OFFICE POC NO
LATER THAN THE DATE & TIME IDENTIFIED IN THE REQUEST FOR PROPOSAL.
DATE OF REQUEST: 12/14/18 QUESTION NO: 003
REQUIREMENT: MAIN DECK REPAIRS REQUISITION NO.: N4523A19R1067
ITEM NO: 3.5.1
TITLE: Main Deck Non-Skid Repair
ISSUING OFFICE POC (CODE 440.22):
PARA. NO: PAGE NO: 36 CONTRACTOR:
PLANNER’S NAME: ATTACH. NO: J-1 CONTRACTOR POC & PHONE
CONTRACTOR QUESTION:
What are the existing coatings on the main deck? Is this the same coating that is on the Deck House Level and Pilot House Deck?
DO NOT WRITE BELOW THIS LINE
The existing coatings in regards to the Main Deck are unknown.
With the existing Main Deck coating(s) being an unknown, the existing coating(s) in regards to the Deck House and Pilot House are unknown.
DATE OF REQUEST: 12/14/18 QUESTION NO: 004
REQUIREMENT: SUPERSTRUCTURE REQUISITION NO.: N4523A19R1067
ITEM NO: 3.6.6
TITLE: Mast Exterior Preservation
ISSUING OFFICE POC (CODE 440.22):
PARA. NO: PAGE NO: 44 CONTRACTOR:
PLANNER’S NAME: ATTACH. NO: J-1 CONTRACTOR POC & PHONE:
CONTRACTOR QUESTION:
Is the mast able to be removed for preservation purposes?
DO NOT WRITE BELOW THIS LINE
Based on the information booklet for this craft, the mast is flanged at the very bottom, and the angled support stanchions are also flanged. It is noted from the craft operator that the electrical cables for mast equipment on this do not have disconnects and cables go directly through penetrations into the boat. It is not desired to have splices or couples external of the ship, so all cables would have to be hard disconnected from the equipment or pulled through penetrations as cutting cables, splicing, or coupling them is not acceptable.