SWFPAC_SV64_Engine_Overhaul_and_LCM_-_Plain_Language_6AUG2018.docx

DOCX document 22 KB Posted

Attached to
SV64 Engine Overhaul and Life Cycle Maintenance
Solicitation number
N4523A18Q1055
Issued by

About this file

Plain Language document for solicitation.

View the file

Other files

File Type Posted
RFC4_Response.doc DOC document
RFC2_Response.doc DOC document
RFC3_Response.doc DOC document
SOW_References_30-50.zipx ZIPX file
N4523A18Q1055_SV64_Engine_Overhaul_and_LCM_-_Amendment_0002.pdf PDF
SOW_References_21-28_52-54_57_58.zipx ZIPX file
Attachment_J-1_SOW_SV64_Engine_Overhaul_and_LCM_dated_9AUG2018.docx DOCX document
SOW_Enclosures.zip ZIP file
RFC1_Response.doc DOC document
SOW_References_55_and_56.zipx ZIPX file
N4523A18Q1055_SV64_Engine_Overhaul_and_LCM_-_Amendment_0001.pdf PDF
Attachment_J-1_SOW_SV64_Engine_Overhaul_and_LCM_dated_26JULY2018.docx DOCX document
Attachment_J-9_Wage_Determination_(Island_and_San_Juan_County)_17JULY2018.pdf PDF
Attachment_J-14_Wage_Determination_(Skagit_County)_17JULY2018.pdf PDF
Attachment_J-10_Wage_Determination_(King_and_Snohomish_County)_17JULY2018.pdf PDF
Attachment_J-3_Area_of_Consideration.pdf PDF
Attachment_J-12_Wage_Determination_(Grays_Harbor_and_Mason_County)_17JULY2018.pdf PDF
Attachment_J-1_SOW_SV64_Engine_Overhaul_and_LCM_dated_16JULY2018.docx DOCX document
Attachment_J-15_Wage_Determination_(Thurston_County)_17JULY2018.pdf PDF
N4523A18Q1055_SV64_Engine_Overhaul_and_LCM.pdf PDF
Attachment_J-6_Corporate_Experience_Data_Sheet.docx DOCX document
Attachment_J-2_GFP_Attachment.pdf PDF
Attachment_J-13_Wage_Determination_(Pierce_County)_17JULY2018.pdf PDF
Attachment_J-17_Pricing_Worksheet.xlsx XLSX spreadsheet
Attachment_J-4_Request_for_Clarification_Form.doc DOC document
Attachment_J-8_Wage_Determination_(Clallam_and_Jefferson_County)_17JULY2018.pdf PDF
Attachment_J-5_Contract_Performance_Data_Sheet.docx DOCX document
Attachment_J-11_Wage_Determination_(Kitsap_County)_17JULY2018.pdf PDF
Attachment_J-16_Wage_Determination_(Whatcom_County)_17JULY2018.pdf PDF
Attachment_J-7_BAVR_Instructions.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Plain Language Document for SWFPAC SV-64 Engine Overhaul and Life Cycle Maintenance N4523A18Q1055

The purpose of this document is to describe the subject requirement in plain language in order to assist with and highlight the complexity/coordination required. In the event of any conflict between this document and the solicitation, the solicitation shall take precedence.

The Government requires various tasks to be completed on each of six (6), 64-foot Screening Vessels (SV). The requirements outlined in the Statement of Work (SOW) are to be done on each vessel, and each vessel’s work will be completed under the contract in a sequential manner:

1) Each delivery order will specify the vessel(s) and the periods of performance for the requirement. Exact periods of performance will be set by mutual agreement depending on vessel availability; however, they will all occur within the overall ordering period of the base IDIQ contract.

2) Each vessel will be delivered to the awardee by the Government to begin work. Upon delivery of the vessel, the Government will conduct sea trials to demonstrate operational performance of the vessel. The awardee will provide a water source for engine circulation during this operation.

3) Once accepted, the Contractor will have the identified timeline for accomplishing the requirements of the particular vessel. Timelines are identified as follows:

a. The awardee will be given 120-days to complete an entire work package (As seen in appendices B, C, D, F, and G).

b. Vessel 64PB0709 will have shortened timeframes since the work package is being accomplished in separate parts. The awardee will only be provided 90 days for its initial package whereas the awardee will be provided 21 days to complete the hull life cycle maintenance, upon its return (As seen in appendices A and E, respectively).

4) Accomplish each task, as required, within the vessel availability:

a. Task 1 Refresh Bottom Paint System: Awardee will accomplish this task in accordance with (IAW) the SOW. Requirements are to clean, perform visual inspection, identify defective areas (submitting results via Condition Found Report, CFR, prior to painting), take pictures IAW the SOW, mask areas for areas not to be painted, apply various coats of paint IAW manufacturer’s instructions, check Dry Film Thickness (DFT), provide report to COR, shift/bump blocks and repeat clean/paint steps on previously blocked areas.

b. Task 2 Clean Vessel Bilge Area: Awardee will accomplish this task IAW the SOW. Requirements are to mark/remove deck plates as necessary to access bilges, clean bilges free of trash/debris/grease/oily liquids/etc., wipe down bilge surfaces with heavy duty cleaning agent, wash with clean potable water, wipe excess water and reinstall deck plates which were removed.

c. Task 3 Fuel Tank Cleaning and Fuel Disposal: Awardee will accomplish this task IAW the SOW. Requirements include providing spill prevention required by law, remove cover, draw and provide sample of fuel to Port Ops Technical Point of Contact (TPOC), clean inside of the tank, dispose of all fuel after tank cleaning, inspect tank and provide CFR of condition to the COR, reinstall access cover with new VITON gaskets, allow for Government to provide additional fuel.

d. Task 4 Main Deck Non-Skid Replacement: Government will provide new non-skid kits upon delivery of the vessel, as delineated in Attachment J-2 GFP Attachment, for accomplishment of this task. NOTE: Task 13 must be completed to accomplish this task. Awardee will accomplish this task IAW the SOW. Requirements include noting existing deck markings for re-application on the newly applied non-skid, remove all existing main deck non-skid strips, clean areas of removed non-skid, inspect and provide report of main deck via CFR to the COR, install new main deck non-skid strips IAW layout provided and per manufacturer’s instructions, complete edge sealing concurrently with non-skid application, re-apply previously noted deck markings.

e. Task 5 USCG Racing Stripe and Emblem: Awardee will accomplish this task IAW the SOW. Requirement is to sand or blast exterior hull to remove diagonal stripe on Port and Starboard bow, inspect area and provide report via CFR to the COR, repaint Port and Starboard bow with new diagonal stripe and install USCG emblem IAW their respective contract enclosures.

f. Task 6 Main Diesel Engine (MDE) Replacement: Awardee will accomplish this task IAW the SOW. Original equipment manufacturer (OEM) of the engines is MTU. NOTE: Task 12 must be completed to accomplish this task.

i. Each vessel, with the exception of vessel SV64107, requires the removal of both Port and Starboard engines (With the engines respective ZF Marine Gears attached); vessel SV64107 only requires the removal of its Port engine assembly. Engines removed from a vessel will not be reinstalled in the same vessel.

ii. The awardee will be required to construct timber engine blocks to be used for resting the removed engine assemblies.

iii. The awardee will be required to install the Government provided Port or Starboard engine assembly directly from its shipping skids/crates. The awardee will need to coordinate with an MTU certified technician to remove engine preservation and to prepare the engine for operation.

iv. The awardee is required to mount the removed engine assemblies to the Government provided shipping skids/crates, and make the engines available for transport by another Contractor, on a concurrent Government contract, to accomplish the rebuild of the engines. THE GOVERNMENT WILL TAKE ACCEPTANCE OF THE ENGINES FROM THE AWARDEE PRIOR TO PICKUP BY THE CONCURRENT GOVERNMENT CONTRACT.

v. Once engines are reinstalled and all other tasks are complete, the awardee will be required to make any corrections resulting from initial engine operations and waterborne trials under the direction of a certified technician of the engine.

g. Task 7 Drive Line Replacement: Awardee will accomplish this task IAW the SOW. This work must be accomplished by Regional Dana GWB authorized distributor and service provided. There are two known sources capable of performing this work: Driveline Service of Portland, Inc. and Pacific Power Group (See SOW paragraph 1.13).

i. The specific requirements of this task are to remove existing Port and Starboard cardan shafts, rebuild the shafts and then re-install IAW contract enclosures.

ii. Inspect the Port and Starboard intermediate shaft, jet coupling, intermediate shaft to jet coupling coupler and companion hub. Clean to like new condition and provide report via CFR to COR. Reinstall the original intermediate shaft, jet coupling, intermediate shaft to jet coupling coupler and companion hub IAW SOW.

iii. Remove existing Port and Starboard cooper carrier bearings and replace with new IAW contract enclosures.

h. Task 8 HM521 Jet Drive (5,000 Hour Maintenance): Awardee will allow for the Government to complete this task in its entirety. The work is to be done in a separate space aboard the vessel by the government and should not interfere with work to be accomplished by the awardee.

i. Task 9 Generator Removal and Replacement: Awardee will accomplish this task IAW the SOW. Requirements include removal of existing and installation of new Government provided generator IAW contract enclosures. Remove and re-install all required brackets/hoses/fittings/ancillary equipment/electrical connections. Replace all engine oil, coolant, fuel and fluids IAW contract enclosures. Clean corrosion from the frame. Remove existing and install new generator supply and exhaust sea water hoses.

j. Task 10 Electrical System Groom: Awardee will accomplish this task IAW the SOW. Requirement is to groom all electrical cables and wiring, cleaning corrosion from all electrical connections IAW contract enclosures, ensuring all wire bundles/wire harnesses/engine harnesses are secure and grounded. Work to be done IAW good marine practices.

k. Task 11 Piping System Inspection: Awardee will accomplish this task IAW the SOW. Requirement is to inspect all engine, AC and auxiliary sea water piping for damage and corrosion IAW contract enclosures. Awardee shall submit results of inspection via CFR to the COR.

l. Task 12 MDE Anchor Point Installation: Awardee will accomplish this task IAW the SOW. Requirement is to install engine anchor points IAW contract enclosures. THIS IS TO BE DONE IN ADVANCE OF REMOVAL AND INSTALLATION OF ENGINES. Remove fuel from tanks prior to performing work. Inspect work surface and submit report of condition via CFR to the COR. Remove any corrosion as necessary. Remove interferences to accomplish this work, and retain/re-install upon completion of anchor point installation. Fabricate anchor points IAW contract enclosure, maintaining gas free certification for all hot work. Remove and clean shavings/slag/material prior to removal of engines and refueling work. Visually inspect all welds and test each anchor point IAW contract enclosures. Submit results of visual inspection via CFR to the COR.

m. Task 13 Mast Fall Protection Installation: Awardee will accomplish this task IAW the SOW. Requirement is to install mast fall protection IAW contract enclosures. THIS IS TO BE DONE IN ADVANCE OF REMOVAL AND REPLACEMENT OF MAIN DECK NON-SKID. Remove ceiling panels, cables, wires, fixtures, equipment hangers, insulation and interferences to accomplish this work, retain and re-install upon completion of mast fall protection installation. Submit condition via CFR to the COR identifying missing/defective fasteners and hardware. Cover specified areas within SOW to prevent damage from hot work and welding. Fabricate fall protection installation IAW contract enclosures. Inspect work surface and submit condition via CFR to the COR. Remove and clean shavings/slag/material prior to removal and re-application of non-skid. Visually inspect all welds. Submit results of visual inspection via CFR to the COR.

5) Upon of the completion of all work specified in the SOW for the respective vessel/delivery order and prior to Government acceptance trials, the awardee will conduct independent pier side trials to verify all work has been accomplished. Awardee will correct for any deficiencies identified. Awardee will allow for OEM Auth. Distributor of rebuilt engines and marine gears to be present. Submit a CFR following completion of trials to report any deficiencies.

6) Government shall provide for operators to conduct acceptance trials. Awardee will provide appropriate personnel and supplies to launch and accomplish a two (2) hour waterborne trial to demonstrate and test all work accomplished. Awardee will allow for OEM Auth. Distributor of rebuilt engines and marine gears to be present. Submit a CFR following completion of trials to report any deficiencies.

Points of Interest:

· This project requires both the awardee and OEM authorized distributor of the engine rebuild/marine gears to attend waterborne trial(s).

· Awardee of this contract does not rebuild the removed engines.

· Once removed, the Awardee prepares engines for the transport. Awardee will coordinate with the Government and the rebuild contractor to pick up removed engines. Transfer of property will occur from awardee to government prior to pick-up via DD-1149.

· Awardee coordinates with the engine certified technicians for installation and associated requirements.

· Subcontract for the Drive Line Replacement; the Government has provided company information of two known sources.