P907_Amend0006_Specs.pdf
PDF 2 MB Posted
- Attached to
- Amendment 0010 -Use the applicable Small Business Forms attached Federal contract opportunity
- Solicitation number
- n44255
About this file
This amendment modifies a solicitation for a construction project. The project involves constructing a general purpose berthing pier and trestle with controlled access, as well as a vessel maintenance facility with parking and a fuel distribution and storage system. These facilities will support the Maritime Force Protection Unit at Naval Base Kitsap Bangor by providing security escort for submarines transiting between homeport and test ranges, supporting the stand-up of the Nuclear Weapons Security Program mission as mandated by national security directives. The amendment likely pertains to the use of applicable small business forms for the solicitation.
View the file
Other files for this federal contract opportunity
Show all 50
Amendment 0010 -Use the applicable Small Business Forms attached has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bangor P-907 TPP Pier 217069
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
List of Contact Personnel; G
1.2 SPECIAL SCHEDULING REQUIREMENTS
a. Tree removal shall not occur between April 1 and September 23. See section 01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS for further restrictions.
b. The Government may undertake or award other contracts for additional work at or near the site of the work under this contract. The Contractor shall fully cooperate with the other contractors and with Government employees and shall carefully adapt scheduling and performing the work under this contract to accommodate the additional work, heeding any direction that may be provided by the Contracting Officer. The Contractor shall not commit or permit any act that will interfere with the performance of work by any other contractor or by Government employees.
c. The KB spit area, including KB pier and B7136, will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
d. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 30 calendar days prior to the desired date of interruption.
e. Fuel facility must be completed and operational before decommissioning existing fuel tanks at Service Pier. Fuel Facility construction activities shall only occur between 1 September and 1 January. Fuel facility construction activities limited to these dates include:
1. All work at the new fuel facility site along Sealion Road.
2. All piping work for the Diesel Fuel Marine (DFM) from the fuel facility to the junction vault shown on CW152.
f. Pile driving shall only occur between 22 July and 15 January. See Section 01 57 19.01 20 SUPPLEMENTAL TEMPORARY ENVIRONMENTAL CONTROLS for further restrictions.
SECTION 01 14 00 Rev 1 Page 1 September 24, 2020 matt.waller Cloud matt.waller Cloud
1.3 CONTRACTOR ACCESS AND USE OF PREMISES
1.3.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
1.3.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.3.1.2 Installation Access
Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html . No fees are associated with obtaining a DBIDS credential.
Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.
1.3.1.2.1 Registration for DBIDS
Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html . Procedure includes:
a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.
b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.
c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html .
d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, finger prints, base restriction and several other assessments.
e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.
SECTION 01 14 00 Rev 1 Page 2 September 24, 2020
1.3.1.2.2 DBIDS Eligibility Requirements
Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.
The Government is the final authority.
1.3.1.2.3 DBIDS Notification Requirements
a. Immediately report instances of lost or stolen badges to the Contracting Officer.
b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:
(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.
1.3.1.2.4 One-Day Passes
Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.
1.3.1.3 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.3.2 Working Hours
Regular working hours must consist of an 8 1/2 hour period , between 7 a.m. and 3:30 p.m., Monday through Friday, excluding Government holidays.
1.3.3 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval.
Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During
SECTION 01 14 00 Rev 1 Page 3 September 24, 2020 periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.3.4 Exclusionary Period
No in-water work may be performed during the period of 16 January to 21 July, inclusive. This period has been considered in computing the time allowed for the performance of this contract.
1.3.5 Occupied Buildings
The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.
1.3.6 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS. Contractor shall not be entitled to additional payment for the utility outages and connections required to be performed outside of regular work hours.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, and compressed air, are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions are further limited to 4 hours. This time limit includes time for deactivation and reactivation. All services shall be maintained operational at all times except for cut-over periods as described above. Temporary and/or portable utilties shall be provided by the contractor at no cost to the governmnet for cut-over periods longer than described above.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain.
1.4 NAVAL BASE KITSAP BANGOR, WA OPERATIONS AREA/SWFPAC PRODUCTION AREA
SECURITY/WATERFRONT RESTRICTED AREA/MAIN LIMITED
1.4.1 Bangor Operations Area
Contractor personnel will require a B9 Code on their security badge to gain access to the SWFPAC Operation Area, this will be required for all work. Contractor personnel will require a B9 and 4X Code on thier security badge to gain access to Service Pier for existing fuel tank decommissioning work.
SECTION 01 14 00 Rev 1 Page 4 September 24, 2020
1.4.1.1 Delays
Contractor operations are subject to reasonable delays, suspensions, and restrictions because of emergencies, alerts, drills, equipment movements and other such activities. Contractor must expect loss of one work day per month due to these delays.
1.4.1.2 Searches and Inspections
Persons entering onto Government Property are, as a condition of access, subject to searches of all vehicles and personal belongings. This includes briefcases, handbags, tool chests, boxes, sealed packages, and personal articles. Random Administrative Vehicle Inspections are conducted by Security Police each day at various hours and locations on base. If selected for a vehicle inspection, be prepared to open your glove box, hood, trunk, and other personal items requested by Security.
1.4.1.3 Photography
Photography by the contractor is prohibited.
1.4.2 Marine Vessel Access to the Work Site
Existing Port Security Barrier System will be in use surrounding the work site. Cooridnate with Port Ops and the Contracting officer for openings.
All personnel present on marine vessels are required to have a B9 Code on their security badge. Vessel arrival/departure shall be coordinated a minimum seven days in advance via the Contracting Officer.
1.4.2.1 Communications
Each vessel shall have a Contracting Officer approved means of communication. The Contractor shall provide a least two communication devices (e.g. radios, batteries, and charger) to maintain such communication with the Contracting Officer.
1.4.2.2 Searches and Inspections
All marine vessels are subject to search and inspection by security personnel.
1.4.2.3 Vessel Launching at the Work Site
Launching of small vessels will be permitted at the adjacent ramp on Carson Spit. All vessel launchings shall be coordinated with the Contracting Officer and shall be announced directly to Port Operations via a marine radio at the time of launch. It shall be noted that the ramp is primitive and its use is tidal dependent. Contractor shall use at their own risk.
1.4.2.4 Containers/Lockboxes
Contractor containers, lock boxes and equipment left overnight at the work area will be subject to search by Security Force Personnel. Construction locks may be utilized but during security events Security Forces reserve the right to cut locks for the purposes of inspection without recourse.
SECTION 01 14 00 Rev 1 Page 5 September 24, 2020
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 01 14 00 Rev 1 Page 6 September 24, 2020
SECTION 01 32 17.00 20
COST-LOADED NETWORK ANALYSIS SCHEDULES (NAS)
05/18
PART 1 GENERAL
1.1 DEFINITIONS
The cost-loaded Network Analysis Schedule (NAS) is a tool to manage the project, both for Contractor and Government activities. The NAS is also used to report progress, evaluate time extensions, and provide the basis for progress payments.
For consistency, when scheduling software terminology is used in this section, the terms in Primavera's scheduling programs are used.
1.2 SCHEDULE REQUIREMENTS PRIOR TO THE START OF WORK
1.2.1 Preliminary Scheduling Meeting
Before preparation of the Project Baseline Schedule, and prior to the start of work, meet with the Contracting Officer to discuss the proposed schedule and the requirements of this section.
1.2.2 Project Baseline Schedule
Submit the Baseline NAS at the PreConstruction Meeting. Government review comments on the Contractor's schedule(s) do not relieve the Contractor from compliance with requirements of the Contract Documents. Only bonds may be paid prior to acceptance of the Baseline NAS. The acceptance of a Baseline NAS is a condition precedent to:
a. The Contractor starting demolition work or construction stage(s) of the contract.
b. Processing Contractor's invoices(s) for construction activities/items of work.
c. Review of any schedule updates.
Submittal of the Baseline NAS, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
1.3 THREE-WEEK LOOK AHEAD SCHEDULE
1.3.1 Weekly CQC Coordination and Production Meeting
Deliver three hard copies and one electronic file of the 3-Week Look Ahead Schedule to the Contracting Officer no later than 8 a.m. each Monday, for review during the weekly CQC Coordination or Production Meeting.
SECTION 01 32 17.00 20 Rev 1 Page 1 September 24, 2020
1.3.2 Look Ahead Schedule Requirements
Prepare and issue a 3-Week Look Ahead schedule to provide a more detailed day-to-day plan of upcoming work identified on the Project Network Analysis Schedule. Requirements include:
a. Key the work plans mapped to NAS activity numbers and updated each week to show the planned work for the current and following two-week period.
b. Include upcoming outages, closures, field evaluation tests, preparatory meetings, and initial meetings.
c. Identify critical path activities on the Three-Week Look Ahead Schedule.
d. The detail work plans are to be bar chart type schedules, derived from but maintained separately from the Project NAS on an electronic spreadsheet program and printed on 8-1/2 by 11 inch sheets as directed by the Contracting Officer.
e. Activities must not exceed 5 working days in duration and have sufficient level of detail to assign crews, tools and equipment required to complete the work.
1.4 MONTHLY NETWORK ANALYSIS
1.4.1 Monthly Network Analysis Updates
Meet with Government representatives at monthly intervals to review and agree on the information presented in the updated project schedule. The submission of an acceptable, updated schedule to the Government is a condition precedent to the processing of the Contractor's invoice. Submit an acceptable, updated schedule to the Government regardless of whether a Contractor's invoice is submitted for the given period. The Contractor and Government must consent to agree on unit quantities of work completed equating to a percentage of payment for each activity progressed during the update period. Monthly update schedules must incorporate as-built events as they occurred and provide ongoing status of anticipated finish dates. As-built events must correspond to contemporaneous records including but not limited to submittals, daily production reports and quality control reports.
Provide the following with each Schedule submittal:
a. Time-Scaled Logic Diagram.
b. Reports listed in paragraph REQUIRED TABULAR REPORTS.
c. Data disks containing the project schedule. Include the back-up native .xer program files.
1.4.2 As-Built Schedule
As a condition precedent to the release of retention and making final payment, submit an "As-Built Schedule," as the last schedule update showing all activities at 100 percent completion. This schedule must reflect the exact manner in which the project was actually constructed.
SECTION 01 32 17.00 20 Rev 1 Page 2 September 24, 2020
1.5 CORRESPONDENCE AND TEST REPORTS
Reference Schedule activity IDs that are being addressed in each correspondence (e.g., letters, Requests for Information (RFIs), e-mails, meeting minute items, Production and QC Daily Reports, material delivery tickets, photographs) and test report (e.g., concrete, soil compaction, weld, pressure).
1.6 ADDITIONAL SCHEDULING REQUIREMENTS
References to additional scheduling requirements, including systems to be inspected, tested and commissioned, that are located throughout the remainder of the Contract Documents, are subject to the requirements of this section.
1.7 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance with Section 01 33 29 SUSTAINABILITY REPORTING.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Designated Project Scheduler; G
Baseline NAS; G
SD-07 Certificates
Monthly Network Analysis Updates; G
SD-11 Closeout Submittals
As-Built Schedule; G
1.8 SOFTWARE
Prepare and maintain project schedules using Primavera P6 software in a version compatible with Government's current version. Importing data into P6 using data conversion techniques or third party software is cause for rejection of the submitted schedule.
1.9 DESIGNATED PROJECT SCHEDULER
Submit to the Contracting Officer for approval an individual who will serve as the Designated Project Scheduler. Include a copy of the candidate's resume with qualifications. The Contracting Officer may remove the Designated Project Scheduler, and require replacement, if the scheduler does not effectively fulfill their duties in accordance with the contract requirements. Payment request will not be processed without an approved Designated Project Scheduler.
1.9.1 Qualifications
The Designated Project Scheduler must have prepared and maintained at least three previous construction schedules, of similar size and
SECTION 01 32 17.00 20 Rev 1 Page 3 September 24, 2020 complexity to this contract, using Primavera P6.
1.9.2 Duties
Duties of the Designated Project Scheduler:
a. Prepare Baseline NAS.
b. Prepare monthly schedule updates.
c. Prepare tabular reports.
d. Prepare Time Impact Analysis (TIA) as necessary.
e. Provide certification that NAS and TIA submittals conform to the contract requirements.
f. Participate with the Prime Contractor and Government Representative in a monthly meeting at the job site in-person, and scheduled with sufficient time to support the Monthly Network Analysis Updates process, to discuss project status, schedule updates, critical activities, potential delays, and contract modifications impacting the schedule.
1.10 NETWORK SYSTEM FORMAT
The system must include time-scaled logic diagrams and specified reports.
Prepare the schedule in accordance with the following Primavera P6 settings and parameters. Deviation from these settings and parameters, without prior consent of the Contracting Officer, is cause for rejection of schedule submission.
1.10.1 Diagrams
Provide 11 by 17 inch hard-copy of Time-scaled Logic Diagram in color and landscape-oriented. Clearly show activities on the longest path. Include the following information for each activity and include accompanying Gantt chart:
a. Activity ID
b. Activity Name
c. Original Duration in Work Days
d. Remaining duration in Work Days
e. Physical Percent Complete
f. Start Date
g. Finish Date
h. Total Float
SECTION 01 32 17.00 20 Rev 1 Page 4 September 24, 2020
1.10.2 Schedule Activity Properties and Level of Detail
1.10.2.1 Activity Identification and Organization
a. Identify construction activities planned for the project and other activities that could impact project completion if delayed in the NAS.
b. Identify administrative type activity/milestones, including all pre-construction submittal and permit requirements prior to demolition or construction stage.
c. Include times for procurement, Contractor quality control and construction, acceptance testing and training in the schedule.
d. Include the Government approval time required for the submittals that require Government Approval prior to construction, as indicated in Section 01 33 00 SUBMITTAL PROCEDURES .
e. Create separate activities for each Phase, Area, Floor Level and Location the activity is occurring.
f. Do not use construction category activity to represent non-work type reference (e.g. Serial Letter, Request for Information) in NAS. Place Non-work reference within the P6 activity details notebook.
Activity categories included in the schedule are specified below.
1.10.2.2 Activity Logic
a. With the exception of the Contract Award and Contract Completion Date (CCD) milestone activities, activity must not be open-ended; each activity must have predecessor and successor ties.
b. Activities must not have open start or open finish (dangling) logic.
c. Do not use lead or lag logic without Contracting Officer prior approval.
d. Minimize redundant logic ties.
e. Once an activity exists on the schedule it must not be deleted or renamed to change the scope of the activity and must not be removed from the schedule logic without approval from the Contracting Officer.
(1) While an activity cannot be deleted, where said activity is no longer applicable to the schedule, but must remain within the logic stream for historical record, change the activity to a milestone and clearly label "NO LONGER REQUIRED" after the activity name. Redistribute accordingly any remaining budget associated with that activity.
(2) Document any such change in the milestone's "Notebook," including a date and explanation for the change.
(3) The ID number for a "NO LONGER REQUIRED" activity must not be re-used for another activity.
SECTION 01 32 17.00 20 Rev 1 Page 5 September 24, 2020
1.10.2.3 Critical and Near Critical Activity Baseline Limitation
For P6 settings, critical activities are defined as being on the Longest Path. "Near Critical" is defined as having total float, of up to 14 days more, than the greatest float value found on the Longest Path. Longest Path (Critical) and Near Critical Activities must not make up more than 20 percent of all activity within the Baseline Schedule.
1.10.2.4 Assigned Calendars
All NAS activity must be assigned calendars that reflect required and anticipated non-work days.
1.10.2.5 Activity Categories
1.10.2.5.1 Pre-construction Activities
Examples of pre-construction activities include, but are not limited to, bond approval, permits, pre-construction submittals and approvals.
Include pre-construction activities that are required to be completed prior to the Contractor starting the demolition or construction stage of work.
1.10.2.5.2 Procurement Activities
Examples of procurement activities include, but are not limited to:
Material/equipment submittal preparation, submittal and approval of material/equipment; material/equipment fabrication and delivery, and material/equipment on-site. As a minimum, separate procurement activities must be provided for critical items, long lead items, items requiring Government approval and material/equipment procurement for which payment will be requested in advance of installation. Show each delivery with relationship tie to the Construction Activity specifically for the delivery.
1.10.2.5.3 Government Activities
Government and other agency activities that could impact progress must be clearly identified. Government activities include, but are not limited to; Government approved submittal reviews, Government conducted inspections/tests, environmental permit approvals by State regulators, utility outages, and delivery of Government Furnished Material/Equipment.
1.10.2.5.4 Construction Quality Management (CQM) Activities
The Preparatory and Initial Phase meetings for each Definable Feature of Work identified in the Contractor's Quality Control Plan must be included in the Three-Week Look Ahead Schedule. Preparatory and Initial phase meetings are not required in the NAS, but can be represented by a start milestone linked to successor parent Construction Activity. The Follow-up Phase must be represented by the Construction Activities themselves in the
NAS.
1.10.2.5.5 Construction Activities
No on-site construction activity may have a duration in excess of 20 working days. Contractor activities must be driven by calendars that reflect Saturdays, Sundays and all Federal Holidays as non-work days, unless otherwise defined in this contract.
SECTION 01 32 17.00 20 Rev 1 Page 6 September 24, 2020
1.10.2.5.6 Turnover and Closeout Activities
Include activities or milestones for items on the NAVFAC Red Zone Checklist/POAM that are applicable to this project. As a minimum, include required Contractor testing, required Government acceptance inspections on equipment, Pre-Final Inspection, Punch List Completion, Final Inspection and Acceptance. Add an unconstrained start milestone for the initial NAVFAC Red Zone - Facility Turnover Planning Meeting at approximately 75 percent construction contract completion or six months prior to Contract Completion Date (CCD), whichever is sooner.
1.10.2.5.7 Testing of HVAC - DALT, TAB, and PVT Activities
Include in the baseline schedule, activities and milestones associated with Government acceptance of Duct Air Leakage Test (DALT), Testing, Adjusting, and Balancing (TAB) and Performance Verification Test (PVT) as required and in accordance with Section 23 05 93 TESTING, ADJUSTING AND BALANCING FOR HVAC and Section 23 09 00 INSTRUMENTATION AND CONTROL FOR
HVAC.
a. Identify the general area or location(s) for Government Acceptance Testing of DALT, TAB and PVT.
b. Incorporate into the baseline schedule, time periods required for advance notification of work, and Government submittal review in accordance with Section 23 05 93 TESTING, ADJUSTING AND BALANCING FOR HVAC, paragraph DALT AND TAB SUBMITTAL AND WORK SCHEDULE.
c. Include the following as schedule activities or milestones:
(1) Pre-DALT/TAB/PVT Meeting
(2) TAB Design Review Report, Government review
(3) TAB Pre-Field Engineering Report, Government review
(4) DALT Field Work
(5) DALT Field Acceptance Testing
(6) Certified Final DALT Report, Government review
(7) Control Contractors PVT Plan, Government review
(8) Equipment Suppliers PVT Plan, Government review
(9) Season I TAB Field Work
(10) Season I Certified Final TAB Report, Government review
(11) Endurance Testing, Government review
(12) PVT Field Work
(13) PVT Report, Government review
(14) Season I TAB Field Acceptance Testing
SECTION 01 32 17.00 20 Rev 1 Page 7 September 24, 2020
1.10.2.5.8 Commissioning Activities
Include in the baseline schedule activities and milestones associated with Commissioning.
a. Identify the general area or location(s) of systems for Commissioning Inspection and Testing
b. Incorporate into the baseline schedule time periods for Government submittal review
1.10.2.6 Contract Milestones and Constraints
1.10.2.6.1 Project Start Date Milestones
Include as the first activity on the schedule a start milestone titled "Contract Award," which must have a Mandatory Start constraint equal to the Contract Award Date.
1.10.2.6.2 NAVFAC Red Zone - Facility Turnover Planning Meeting Milestones
See paragraph TURNOVER AND CLOSEOUT ACTIVITIES above.
1.10.2.6.3 Substantial Completion Milestone
Include an unconstrained finish milestone on the schedule titled "Substantial Completion." Substantial Completion is defined as the point in time the Government would consider the project ready for beneficial occupancy wherein by mutual agreement of the Government and Contractor, Government use of the facility is allowed while construction access continues in order to complete remaining items (e.g. punch list and other close out submittals). Include a separate Substantial Completion Milestone for each phase if the contract requires construction to be completed in phases.
1.10.2.6.4 DD-1354 Finish Milestone
Add unconstrained finish milestone, titled "DD-1354" and scheduled 30 calendar days prior to Substantial Completion, whenever a Form DD-1354 is required in accordance with Section 01 20 00.00 20 PRICE AND PAYMENT
PROCEDURES.
1.10.2.6.5 Projected Completion Milestone
Include an unconstrained finish milestone on the schedule titled "Projected Completion." Projected Completion is defined as the point in time all contract requirements are complete and verified by the Government with a successful Final Inspection in accordance with Section 01 45 00.00 20 QUALITY CONTROL . This milestone must have the Contract Completion Date (CCD) milestone as its only successor.
1.10.2.6.6 Contract Completion Date (CCD) Milestone
Last schedule entry must be an unconstrained finish milestone titled "Contract Completion (CCD: DD-MM-YY)." DD-MM-YYYY is the current contract completion date at data date, day-month-year corresponding to P6 Must Finish Date. NAS milestone updates of Project Completion finish date for longest path must reflect calculated float as positive or negative based on CCD. Calculation of schedule updates must be such that if the finish
SECTION 01 32 17.00 20 Rev 1 Page 8 September 24, 2020 of the "Projected Completion" milestone falls after the contract completion date, then negative float is calculated on the longest path.
If the finish of the "Projected Completion" milestone falls before the contract completion date, the float calculation must reflect positive float on the longest path.
1.10.2.7 Work Breakdown Structure & Activity Code
At a minimum, establish a Work Breakdown Structure (WBS) and provide activity codes identified as follows:
1.10.2.7.1 Work Breakdown Structure (WBS)
Group all activities and milestones within appropriate WBS categories including, at a minimum, the following:
a. Project Milestones:
(1) Management Milestones
(2) Project Administrative Meetings
(3) Permits
b. Pre-Construction Phase:
(1) Submittals and Reviews
(2) Procurement
(3) Mobilization
c. Construction Phase: Create multiple sub-sections in accordance with project specific categories of work including in WBS descending order as follows:
(1) General Area
(a) Type of Work Item
1. Location
d. Commissioning & Testing:
(1) Specific area/locations of commissioning
(2) Final Testing
(3) Training
d. Project Closeout: Include activity items such as Punchlist, Demobilization, O&M, As-built Drawings, Training, and As-built NAS.
e. Modifications: Create sub-category of Conformed and Non-Conformed under Modification WBS. Create multiple sub-sections as the project progresses identified by issue and Fragnet placed in Conformed for modifications issued prior data date, or Non-Conformed for issues not modified to contract prior data date.
SECTION 01 32 17.00 20 Rev 1 Page 9 September 24, 2020
f. Removed Activity: Activity "removed" by remaining within logic sequence and changing to Finish Milestone. Actualize finish date to date activity removed from schedule and provide reason(s) for removal explained in Activity Notebook.
1.10.2.7.2 Responsibility Code
All activities in the project schedule must be identified with the party responsible for completing the task. Activities must not belong to more than one responsible party.
1.10.2.7.3 Activity Category Code
Provide user defined "CAT" codes for Project Level activity codes. Use the following codes:
a. Assign "Procure" to Procurement type activity
b. Assign "Construct" Construction type activity
c. Assign "Close Out" to dedicated Commissioning, Testing & Close Out type activity.
d. Assign "Other" to other activity not otherwise designated.
1.10.2.7.4 Construction Specification Institute (CSI) Masterformat Code
Identify all activities in the project schedule with its respective Specification Section number. Activities must not belong to more than one Section number. If an activity does not have an applicable CSI Code (e.g.
Mobilize), the code must be "0000".
1.10.2.8 Anticipated Weather Lost Work Days
Use the following schedule of anticipated monthly non-work days due to adverse weather as the basis for establishing a "Weather Calendar" showing the number of anticipated non-workdays for each month due to adverse weather, in addition to Saturdays, Sundays and all Federal Holidays as non-work days.
MONTHLY ANTICIPATED ADVERSE WEATHER DELAYS
JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
4 4 3 2 1 0 0 0 1 2 3 4
Assign the Weather Calendar to any activity that could be impacted by adverse weather. The Contracting Officer will issue a modification in accordance with the contract clauses, giving the Contractor a time extension for the difference of days between the anticipated and actual adverse weather delay if the number of actual adverse weather delay days exceeds the number of days anticipated for the month in which the delay occurs and the adverse weather delayed activities are critical to contract completion. A lost workday due to weather conditions is defined as a day in which the Contractor cannot work at least 50 percent of the day on the impacted activity.
SECTION 01 32 17.00 20 Rev 1 Page 10 September 24, 2020
1.10.2.9 Anticipated Restricted Delays
As defined in Section 01 14 00 WORK RESTRICTIONS, allow in the schedule one lost work day per month for instances where base access is not permitted or where work areas are temporarily not accessible for security reasons. Additionally, allow in the schedule two lost work days per month during pile driving activities due to the presence of marine mammals and/or marbled murrelets. Use Anticipated Restricted Delays as basis for establishing a "Security Calendar" showing the number of anticipated non-workdays for each month due to anticipated restrictions, in addition to anticipated adverse weather, Saturdays, Sundays and all Federal Holidays as non-work days. Assign the Security Calendar to any activity that could be impacted by restriction delays. The Contracting Officer will issue a modification in accordance with the contract clauses, giving the Contractor a time extension for the difference of days between the anticipated and actual lost work days if the number of actual restriction delay days exceeds the number of anticipated for the month in which the delay occurs and the restriction delayed activities are critical to contract completion. A lost workday due to restriction delay is defined as a day in which the Contractor cannot work at least 50 percent of the day on the impacted activity.
1.10.2.10 Cost Loading
The Project Network Analysis Schedule (NAS) must be cost-loaded and will provide the basis for progress payments. Earned Value Reports must be derived from and correspond to cost loaded NAS. Use the Critical Path Method (CPM) and the Precedence Diagram Method (PDM) to satisfy time and cost applications.
1.10.2.10.1 Cost Loading Activities
Assign Material and Equipment Costs, for which payment will be requested in advance of installation, to their respective procurement activity (i.e., the material/equipment on-site activity). Assign cost for material/equipment, paid for after installation; labor; and construction equipment to their respective Construction Activities. Provide breakdown of definable features of work for cost loaded activities comprising Mobilization and De-Mobilization (Lump sum not allowed). The value of commissioning, testing and closeout WBS section may not be less than 10 percent of the total costs for Procurement and Construction Activities.
Evenly disperse overhead and profit to each activity over the duration of the project.
1.10.2.10.2 Partial Payment
Breakdown unit of measure and cost must be defined within P6 Activity Detail Expenses for partial payment of any cost loaded activity. Lump sum cost loaded activity will not be partially paid.
1.10.3 Schedule Software Settings and Restrictions
a. Activity Constraints: Date/time constraint(s), other than those required by the contract, are not allowed unless accepted by the Contracting Officer. Identify any constraints proposed and provide an explanation for the purpose of the constraint in the Narrative Report as described in paragraph REQUIRED TABULAR REPORTS.
b. Default Progress Data Disallowed: Actual Start and Actual Finish
SECTION 01 32 17.00 20 Rev 1 Page 11 September 24, 2020 dates on the CPM schedule must match the dates on the Contractor Quality Control and Production Reports.
c. Software Settings: Handle schedule calculations and Out-of-Sequence progress (if applicable) through Retained Logic, not Progress Override. Show all activity durations and float values in days. Show activity progress using Remaining Duration. Set default activity type to "Task Dependent".
d. At a minimum, include the following settings and parameters in P6 Schedule preparation:
(1) General: Define or establish Calendars and Activity Codes at the "Project" level, not the "Global" level.
(2) Admin Drop-Down Menu, Admin Preferences, Time Periods Tab:
(a) Set time periods for P6 to 8.0 Hours/Day, 40.0 Hours/Week,
172.0 Hours/Month and 2000.0 Hours/Year.
(b) Use assigned calendar to specify the number of work hours for each time period: Must be checked.
(3) Admin Drop-Down Menu, Admin Preferences, Earned Value Tab:
(a) Earned Value Calculation: Use "Budgeted values with current dates".
(4) Project Level, Dates Tab:
(a) Set "Must Finish By" date to "Contract Completion Date", and set "Must Finish By" time to 05:00pm.
(5) Project Level, Defaults Tab:
(a) Duration Type: Set to "Fixed Duration & Units".
(b) Percent Complete Type: Set to "Physical".
(c) Activity Type: Set to "Task Dependent".
(d) Calendar: Set to "Standard 5 Day Workweek". Calendar must reflect Saturday, Sunday and all Federal holidays as non-work days. Alternative calendars may be used with Contracting Officer approval.
(6) Project Level, Calculations Tab:
(a) Activity percent complete based on activity steps: Must be Checked.
(b) Reset Remaining Duration and Units to Original: Must be Checked.
(c) Subtract Actual from At Completion: Must be Checked.
(d) Recalculate Actual units and Cost when duration percent complete changes: Must be Checked.
SECTION 01 32 17.00 20 Rev 1 Page 12 September 24, 2020
(e) Link Actual to Date and Actual This Period Units and Cost:
Must be Checked.
(f) Price/Unit: Set to "$1/h".
(g) Update units when costs change on resource assignments: Must be Unchecked.
(7) Project Level, Settings Tab:
(a) Define Critical Activities: Check "Longest Path".
(8) Work Breakdown Structure Level, Earned Value Tab:
(a) Technique for Computing Performance Percent Complete:
"Activity percent complete" is selected.
(b) Technique for Computing Estimate to Complete (ETC): "PF = 1" is selected.
1.10.4 Required Tabular Reports
Include the following reports with the Baseline, Monthly Update and any other required schedule submittals:
a. Log Report: P6 Scheduling/Leveling Report.
b. Narrative Report: Identify and justify:
(1) Progress made in each area of the project;
(2) Longest Path;
(3) Date/time constraint(s), other than those required by the contract
(4) Listing of all changes made between the previous schedule and current updated schedule include: added or deleted activities, original and remaining durations for activities that have not started, logic (sequence constraint lag/lead), milestones, planned sequence of operations, longest path, calendars or calendar assignments, and cost loading;
(5) Any decrease in previously reported activity Earned Amount;
(6) Pending items and status thereof, including permits, changes orders, and time extensions;
(7) Status of Contract Completion Date and interim milestones;
(8) Current and anticipated delays (describe cause of delay and corrective actions(s) and mitigation measures to minimize);
(9) Description of current and potential future schedule problem areas.
Each entry in the narrative report must cite the respective Activity ID and Activity Name, the date and reason for the change, and description of the change.
c. Earned Value Report: Derive from and correspond to P6 cost loaded
SECTION 01 32 17.00 20 Rev 1 Page 13 September 24, 2020 schedule. List all activities having a budget amount cost loaded.
Compile total earnings on the project from notice to proceed to current progress payment request. Show current budget, previous physical percent complete, to-date physical percent complete, previous earned value, to-date earned value and cost to complete on the report for each activity.
d. Schedule Variance Control (SVC) Diagram: With each schedule submission, provide a SVC diagram showing 1) Cash Flow S-Curves indicating planned project cost based on projected early and late activity finish dates and 2) Earned Value to-date. Revise Cash Flow S-Curves when the contract is modified, or as directed by the Contracting Officer.
e. Daily Reported Production Activity: Submit on a monthly basis, in electronic spreadsheet (format provided by the Government), summary of daily reported production activity for the reporting month in the update schedule. Use the following columns for reporting:
(1) Date
(2) Activity ID
(3) Work Description
(4) Contractor
(5) Billable Hours
1.11 CONTRACT MODIFICATION
1.11.1 Time Impact Analysis (TIA)
Submit a Time Impact Analysis with each cost and time proposal for a proposed change. TIA must illustrate the influence of each change or delay on the Contract Completion Date or milestones. No time extensions will be granted nor delay damages paid unless a delay occurs which consumes all available Project Float, and extends the Projected Completion beyond the Contract Completion Date.
a. Each TIA must be in both narrative and schedule form. The narrative must define the scope and conditions of the change; provide start and finish dates of impact, successor and predecessor activity to impact period, responsible party; describe how it originated, and how it impacts the schedule. The schedule submission must consist of three native files:
(1) Fragnet used to define the scope of the changed condition
(2) Most recent accepted schedule update as of the time of the proposal or claim submission that has been updated to show all activity progress as of the time of the impact start date.
(3) The impacted schedule that has the fragnet inserted in the updated schedule and the schedule "run" so that the new completion date is determined.
b. For claimed as-built project delay, the inserted fragnet TIA method must be modified to account for as-built events known to occur after
SECTION 01 32 17.00 20 Rev 1 Page 14 September 24, 2020 the data date of schedule update used.
c. All TIAs must include any mitigation, and must determine the apportionment of the overall delay assignable to each individual delay. Apportionment must provide identification of delay type and classification of delay by compensable and non-compensable events.
The associated narrative must clearly describe analysis methodology used, and the findings in a chronological listing beginning with the earliest delay event.
(1) Identify and classify types of delay defined as follows:
(a) Force majeure delay (e.g. weather delay): Any delay event caused by something or someone other than the Government or the Contractor, or the risk of which has not been assigned solely to the Government or the Contractor. If the force majeure delay is on the longest path, in absence of other types of concurrent delays, the Contractor is granted an extension of contract time, classified as a non-compensable event.
(b) A Contractor-delay: Any delay event caused by the Contractor, or the risk of which has been assigned solely to the Contractor.
If the contractor-delay is on the longest path, in absence of other types of concurrent delays, Contractor is not granted extension of contract time, and classified as a non-compensable event. Where absent other types of delays, and having impact to project completion, Contractor must provide to Contracting Officer a Corrective Action Plan identifying plan to mitigate delay.
(c) A Government-delay: Any delay event caused by the Government, or the risk of which has been assigned solely to the Government.
If the Government-delay is on the longest path, in absence of other types of concurrent delays, the Contractor is granted an extension of contract time, and classified as a compensable event.
(2) Functional theory must be used to analyze concurrent delays, where: separate delay issues delay project completion, do not necessarily occur at same time, rather occur within same monthly schedule update period at minimum, or within same as-built period under review. If a combination of functionally concurrent delay types occurs, it is considered Concurrent Delay, which is defined in the following combinations:
(a) Government-delay concurrent with contractor-delay: excusable time extension, classified non-compensable event.
(b) Government-delay concurrent with force majeure delay:
excusable time extension, classified non-compensable event.
(c) Contractor-delay concurrent with force majeure delay:
excusable time extension, classified non-compensable event.
(3) Pacing delay reacting to another delay (parent delay) equally or more critical than paced activity must be identified prior to pacing. Contracting Officer will notify Contractor prior to pacing. Contractor must notify Contracting Officer prior to pacing. Notification must include identification of parent delay issue, estimated parent delay time period, paced activity(s) identity, and pacing reason(s). Pacing Concurrency is defined as
SECTION 01 32 17.00 20 Rev 1 Page 15 September 24, 2020 follows:
(a) Government-delay concurrent with contractor-pacing: excusable time extension, classified compensable event.
(b) Contractor-delay concurrent with Government-pacing:
inexcusable time extension, classified non-compensable event
d. Submit Data disks containing the narrative and the source schedule files used in the time impact analysis.
e. All as-built and known planned activity must be included in NAS. Add cost loading or change Contract Completion Date to NAS in accordance to conformed contract modifications issued prior to Data Date of NAS update.
1.11.2 No Reservation of Rights
All direct costs, indirect cost, and time extensions will be negotiated and made full, equitable and final at the time of modification issuance.
1.12 PROJECT FLOAT
Project Float is the length of time between the Contractor's Projected Completion Milestone and the Contract Completion Date Milestone. Project Float available in the schedule will not be for the exclusive use of either the Government or the Contractor.
The use of Resource Leveling or other techniques used for the purpose of artificially adjusting activity durations to consume float and influence critical path is prohibited.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
SECTION 01 32 17.00 20 Rev 1 Page 16 September 24, 2020
A180090 A180090PPI
SECTION 01 45 35
SPECIAL INSPECTIONS
02/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
INTERNATIONAL CODE COUNCIL (ICC)
ICC IBC (2015) International Building Code
1.2 GENERAL REQUIREMENTS
Perform Special Inspections in accordance with the Contract Documents and Chapter 17 of ICC IBC . Special Inspections are to be performed by an independent third party and are intended to ensure that the work of the prime contractor is in accordance with the Contract Documents and applicable building codes. Special inspections do not take the place of the three phases of control inspections performed by the Contractor's QC Manager or any testing and inspections required by other sections of the specifications.
Structural observations will be performed by the Government. The contractor must provide notification to the Contracting Officer 14 days prior to the following points of construction:
a. Pile Driving
ab. Placement of pile plug concrete.
bc. Placement of stage I pile cap concrete incorporating pile to pile cap connections.
cd. Placement of stage I spine beam concrete incorporating grade 80 stirrups.
de. Foam filling of berthing camel.
ef . Transportation of the berthing camel from the fabrication facility.
1.3 DEFINITIONS
1.3.1 Continuous Special Inspections
Continuous Special Inspections is the constant monitoring of specific tasks by a special inspector. These inspections must be carried out continuously over the duration of the particular tasks.
1.3.2 Periodic Special Inspections
Periodic Special Inspections is Special Inspections by the special inspector who is intermittently present where the work to be inspected has been or is being performed.
SECTION 01 45 35 Page 1 rygel Architect rygel Cloud+
PPI 265
1.3.3 Perform
Perform these Special Inspections tasks for each welded joint or member.
1.3.4 Observe
Observe these Special Inspections items on a random daily…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .