This is Amendment 0004 to Solicitation N40085-26-R-9007 for repair work on Building AS4211 (Barracks/Enlisted Quarters) at Marine Corps Air Station New River, issued by NAVPAC Mid-Atlantic on January 20, 2026. The amendment extends the proposal due date to Friday, January 23, 2026 at 12:00 PM EST and replaces the pricing sheet from Amendment 0003. All other terms and conditions remain unchanged. Contractors must acknowledge receipt of this amendment with their proposal submission; failure to do so may result in rejection of the offer.

The pricing sheet contains nine line items (ELINs 0001-0009) requiring separate pricing for: general AS4211 repairs; lightning protection installation; sidewalk replacement (1,000 linear feet); asbestos-containing material removal in piping and HVAC systems (100 linear feet); asbestos-containing material removal in adhesives, flooring, and roofing (1,000 square feet); lead-based material removal per North Carolina requirements (1,000 square feet); unsuitable soil removal and replacement (200 cubic yards); unforeseen buried utilities removal and disposal (400 tons); and formal partnering services. All offers must include pricing for all nine line items with all applicable costs, overhead, and profit included. The Government will evaluate offers by adding prices across all ELINs for award purposes, though evaluation of options does not obligate exercise of any option.

View the file

Other files

File Type Posted
Amend 0006 250002.pdf PDF
Amend 0005.pdf PDF
Amend 0003 250002.pdf PDF
Amend 0002 250002.pdf PDF
Amend 0001 250002.pdf PDF
Dwgs 250002.pdf PDF
Spec 250002.pdf PDF
RFP 250002.pdf PDF
Paving Detail ELIN 0003.pdf PDF
Appendix D 250002.pdf PDF
Spec 28 31 76.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N40085-26-R-9007 Amendment 0004

CONTINUATION SHEET

1. Replace the Pricing Sheet provided in Amendment 0003 with the Pricing Sheet below.

2. All other terms and conditions remain unchanged.

Repair BEQ AS4211 Solicitation No. N40085-26-R-9007 MCAS New River Project No. 25-0002

PRICING SHEET

Under the line items furnished, the offers shall state prices for each Exhibit Line Item Number (ELIN) given hereinafter:

ELIN 0001

Price includes completing all work associated with repairs of AS4211 in accordance with the provided drawings and specifications, but excluding work described in ELIN 0002-0009. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0002

Price includes completing all work associated with installation of lightning protection in accordance with the provided drawings and specifications, but excluding work described in ELIN 0001, and 0003-0009. The price for this line item should include all applicable costs, overhead and profit for this work.

ELIN 0003

Price includes completing all work associated with replacement of sidewalks including demolition, sub-grade preparation, permits, and replacement (see detail A/CS501) but excluding work described in ELIN 0001-0002, 0004-0009. The price for this line item should include all applicable costs, overhead and profit for this work.

Quantity Unit Price Total

1,000 LF $_________ $___________________________________

ELIN 0004

Price includes completing all work associated with unforeseen asbestos containing material (ACM) (piping, pipe insulation, HVAC insulation, etc.). This includes identification, removal, wetting/handling, proper packaging, and disposal of ACM in accordance with all state/federal asbestos handling laws. This excludes work described in ELIN 0001-0003, 0005-0009. The price for this line item should include all applicable costs, overhead and profit for this work.

Quantity Unit Price Total

100 LF $_________ $___________________________________

ELIN 0005

Price includes completing all work associated with unforeseen asbestos containing material (ACM) (Adhesives, vinyl floor tiles, wall and ceiling insulation, roofing, etc.). This includes identification, removal, wetting/handling, proper packaging, and disposal of ACM in accordance with all state/federal asbestos handling laws. This excludes work described in ELIN 0001-0004 and 0006-0009. The price for this line item should include all applicable costs, overhead and profit for this work.

1,000 SF $_________ $___________________________________

ELIN 0006

Price includes completing all work associated with unforeseen lead removal. This includes identification, scraping/removal, encapsulation, handling, proper packaging, and disposal of lead based material per local requirements of North Carolina. This excludes work described in ELIN 0001-0005, and 0007-0009. The price for this line item should include all applicable costs, overhead and profit for this work.

Quantity Unit Price Total

1,000 SF $_________ $___________________________________

ELIN 0007

Price includes completing all work associated with removal, disposal, and replacement of unsuitable soil (non-contaminated) but excluding work described in ELIN 0001-0006, and 0008-0009. The price for this line item should include all applicable costs, overhead and profit for this work.

Quantity Unit Price Total

200 CY $_________ $___________________________________

ELIN 0008

Price includes completing all work associated with removal and disposal of unforeseen buried utilities (concrete duct banks, piping, cable, etc.), but excluding work described in ELIN 0001-0007, and ELIN 0009. The price for this line item should include all applicable costs, overhead and profit for this work.

400 TONS $_________ $___________________________________

ELIN 0009

Price includes completing all work associated with Formal Partnering, but excluding work described in ELIN 0001-0008. The price for this line item should include all applicable costs, overhead and profit for this work.

Quantity Unit Price Total 1 $_________ $___________________________________

TOTAL ELIN 0001 - 0009: $______________________________________

Notes A. Offers must be submitted on all line items. Failure to propose on all line items may result in the offer being rejected as non-responsive.

B. ELINs shall include all markups (overhead, labor burden, and profit).

C. Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR 17.206(b) Evaluation not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for ELINs 0001 through 0009. In accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).

File details come from the government source that posted it. Updated .