BUILDING REPAIRS, BUIILDING 530, DAM NECK ANNEX
Solicitation number
N4008526R0176
Issued by

About this file

This is Amendment 0001 to a Request for Proposal (RFP) for Building Repairs at NAS Oceana, Dam Neck Annex, Virginia Beach, Virginia, issued on 07 June 2026. The amendment comprehensively revises HVAC, fire protection, furnishings, and site work sections of the original solicitation.

The amendment establishes detailed requirements for HVAC system demolition and replacement, including removal of existing heating/ventilating systems, boilers, pumps, ductwork, and controls, with new installation of space heating hot water systems, pool dehumidification units, source capture exhaust systems, and Direct Digital Control (DDC) systems. Specific materials of construction are mandated, including fabric duct systems with 100% premium non-permeable polyester, heavy-gauge aluminum return air ductwork, and rigid PVC or polypropylene industrial duct for source capture exhaust. The amendment adds comprehensive commissioning requirements (Section D3080) requiring Testing and Adjusting and Balancing (TAB) by NEBB or AABC-certified contractors, pre-construction baseline verification including geotechnical assessment and pool water temperature monitoring, and functional performance testing of all systems. Training requirements include structured hands-on sessions for facility maintenance staff and two eight-hour sessions for the base fire department. Fire Protection Systems requirements (Section D40) mandate an integrated fire alarm and mass notification system with voice evacuation capability, addressable intelligent detectors, compatibility with existing base fire reporting systems using Monaco radios and Federal Signal radios for mass notification, and full sprinkler coverage with specific application rates for light and ordinary hazard areas. The amendment deletes previous furnishings requirements and adds comprehensive site preparation and site improvements sections addressing geotechnical investigation, topographic surveys, erosion and sediment control, utility coordination, and roadway pavement design for 50 years of anticipated traffic loads. Fire Protection Quality Control (FPQC) specialist surveillance requirements are detailed with specific inspection schedules for suppression systems, special suppression systems, passive fire protection, and fire alarm systems during construction, pre-final acceptance, and final acceptance phases.

View the file

Other files

File Type Posted
Amendment 0002 Scope of Work.pdf PDF
26R0176 AMENDMENT_0005.pdf PDF
Master PPI Spreadhseet OC530.pdf PDF
26R0176_AMENDMENT 0002.pdf PDF
Building DN 530 Flow Test.pdf PDF
Building DN530 Water Mains.pdf PDF
Master PPI Spreadsheet OC530 NAVFAC.pdf PDF
B530DNA_GIS Utility Site Plan.pdf PDF
26R0176 AMENDMENT_0001.pdf PDF
ATTACHMENT F_PPI_Spreadsheet.xlsx XLSX spreadsheet
ATTACHMENT A.pdf PDF
ATTACHMENT E.xlsx XLSX spreadsheet
N4008526R0176 GENERAL REQUIREMENTS.pdf PDF
ATTACHMENT G_PRICE SCHEDULE FORM.pdf PDF
ATTACHMENT B WD.pdf PDF
ATTACHMENT H - PIEE Vendor Access Instructions.pdf PDF
ATTACHMENT D SECNAV 5512.pdf PDF
ATTACHMENT C BASE ACCESS INSTRUCTION.pdf PDF
Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUILDING 530 – BUILDING REPAIRS

NAS Oceana, Dam Neck Annex, Virginia Beach VA

Amendment 0001

07 JUNE 2026

1) In PART 3, D30 HVAC:

Delete the following:

D30 HVAC, Demolition: – Delete entire section D30 HVAC, Demolition.

Add the following:

D30 HVAC

Demolition:

Demolish the existing heating and ventilating system (HV-1, HE-1, EF-1 & associated ductwork) serving the pool area, complete.

Demolish the supplemental pool air exhaust system (EF-5, EF-6, EF-7, EF-8, EF-9, EF-10), complete.

Demolish existing air-to-air heat exchanger (HE-2) and exhaust fan (EF-2 and EF-3) system and associated ductwork, complete.

Demolish existing heating and ventilating system serving the Locker Room/Shower and Lobby/Office areas (HV-2, HV-3, HV-4) and associated ductwork, complete.

Demolish space heating hot water boiler (B-20), associated gas train and associated space heating hot water pump(s) (P-9), complete (2008 ESPC-1 reference drawings). Demolish all space heating hot water piping and associated hydronic specialties, complete. Demolish heating hot water system air separator, expansion tank and chemical feed, complete.

Demolish each space heating hot water unit heater (UH-1 thru UH-4) and fin tube radiator (FT-1 thru FT-4) and associated balancing valves and control valves, complete.

Demolish existing Trane DDC system, complete.

Demolish air compressor and controls associated with hoist being demolished.

Demolition of ductwork includes associated GRD, supports & hangers and other associated air system components.

Patch all wall and roof penetrations left by removal of existing equipment, ductwork or piping.

See Architectural section C1010 for additional information.

2) In PART 3, D30 HVAC:

D30 HVAC, Existing to Remain: – Delete entire section D30 HVAC, Existing to Remain.

Existing to Remain:

Domestic hot water boiler (DHW-9), associated pump(s), storage tank, piping and hydronic specialties are existing to remain.

Pool water heating system (including steam boiler (B-19), shell & tube heat exchanger, pump, piping and associated hydronic specialties) are existing to remain.

The pool water filtration, pumping and treatment system is existing to remain.

All exhaust fans not identified to be demolished are existing to remain.

3) In PART 3, D30 HVAC, D3020 HEAT GENERATING SYSTEMS:

D30 HVAC, D3020 HEAT GENERATING SYSTEMS: – Delete entire section D30 HVAC, HEAT

GENERATING SYSTEMS.

D3020 HEAT GENERATING SYSTEMS

Space Heating Hot Water System Provide constant flow space heating hot water hydronic system, including all specialties required to comprise a complete system. All components must be new.

Space Heating Hot Water Boiler Provide space heating hot water boiler and gas train and connect to existing gas piping. Provide combustion air system. Provide calculations for ventilation air requirements. If existing ventilation air components are adequately sized according to DOR’s calculations, existing ventilation air components may be reused. If existing ventilation air components are not adequately sized, provide new.

Select space heating hot water boiler for loads from pool dehumidification unit, DOAS on low roof and new unit heaters and fin tube radiators.

Space Heating Hot Water Pumps Provide two pumps, one to act as primary and the other as standby. Alternate primary pump via DDC system.

Space Heating Hot Water Piping Provide space heating hot water piping to Pool Dehumidification Unit and DOAS on low roof.

Provide space heating hot water piping to all existing to be reused unit heaters and fin tube radiators.

Space Heating Hot Water Equipment Provide space heating hot water unit heaters (UH-1 thru UH-4).

Provide space heating hot water fin tube radiators (FT-1 thru FT-4).

Provide balancing valve and control valve for each space heating hot water unit heater and fin tube radiator.

Provide all hydronic specialties required for a complete and functioning system.

4) In PART 3, D30 HVAC, D3040 DISTRIBUTION & OTHER SYSTEMS:

Add the following at the end of the section:

Pitch and Drainage All duct runs that have any possibility of carrying internal condensation must be sloped (minimum 1/16” per foot) back toward the PDU or a designated low-point drain to prevent stagnant pooling of chlorinated condensation.

Materials of Construction

Fabric Duct System Duct fabric must be 100% premium non-permeable polyester.

Primary track and rails must be extruded heavy-duty anodized aluminum track (with a clear anodized architectural finish).

Cables, turnbuckles and cable grips must be grade 316 Stainless Steel (Type 316) or heavy-duty PVC-coated galvanized steel aircraft cable.

Slide hardware and connectors must be heavy-duty polymer, nylon or PVC sliders.

Return Air Ductwork Heavy-Gauge Aluminum (Grades 5052 or 3003).

Pre-Insulated Phenolic/Polyisocyanurate (PIR) Ductwork.

PVC-Coated G90 Galvanized Steel: Structural steel with a minimum 4-mil factory-applied PVC plastic coating on both the interior and exterior surfaces to isolate the steel core.

Hanger Galvanic Isolation Heavy-duty rubber, neoprene or nylon isolators/grommets must be installed between the aluminum return duct and any steel hanging rods to prevent galvanic (dielectric) corrosion.

Source Capture Exhaust Ductwork Rigid PVC (polyvinyl Chloride) or PP (Polypropylene) Industrial Duct.

Explicit Material Prohibitions Bare Galvanized Steel.

Type 304 Stainless Steel.

5) In PART 3, D30 HVAC, D3070 SYSTEMS TESTING AND BALANCING:

D30 HVAC, D3070 SYSTEMS TESTING AND BALANCING: – Delete entire section D30 HVAC, D3070 SYSTEMS TESTING AND BALANCING.

D3070 SYSTEMS TESTING AND BALANCING

Provide complete Testing and Balancing (TAB) of all air and water system components, including but not limited to the following:

• Pool Dehumidification System

• Source Capture Exhaust System

• DOAS (for Locker Room/Shower & Lobby/Office areas)

• Space Heating Hot Water System.

• DDC System

Provide pre-TAB for the following:

• Pool Water Heating System

• Domestic Hot Water System

• Pool Water Treatment System and Filtration System

• Existing to remain exhaust fans

6) After PART 3, D30 HVAC, D3070 SYSTEMS TESTING AND BALANCING:

D3080 COMMISSIONING

Dam Neck Building 530 1862885 Repair Building

- Natatorium Commissioning Statement of Work

SECTION 1: PROJECT OVERVIEW & GENERAL PROVISIONS

1.1 Purpose and Objective

The purpose of this Statement of Work (SOW) is to define the commissioning (Cx) and Testing, Adjusting, and Balancing (TAB) requirements for the Natatorium HVAC Renovation project. Bidding contractors shall include all labor, materials, equipment, and services necessary to fully support and execute the commissioning activities detailed herein.

1.2 Project Context & Boundaries

The renovation includes the mechanical, exhaust, heating, control, fire protection, and lighting systems serving the natatorium. The pool structure, building envelope (except as specified for roofing), and specific water systems remain unchanged.

Systems Being Replaced/Added (In-Scope for Cx):

• Pool Dehumidification System (PDS)

• Source Capture Exhaust System (SCES)

• Space Heating Hot Water System (boilers, pumps, valves, and piping)

• Direct Digital Control (DDC) System

• Fabric Supply Duct System

• Return Air System (All new return air ductwork and grilles)

• Fire Alarm and Detection System (Voice-evacuation, mass notification integration)

• Pool Area LED Lighting and Control System

• Roofing System (with Registered Roof Consultant oversight)

Existing Systems Remaining (Out-of-Scope / Baseline Only):

• Pool Water Heating System

• Domestic Hot Water System

• Pool Water Treatment and Filtration System

SECTION 2: PRE-CONSTRUCTION & PRE-TAB BASELINE

VERIFICATION

Because multiple critical systems and structural boundaries are existing to remain, the Contractor shall perform a rigorous pre-construction assessment and baseline verification prior to any demolition or installation of new equipment.

2.1 Geotechnical and Structural Verification

• Requirement: The Contractor’s geotechnical engineer shall verify that the existing concrete slab and subgrade can support the new, heavier pool dehumidifier unit.

• Commissioning Verification: Prior to approval for startup and functional performance testing, the

Commissioning Authority (CxA) must verify and document that this geotechnical report has been completed and that its physical structural recommendations are successfully implemented.

2.2 Roof Curbs & Penetration Coordination

• Requirement: The project incorporates a new roof installation, governed by a Registered Roof

Consultant (RRC).

• Commissioning Verification: The commissioning process shall verify that the RRC has formally approved the design and that the quality control program is strictly adhered to during construction.

Additionally, the CxA must perform a coordinated inspection of all rooftop HVAC interfaces, verifying that all roof curbs, ductwork penetrations, and equipment supports for the PDS and exhaust fans are installed according to the approved design so that the 10-year roof warranty is not voided.

2.3 Baseline Building Pressure Testing

• Requirement: Measure and document the existing static pressure relationship between the natatorium space, adjacent indoor spaces (e.g., locker rooms, corridors, offices), and the outdoors.

• Objective: Establish a precise pressure baseline to ensure that the new PDS and Source Capture

Exhaust systems maintain a continuous negative pressure environment (0.05 to 0.15 inches w.g.)

under all operating modes, preventing chloramine-laden air from migrating into adjacent spaces.

2.4 Envelope & Structural Inspection

• Requirement: Conduct a sensory and structural inspection of existing exterior window glazing, structural steel, and roof decks to document existing moisture or condensation damage. This serves as a baseline to protect all parties from disputes regarding preexisting conditions versus new system performance.

2.5 Pool Water Temperature Baseline

• Requirement: Measure and record the operating temperature of the existing pool water system over a 48-hour cycle.

• Frequency of Recording: Temperatures must be recorded automatically at 15-minute intervals throughout the 48-hour cycle to capture high-resolution diurnal and operational thermal shifts.

• Rationale: The new DDC system must be programmed with an understanding of this baseline, as the natatorium air temperature must be maintained at approximately 2°F above pool water temperature to control evaporation.

SECTION 3: TESTING, ADJUSTING, AND BALANCING (TAB)

REQUIREMENTS

The TAB Contractor shall be certified by NEBB or AABC and shall coordinate all activities with the Commissioning Authority (CxA).

3.1 Fabric Duct System Calibration

• Static Pressure Verification: Fabric supply air ducts require specific static pressure to inflate properly and distribute air evenly without flapping or sagging. TAB must calibrate the PDS supply fan speed to meet the exact static pressure requirements specified by the fabric duct manufacturer.

• Velocity Profile & Window “Wash”: Verify that the discharge velocities through the fabric orifices achieve the design “throw” to wash exterior glass and cold surfaces, thereby eliminating condensation risk without creating draft conditions at the pool deck level.

3.2 Source Capture Exhaust System Balancing

• Intake Velocity: Calibrate the source capture exhaust intakes to ensure designated airflow rates are achieved directly above the water surface to capture chloramines and heavy gases.

• Draft Prevention: Confirm that air velocities at the pool water surface and adjacent wet deck areas do not exceed 30 feet per minute (FPM) to avoid evaporative cooling and discomfort for swimmers.

3.3 Overall Space Pressurization

• Volumetric Balance: Balance the total supply air, outside air, PDS exhaust air, and Source Capture

Exhaust air volumes to maintain a continuous negative pressure between 0.05 and 0.15 inches w.g.

relative to adjacent spaces across all operational modes.

3.4 Acoustic Performance & MNS Intelligibility Verification

• Requirement: During the TAB phase, the CxA shall require sound level readings (Noise Criteria or NC levels) in the pool area with the PDS and exhaust fans running at maximum capacity.

• Objective: Ensure that background noise generated by the new HVAC system does not exceed levels that would prevent the Mass Notification System (MNS) from passing its required voice intelligibility testing, safeguarding clear communication of emergency broadcasts to building occupants.

SECTION 4: FUNCTIONAL PERFORMANCE & INTEGRATED

SYSTEMS TESTING (FPT)

The Contractor shall assist the Commissioning Authority in executing functional performance testing for all new equipment. Testing shall verify the dynamic response of the systems under simulated load conditions, emergency operations, and sequence transitions.

System / Test Area Functional Testing & Verification Requirements

Pool Dehumidification System (PDS)

Test transitions (Occupied, Unoccupied, Economizer, Purge), compressor & hot gas reheat staging, and relative humidity control (50–60% RH).

Source Capture Exhaust System

Verify VFD speed response & interlocks, and manual override operations.

Space Heating Hot Water System

Check boiler staging, pump lead/lag, hot water supply temp reset, and freeze protection sequences.

Direct Digital Controls

(DDC)

Conduct point-to-point sensor calibration, alarm routing & critical thresholds, and graphics verification.

Fire Alarm & Detection System

Functional testing of the new voice-evacuation fire alarm system, including all detectors, manual pull stations, and visual/audible notification appliances.

Test and verify base-wide communication of all alarm, supervisory, and trouble signals to the base fire alarm receiving station via the radio transceiver.

Lighting System Commissioning

Functionally test the new LED lighting control system to ensure it operates as designed (e.g., scheduling, dimming, occupancy sensing). Measure and verify actual light levels throughout the pool area after

System / Test Area Functional Testing & Verification Requirements installation to confirm compliance with design specifications.

Fire Alarm & HVAC Interlocks

Perform physical simulations of fire alarm events (e.g., triggering a smoke detector or manual pull station) to verify that the DDC system interfaces correctly with the fire panel. Confirm automatic HVAC shutdown sequences (PDS and SCES fan shutdown, damper closures to prevent smoke migration) and verify that systems do not automatically restart until the fire panel is reset.

Mass Notification System (MNS) & PA Integration

Verification that the fire alarm system correctly integrates with and can be overridden by the building‘s MNS. Test LED text signs and the modified PA system’s ability to broadcast emergency messages.

Verify functional connection of new wall-mounted speakers with existing building PA and two-way communication systems.

SECTION 5: OPERATIONS, TRAINING, AND DOCUMENTATION

5.1 Documentation, Warranties, and O&M Submittals

1. Provide complete, project-specific Operations and Maintenance (O&M) manuals for the PDS, Hot

Water System, DDC System, and Fire Protection/Life Safety Systems. General, non-specific manufacturer cut sheets are not acceptable.

2. Provide a certified final TAB report approved by the CxA.

3. Submit a 10-year special maintenance warranty for the new roofing system. The commissioning authority must verify that this document is submitted and meets all requirements (including bi-annual preventative maintenance visits) prior to project closeout.

5.2 Technical & Operational Training

The Contractor shall coordinate and conduct structured training sessions as follows:

Facility Maintenance Staff Training (Structured hands-on sessions):

• PDS Operations: Filter replacement schedules, compressor diagnostic procedures, and belt/motor maintenance.

• Fabric Duct Maintenance: Launder instructions, removal, and re-installation procedures.

• DDC Interface: Sequence scheduling, setpoint adjustments, sensor calibration, and emergency alarm response.

• Source Capture System: Periodic cleaning and system override operations.

Base Fire Department Training:

• Provide two separate eight-hour training sessions for the base fire department. The commissioning plan must track and verify that this training occurs and is formally documented.

Coordination with Base Contractors:

• All outages, tie-ins, and testing schedules must be coordinated with the existing NAS Oceana fire protection maintenance contractor. The commissioning plan must include this coordination as a verified activity.

7) In PART 3, D40 FIRE PROTECTION SYSTEMS:

D40 – Delete entire section D40.

D40 FIRE PROTECTION SYSTEMS

Refer to Part 4 Section D40 for performance requirements of the building elements included in the fire protection systems.

SYSTEM DESCRIPTION

Provide an integrated fire alarm and mass notification system and suppression system capable of notifying building occupants and controlling any fire that may start inside the facility.

Provide panic hardware on all new egress doors associated with the secure area to comply with all life safety requirements.

GENERAL SYSTEM REQUIREMENTS

The Contractor must be responsible to engage and coordinate ALL required Fire Protection related outages with the “existing NASO fire protection maintenance contractor”. The successful bid must include all associated costs and fees incurred by the “existing NASO fire protection maintenance contractor” to perform all required Fire Protection related outages for the project Provide working space around all equipment. Provide concrete pads under all equipment. Provide all required fittings, connections and accessories required for a complete and usable system.

Install equipment in accordance with the criteria of PTS section D40 and the manufacturer’s recommendations. Where the word "should" is used for manufacturer recommendations, substitute the word "must".

All Design Documents, (i.e. Building Code/Life Safety Analysis, plans, specifications, and calculations) developed for Section D40 must be prepared by, or under the supervision of the design/build contractor's Qualified Fire Protection Engineer, the Fire Protection Designer of Record (FPDOR). A Basis of Design and Life Safety analysis is required for this project.

Installation drawings, shop drawings or working plans, calculations, other required pre-construction documentation and as-built drawings must be prepared by, or under the direct supervision of a National Institute for Certification in Engineering Technologies (NICET) engineering technician as specified below. NICET engineering technicians must hold a current certification as an engineering technician in the field of Fire Protection Engineering Technology with Level III certification for fire sprinkler and Level IV for fire alarm and mass notification.

Provide training for the active systems consisting of two (2) eight (8)-hour sessions to accommodate all shifts of the base fire department and allow for rescheduling for unforeseen fire department responses.

Provide proper paintings and coatings and to protect metallic components exposed to higher chlorine environments.

D4010 FIRE ALARM AND DETECTION SYSTEMS

Provide an integrated fire alarm and mass notification system capable of notifying building occupants inside the facility. Provide a complete, electrically supervised, addressable intelligent, manual and automatic, annunciated fire alarm and detection system throughout the facility. Provide a voice evacuation type system that also serves as a mass notification system. Provide integrated systems capable of notifying building occupants by means of tones, strobes, text display signs, and live voice announcements. The integrated fire alarm and mass notification system (FA/MNS) must include fire alarm transmitter, MNS transceiver, antennas, and associated equipment to interface with existing base-wide fire reporting system and base-wide mass notification system. Demo any existing fire alarm and mass notification systems/components. Do not place any notification appliances or wiring circuits above pool. Modify current PA system to be disabled, via a fire alarm system relay module, during broadcast of any messages or tones by the fire alarm and mass notification system. Locate fire alarm panel in a conditioned space as approved by the Contracting Officer and NAVFAC FPE.

The fire reporting portion of the system must be compatible with the existing base fire reporting system. The fire reporting system uses Monaco radios.

The integrated system must be capable of receiving mass notification messages from the base-wide emergency management system (mass notification system) and rebroadcasting messages over the building speakers. Prerecorded messages must be provided for the fire alarm and carbon monoxide evacuation system. Existing base-wide mass notification system uses Federal Signal radios.

Provide a complete and useable fire alarm system including manual stations, system smoke detectors, duct smoke detectors, audio/visual alarms, fire alarm radio transmitter, electrical supervision of all sprinkler system alarm and supervisory devices.

Provide a fire alarm control panel capable of handling a minimum of 500 individually identified sensors within the main control panel. Provide Class B Notification Appliance Circuits, Class A Signaling Line Circuits, and Class B Initiation Device Circuits. Any Initiation Device Circuits must be less than 10 feet in length. Provide back-up amplifiers for combination fire alarm/mass notification systems.

Provide semi-flush and surface mounted manual pull stations.

Provide a remote annunciator (RA) located in the Lobby. Provide a Local Operator Consoles (LOC Emergency Microphone), in a non-lockable cabinet, for the mass notification system in the Pool area and in the Lobby. The LOC must include a microphone for live message only. The fire alarm panel must also include a microphone. The LOC must not include any buttons for pre-recorded messages. The remote annunciator and LOC’s must be located as directed by the Contracting Officer in conjunction with the cognizant NAVFAC Fire Protection Engineer.

Text display signs must be provide at all exit doors.

Coordinate with Electrical to modify the existing PA system to function as described herein. Any portion of the fire alarm and mass notification system located in areas susceptible to moisture presence must be enclosed with weather-proof or water-resistant system. These include panels, junction boxes, and conduit/raceway system being utilized.

Provide a high-fidelity loudspeaker system to provide emergency messages in the pool area to provide a minimum CIS score of 0.7. Voice paging and tone signaling loudspeaker must be UL 1480 listed, weather resistant and constructed of powder coated aluminum and steel and suitable for the pool environment. The loudspeaker must be able to operate within any ambient temperature environment ranging from -4 degree F to 140 degrees F. The speaker must have a horizontal beam width of 187 inches (AVG 1kHz to 4kHz). The transducer coils must have a nominal 8 ohm impedance. When applicable, a minimum of four transformer power settings must be selectable for each speaker, and it must operate on 25V, 70V, or 100V distributed audio systems. Transformers must contain an in-line capacitor to allow DC supervision of wiring. Frequency response must be 250kHz-15kHz. Speaker manufacturer must provide design for loudspeaker system and must be submitted with fire alarm system shop drawings.

Provide explosion devices and raceways as needed.

Provide carbon monoxide detectors as required. Mount CO detectors at 7 feet above floor.

Fire alarm signals must be sent to the fire alarm receiving station via the radio transmitter. Provide a dedicated power for fire alarm and mass notification systems via coordination with Electrical.

All fire alarms, supervisory alarms and trouble conditions indicated at the fire alarm control panel must be transmitted to the fire alarm receiving station. Transmitter zones must be as follows:

a. Fire Alarm

b. Supervisory

c. Trouble

d. Duct Smoke Detector

e. CO Detector

D4020 FIRE SUPPRESSION WATER SUPPLY AND EQUIPMENT –

Water Flow Test Data for Reference and bidding purpose only: Part 6 (Attachments) includes a site schematic and locations of hydrants where readings were recorded. On June 7, 2026 a static pressure of [????] psi and a residual pressure of [????] psi at [???? ] gpm were measured at Fire Hydrant # 519, the first hydrant west of Terrier Avenue on the north side of Sparrow Street.

Base hydraulic calculations at the junction with the water distribution piping system. The water supply information provided in the RFP is for bidding purposes only. The project FPDOR must conduct additional water flow tests after the contract award for design submissions and shop drawing submittals. Water flow test must be conducted at about the same time of the day as indicated in the Gov’t flow test data.

Locate the FDC on the front face of building.

Provide the incoming sprinkler service with a reduced pressure principle backflow preventer.

D4040 SPRINKLERS

Provide wet pipe automatic sprinkler protection to provide complete coverage throughout the building, including the lower level.

For light hazard areas the sprinkler rate of application must be 0.1 gpm/ft2, over an area of 1,500 with a hose stream allowance of 250 gpm. For ordinary hazard areas the sprinkler rate of application must be 0.2 gpm/ft2, over an area of 2,500 with a hose stream allowance of 250 gpm.

Provide quick-response recessed sprinklers with ordinary temperature rating in areas with finished ceilings. Provide corrosion resistant white polyester finish sprinklers in all areas of the building with matching escutcheon plates for spaces with drop ceilings.

Fire sprinklers above the pool surface area may be omitted as permitted by NFPA 13. Do not route sprinkler piping above pool surface.

D4090 OTHER FIRE PROTECTION SYSTEMS – NOT APPLICABLE

8) In PART 2, 01 4500.05 20:

INSTRUCTION for FPQC Specialist and PERFORM SURVEILLANCE DURING CONSTRUCTION from page 24 to 28.

1. INSTRUCTIONS for FPQC Specialist:

Perform surveillance of fire protection system installation during construction and during pre-final and final acceptance inspections. Surveillance includes either visual inspections or observations performed by the FPQC as indicated in the following Schedule of Fire Protection System Inspections. Check boxes in the schedule indicate the inspections or observations that are applicable to this project, which must be performed and documented by the FPQC.

Surveillance of fire protection system inspections is divided into three phases:

Surveillance During Construction – Includes periodic on-site visits by the FPQC during construction Pre-Final Acceptance Inspection – FPQC must be onsite during pre-final acceptance inspection Final Acceptance inspection – FPQC must be onsite during final acceptance inspection

2. INSPECTION TYPE

VISUAL INSPECTION:

Perform on-site visual inspections as indicated in the Schedule of Fire Protection System Inspections as construction progresses to confirm work conforms with the contract requirements including but not limited to verifying proper installation of equipment and materials in accordance with applicable codes. Where work will be covered up by finished walls and ceilings, inspections must be scheduled and performed when work is still visible.

OBSERVATION:

Observe component and system testing in person on-site as indicated in the Schedule of Fire Protection System Inspections. Confirm testing is completed in accordance with applicable codes and that testing was successful.

DOCUMENTATION:

Document all inspections and observations in the FPQC Report in accordance with UFGS 01 45 00. Document any deficiencies and all work observed that has been successfully performed in accordance with the contract documents. Record deficiencies in the rework list.

PERFORM SURVEILLANCE DURING CONSTRUCTION

~ FIRE SUPPRESSION SYSTEM ~

PERFORM

TASK IF

CHECKED

TASK INSPECTION

TYPE DESCRIPTION

☒ 1. Verify proper installation of underground service main and service; laterals, thrust blocks, tie-rods and connection to above ground piping.

VISUAL

INSPECTION

Visually inspect materials Visually inspect installation

☒ 2. Verify proper orientation of fire hydrants and fire department access

VISUAL

INSPECTION

Visually inspect installation and orientation

☐ 3. Verify proper installation of interior and exterior attachments, coatings, and vortex plate prior to filling fire protection water tank

VISUAL

INSPECTION

Visually inspect fire protection water tank installation

☒ 4. Hydrostatic/leak test for underground piping

OBSERVE Verify proper test method Confirm test was successful

☒ 5. Hydrostatic/leak test for above ground piping prior to ceiling installation

OBSERVE Verify proper test method Confirm test was successful

☒ 6. Underground system flush prior to connection to the riser

OBSERVE Verify system was properly flushed

☒ 7. Forward flow test for Backflow preventer

OBSERVE Verify proper test method Confirm test was successful

☐ 8. Suction pipe flush prior to fire pump startup

OBSERVE Verify system was properly flushed

☐ 9. Hydrostatic test fire pump suction and discharge piping

OBSERVE Verify proper test method Confirm test was successful

☐ 10. Fire pump startup OBSERVE Confirm successful startup

☒ 11. Verify proper installation of sprinkler piping prior to wall or ceiling installation

VISUAL

INSPECTION

Inspect pipe hangars, bracing, sprinkler heads

Inspect for sprinkler obstructions;

damaged, painted or covered heads

Verify proper location of control valves, drains, vents, backflow, test header

Verify proper component mounting heights

☒ 12. Document inspections and observations in FPQC Report

DOCUMENT Submit report for each day inspections or observations occur

Annotate deficiencies and satisfactory work observed

Record rework items in FPQC report

~ SPECIAL FIRE SUPPRESSION SYSTEM ~

PERFORM

TASK IF

CHECKED

TASK INSPECTION

TYPE DESCRIPTION

☐ 1. Verify proper installation of gaseous fire suppression system

VISUAL

INSPECTION

Inspect gas cylinders, initiating controls, shutdowns, aborts, and visual warning

☐ 2. Verify proper installation of IR hangar detector

VISUAL

INSPECTION

Inspect detector and nozzle layout Inspect for obstructions, abort stations Inspect riser piping

☐ 3. Verify proper installation of elevator fire protection

VISUAL

INSPECTION

Inspect elevator recall functions Inspect two-way communication

☐ 4. Verify proper installation of fire suppression in secure spaces

VISUAL

INSPECTION

Inspect location of sprinkler piping and sprinklers

☒ 5. Document inspections and observations in FPQC Report

DOCUMENT Submit report for each day inspections or observations occur

Document deficiencies and satisfactory work observed in FPQC Report

Record deficiencies in rework list

~ PASSIVE FIRE PROTECTION SYSTEMS ~

PERFORM

TASK IF

CHECKED

TASK INSPECTION

TYPE DESCRIPTION

☒ 1. Verify proper construction of fire rated assemblies

VISUAL

INSPECTION

Inspect partitions for proper fire rated construction per design

Inspect doors and door hardware for proper fire rating

Inspect glass for proper fire rating ☐ 2. Verify proper installation of fireproofing

VISUAL

INSPECTION

Inspect for use of proper fireproofing materials

Inspect for cracking, spalling or delaminating

Inspect for proper application thickness

☒ 3. Verify proper installation of firestopping

VISUAL

INSPECTION

Inspect to confirm firestopping system is UL tested or an engineering judgement has been obtained and submitted

Inspect for use of proper firestopping materials

Inspect penetrations through fire rated walls, partitions and ceilings

Inspect construction joints and gaps ☒ 4. Document inspections and observations in FPQC Report DOCUMENT Submit report for each day inspections or observations occur Document deficiencies and satisfactory work observed in FPQC Report

Record deficiencies in rework list

~ FIRE ALARM SYSTEMS ~

PERFORM

TASK IF

CHECKED

TASK INSPECTION

TYPE DESCRIPTION

☒ 1. Verify proper installation of fire alarm system after conduit is installed and wiring pulled, but before devices are installed

VISUAL

INSPECTION

Inspect conduit, wiring, conduit fill, wire type

Inspect installation heights of back boxes

☒ 2. Document inspections and observations in FPQC Report

DOCUMENT Submit report for each day inspections or observations occur

Document deficiencies and satisfactory work observed in FPQC Report

Record deficiencies in rework list

~ END OF SURVEILLANCE DURING CONSTRUCTION SECTION

PERFORM DURING PRE-FINAL ACCEPTANCE INSPECTION

PERFORM

TASK IF

CHECKED

TASK INSPECTION

TYPE DESCRIPTION

☒ 1. Inspect all fire protection systems and all life safety features

VISUAL

INSPECTION

Verify proper installation of fire protection and life safety systems

☒ 2. Witness functional testing of all fire protection and life safety systems

OBSERVE Verify proper testing is performed on fire protection and life safety systems

☒ 3. Identify deficiencies that require correction

VISUAL

INSPECTION

Document deficiencies in FPQC Report and record in rework list

☒ 4. Verify rework items have been corrected

VISUAL

INSPECTION

Record re-inspection results on FPQC Report

☒ 5. Document results of pre-final inspection and photograph unsatisfactory conditions

DOCUMENT Document results of pre-final inspection in FPQC Report

☒ 6. Certify installation and operation of all fire protection and life safety systems conform to the contract documents

DOCUMENT Provide separate letter certifying conformance with contract requirements

~ END OF PRE-FINAL INSPECTION SECTION

PERFORM DURING FINAL ACCEPTANCE INSPECTION

PERFORM

TASK IF

CHECKED

TASK INSPECTION

TYPE DESCRIPTION

☒ 1. Verify proper installation and operation of all fire protection systems and all life safety features

VISUAL

INSPECTION

☒ 2. Note any deficiencies identified by Government FPE on deficiency list

DOCUMENT Document deficiencies identified by Government FPE on deficiency list

☒ 3. Verify all deficiencies have been corrected

VISUAL

INSPECTION

Inspect rework to confirm all deficiencies have been corrected

☒ 4. Certify that all deficiencies have been corrected

DOCUMENT Document inspection results on FPQC Report

~ END OF FINAL ACCEPTANCE INSPECTION SECTION

9) FOLLOWING DOCUMETS ISSUED WITH AMENDMENT 0001:

a) Building DN 530 Water Mains

b) Building DN 530 Flow Test

c) Building DN 530 GIS Utility Site Plan

10) Part 3, E20 FURNISHINGS

INTERIOR DESIGN REQUIREMENTS

Furnishings include fixed furnishings the design and documentation of the movable furnishings, the Furniture, Fixtures, and Equipment (FF&E) Concept Package. Refer to ATTACHMENT 6.

Furnishing will be provided by others and not part of this contract.

The design and documentation of both will be funded as a separate contract. The purchase and installation of the FF&E Package will be funded separately. Contractor to coordinate and provide FF&E power and data requirements with FF&E installer.

The movable furniture and furnishings (FF&E) for this facility may include, but are not limited to movable furniture systems and freestanding furniture.

The Audio Visual (AV) Equipment is part of this Package. Refer to Part 3 Section E1090 of this

RFP.

11) In PART 3, G10 SITE PREPARATION:

G10 – Delete entire section G10.

Add the following:

G10 SITE PREPARATION

Refer to Part 4 Section G10 for performance requirements of the site elements included in the civil site and site utility work.

SYSTEM DESCRIPTION

The site preparation activities consist of site clearing, demolition, salvage, relocation, earthwork, and hazardous waste remediation to ready the site for other work associated with the project.

GENERAL SYSTEM REQUIREMENTS

Develop the project site and perform off-site work necessary to meet the requirements of the project, local codes, reference standards, technical specifications and performance criteria.

Perform a topographic survey of the project area that will be impacted by the work in accordance with FC 1-300-09N, Navy and Marine Corps Design Procedures. Include the topographic survey in all design submittals. The existence, size, and location of the utilities are not guaranteed by the provided site plans. Verify the location of all utilities prior to construction.

Unless otherwise noted, provide new facilities at the locations indicated on the drawings in Part 6.

Minimize the impact of construction activity on operations and neighboring facilities.

Identify and obtain permits to comply with federal, state, and local regulatory requirements associated with the work. Submit a complete Permits Record of Decision (PROD) form with the first design submittal package. Determine correct permit fees and pay said fees. Forward copies of permits, permit applications, and the completed PROD form to the Government's Civil Reviewer and Environmental Reviewer. Perform work in accordance with the obtained permits.

Jurisdictional tidal and non-tidal wetlands have not been identified on the project site.

Coordinate and obtain the Contracting Officer's approval for proposed haul route(s), work site access point(s), employee parking location(s) and material laydown and storage area(s).

Refer to Site Analysis and Building Requirements Sections for additional site preparation functional program information.

Anticipate minor variations in subsurface conditions between borings. The Contractor is responsible for costs associated with the site preparation, ground improvement and foundations except as allowed by Contract Clause Federal Acquisition Regulation (FAR) 52.236-2, "Differing Site Conditions". The Contractor's Geotechnical Engineer must perform subsurface investigation / testing as required to adequately determine geotechnical factors including the type and capacity of the pipe bedding material. The Contractor's Geotechnical Engineer is required to evaluate the information obtained and prepare a report as described in other portions of this RFP. The minimum requirements for the subsurface investigation and report are as required by FC 1-300- 09N with associated references.

Perform the soils investigation at the site for use in the design and construction of the new facilities. Perform, at Contractor's expense, subsurface exploration, investigation, testing, and analysis for the design and construction of features such as the pavement section(s) and utility structure foundations. Prepare a report including laboratory analysis of samples and recommendations for foundation and pavement design by a Professional Engineer as specified and in accordance with UFC 3-201-01, Civil Engineering.

As a minimum, the successful bidder's Geotechnical Engineer must perform additional subsurface exploration and supplementary laboratory testing as necessary to support the design concept.

Observed site conditions which may present a challenge during design/construction include - The soils that will be exposed after completion of stripping will be soft and at or near the groundwater elevation. Anticipate these marginal subgrade support conditions and incorporate measures into the design and construction procedures to obtain required soil support while maintaining progress for completion on schedule.

Provide personnel under the supervision of a registered Professional Engineer to inspect excavations and soil/groundwater conditions throughout construction. The Engineer is required to perform pre-construction and periodic site visits throughout construction to assess site conditions. The Engineer, with the concurrence of the Contractor and the Contracting Officer, is required to update the excavation, sheeting, shoring and dewatering plans as construction progresses to reflect actual site conditions and is required to submit the updated plan and a written report (with professional stamp) at least monthly informing the Contractor and Contracting Officer of the status of the plan and an accounting of Contractor adherence to the plan;

specifically addressing any present or potential problems. The Engineer must be available to meet with the Contracting Officer at any time throughout the Contract duration. Provide the services of the Engineer at no additional cost to the Government. It is important to note that the presence of loose or compressible soils may result in excessive settlement that could impact the performance of surface bearing structures and supporting facilities such as pavements and utilities. The magnitude and duration of consolidation settlement will be dependent on the composition, depth, and thickness of the compressible soils as well as the successful bidder's design concept. The Contractor's Geotechnical Engineer is responsible for evaluating potential global settlement due to designed grade increases and final structural loads. The Contractor's Geotechnical Engineer must develop any settlement mitigation procedures (such as preloading, surcharging, fill monitoring programs, and ground improvement systems) needed to maintain global settlements within tolerable limits.

G1010 SITE CLEARING

Install erosion and sediment control devices prior to beginning clearing operations.

If approved by the Government, clearing may be allowed to accommodate construction equipment within the designated construction laydown area.

The project site does not have saleable timber.

Waste materials will become the property of the Contractor; transport, dispose of or recycle waste materials in accordance with Part 2 Section 01 57 19, Temporary Environmental Controls.

G1020 SITE DEMOLITION & RELOCATIONS

Preserve the following aboveground site elements: pavements to remain: paved asphalt parking and driveway to maximum practicable extent; underground site elements: existing utilities to remain: existing utilities required for project that remain undisturbed.

Existing utilities include but are not limited to piping, structures and conduits.

Remove utilities as indicated on the drawings in Part 6. Remove all appurtenances associated with the utility to be removed so there is no presence of the utility at ground surface.

G1030 SITE EARTHWORK

Provide grading so the site will drain. Blasting for rock excavation will not be permitted.

Provide materials required in excess of those resulting from excavations from off Government property.

All unsuitable material and surplus excavation must become the property of the Contractor and must be disposed of off Government property.

12) In PART 3, G20 SITE IMPROVEMENTS:

G20 – Delete entire section G20.

Add the following:

G20 SITE IMPROVEMENTS

Refer to Part 4 Section G20 for performance requirements of the site elements included in the civil site and site utility work.

SYSTEM DESCRIPTION

Provide site improvements that support project sustainability goals of& Part 2 UFGS Section 01 33 29, Sustainability Requirements and Reporting.

The site improvements consist of pavements and pavement related features, landscaping and other exterior site development work related to this project. Provide a pavement design by a licensed Professional Engineer familiar with conditions local to the project site. Site design, including but not limited to design of parking and pedestrian circulation, will include coordination with the Civil Engineer and the Landscape Architect.

GENERAL SYSTEMS REQUIREMENTS

Provide site improvements as required to make a useable facility that meets functional and operational requirements, incorporates all applicable anti-terrorism, force protection and physical security requirements and blends into the existing environment.

Provide accessibility in conformance with requirements of UFC 1-200-01 , DoD Building Code (General Building Requirements).

Identify and obtain permits to comply with federal, state, and local regulatory requirements associated with this work. Complete the Permits Record of Decision (PROD) form with the first design submittal package. Determine correct permit fees and pay said fees. Forward copies of permits, permit applications, and the completed PROD form to the Government's Civil Reviewer.

Perform work in accordance with the obtained permits.

Minimize the impact of construction activity on operations and neighboring facilities.

Locate new site improvements at locations indicated on the drawings in another part of this RFP.

https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01

If specific locations are not provided, site the improvements to develop appropriate and positive relationships with other facilities and to conform to existing development patterns.

Refer to Site Analysis and Building Requirements Sections for additional site improvement functional program information.

G2010 ROADWAYS

The design of pavement repair must take into consideration the anticipated daily traffic (50 cars, 12 single unit trucks, 4 H20 loadings) over the life of the project (25 years) as well as the existing soil conditions at the site.

Provide roadways of bituminous pavement as required to match existing along the limits of work as required to provide a new 8” water line and demolition of the existing 6” water line as indicated on the drawings in Part 6. Permeable pavement must not be used. Aggregate pavement may not be used.

Provide curb and gutter as required to tie into adjacent facilities based on the contractor’s limits of construction.

Upon completion of water line installation and demolition, provide resurfacing of existing pavement by mill and overlay bituminous pavement, full width of the drive aisle, 24’±.

13) Provide other roadway improvements including pavement markings, etc. to match existing.

**End of Amendment 0001**

Dam Neck Building 530 1862885 Repair Building - Natatorium Commissioning Statement of Work
SECTION 1: PROJECT OVERVIEW & GENERAL PROVISIONS
1.1 Purpose and Objective
1.2 Project Context & Boundaries
SECTION 2: PRE-CONSTRUCTION & PRE-TAB BASELINE VERIFICATION
2.1 Geotechnical and Structural Verification
2.2 Roof Curbs & Penetration Coordination
2.3 Baseline Building Pressure Testing
2.4 Envelope & Structural Inspection
2.5 Pool Water Temperature Baseline
SECTION 3: TESTING, ADJUSTING, AND BALANCING (TAB) REQUIREMENTS
3.1 Fabric Duct System Calibration
3.2 Source Capture Exhaust System Balancing
3.3 Overall Space Pressurization
3.4 Acoustic Performance & MNS Intelligibility Verification
SECTION 4: FUNCTIONAL PERFORMANCE & INTEGRATED SYSTEMS TESTING (FPT)
SECTION 5: OPERATIONS, TRAINING, AND DOCUMENTATION
5.1 Documentation, Warranties, and O&M Submittals
5.2 Technical & Operational Training