This is a Questions and Answers document from the RFP for a Naval Station Newport water/wastewater infrastructure divestiture project. The document addresses a single question regarding base access requirements for site visit participants.

The Q&A clarifies that current Common Access Card (CAC) holders are not required to complete the base access form for site visits. However, the response notes that CAC holders may still be required to provide additional information or documentation to Installation security before being granted entry to the facility.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Question: If a site visit participant is a current Common Access Card (CAC) holder, do they need to fill out the Base Access Form?

Answer: Those who hold an active CAC are not required to complete the access form at this time, however, all CAC holders could be subject to provide additional information and/or documentation by Installation security prior to entry.