Amendment 06.pdf
PDF 335 KB Posted
- Solicitation number
- N4008525R2605
About this file
This document is an Amendment (Amendment 0006) to Solicitation N4008525R2605 for a de-leading and repair project at Rodriguez Range on Joint Expeditionary Base Little Creek - Fort Story in Virginia Beach, Virginia. The amendment addresses a Pre-Proposal Inquiry (PPI) submitted on March 27, 2025, specifically focusing on soil classification for CLINs 0001C and 0001D. The contractor requested clarification on whether removed soil material should be classified as "Contaminated" (less than 5 parts per liter TCLP tested) or "Hazardous Contaminated", as the disposal cost difference is approximately 400% (4-5 times higher for hazardous contaminated soil). The government response directs the contractor to refer to Section 01 57 19.01 20 paragraph 1.3.1.4.4 for further guidance. The solicitation is restricted to contractors on NAVFAC Mid-Atlantic Small Business Multiple Award Construction Contract (MACC) ML-C00081.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 10.pdf | ||
| Amendment 09.pdf | ||
| Amendment 05.pdf | ||
| Amendment 08.pdf | ||
| Amendment 07.pdf | ||
| Amendment 04.pdf | ||
| Amendment 03.pdf | ||
| General Requirements- Rodriguez Range-De-lead and Repair Berms.pdf | ||
| Amendment 02..pdf | ||
| Amendment 01_ckj.pdf | ||
| Attachment A - Specifications.pdf | ||
| Attachment B - Drawings.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
7. ADMINISTERED BY (If other than Item 6) CODE
STANDARD FORM 30 (REV. 11/2016)
Prescribed by GSA FAR (48 CFR) 53.243
FACILITY CODE
9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
12. ACCOUNTING AND APPROPRIATION DATA (If required) copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
15C. DATE SIGNED
15A. NAME AND TITLE OF SIGNER (Type or print)
16C. DATE SIGNED
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
PAGE OF PAGES
6. ISSUED BY CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X)
CODE
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
Previous edition unusable
2. AMENDMENT/MODIFICATION NUMBER
N40085
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
LC-U33-Rodriguez Range-De-lead and Repair Berms on Outdoor Ranges, Joint Expeditionary Base, Little Creek - Fort Story (Little Creek Site), Virginia Beach, Virginia.
The purpose of this amendment is to provide response to PPI submitted March 27, 2025 (see attached)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
NAVFACSYSCOM MID-ATLANTIC
PWD LITTLE CREEK
FACILITIES ENGINEERING & ACQ DIV
1450 GATOR BLVD
VIRGINIA BEACH VA 23459-8616
SEE ITEM 6
ACQR 6021397
N4008525R2605
03/27/2025
02/13/2025
Chirine Johnson, Contract Specialist
3/27/2025
X
Page Section Para.
3/27/2025 Price Sheet 1C / 1D
In order to responsibly price CLIN‐0001C and CLIN‐ 0001D, the contractor must know if removed soil material is classified as Contaminated or Hazardous Contaminated. For the material to classified as
Contaminated it must have less than 5 parts per liter TCLP tested. The cost of contaminated soil disposal verses hazardous contaminated soil disposal is approximately 400 percent or 4 to 5 times as much for hazardous contaminated soil disposal. Please issue another amendment to classify the soil material to be removed as Contaminated or hazardous contaminated.
See Section 01 57 19.01 20 paragraph 1.3.1.4.4 0006
Amend No.
RFI
No.
Date Submitted
REFERENCE
QUESTION GOVERNMENT RESPONSE
PPIs - Amendment 0006