This document is a specification section (Section 01 45 00) for Quality Control requirements for a Naval Building P-1334 Child Development Center construction project. The specification outlines comprehensive quality control procedures for the contractor, including requirements for:

Quality Control (QC) Manager qualifications, with a minimum of a bachelor's degree in engineering and 10 years of construction experience, responsible for implementing a three-phase control system covering all construction work. Key responsibilities include maintaining daily inspection logs, conducting quality control meetings, performing preparatory, initial, and follow-up phases of work, managing deficiency tracking, and ensuring compliance with contract requirements. The QC Manager must provide certifications, maintain documentation, and coordinate with government representatives throughout the project, with specific emphasis on testing, documentation, and maintaining high standards of workmanship across all construction activities.

View the file

Other files

File Type Posted
AMENDMENT 0008- 25R2527.pdf PDF
AMENDMENT 0007- 25R2527.pdf PDF
1782837Amend0006dwg_P1334CDC.pdf PDF
AMENDMENT 0006 - 25R2527.pdf PDF
AMENDMENT 0005 - 25R2527.pdf PDF
1782837Amend0004dwg_P1334CDC.pdf PDF
1782837Amend0004spec_P1334CDC 1-2.pdf PDF
JA ML 25-47 P1334 Brand Name or Equal Interior Finishes - Redacted.pdf PDF
AMENDMENT 0004 - 25R2527.pdf PDF
P1334 Price Schedule_Blank- rev1 072125.docx DOCX document
AMENDMENT 0003 - 25R2527.pdf PDF
Class JA ML 25-30 FRCS Standardization NSN_Redacted.pdf PDF
AMENDMENT 0002 - 25R2527.pdf PDF
AMENDMENT 0001 - 25R2527.pdf PDF
P1334 Site Visit Log - Completed.pdf PDF
ATTACHMENT A14 - 1782837dwg13of14.pdf PDF
ATTACHMENT A8 - 1782837dwg07of14.pdf PDF
25R2527 General Requirements .pdf PDF
ATTACHMENT A15 - 1782837dwg14of14.pdf PDF
ATTACHMENT A9 - 1782837dwg08of14.pdf PDF
ATTACHMENT A10 - 1782837dwg09of14.pdf PDF
ATTACHMENT A13 - 1782837dwg12of14.pdf PDF
ATTACHMENT A11 - 1782837dwg10of14.pdf PDF
ATTACHMENT A7 - 1782837dwg06of14.pdf PDF
ATTACHMENT A2 - 1782837dwg01of14.pdf PDF
ATTACHMENT A5 - 1782837dwg04of14.pdf PDF
ATTACHMENT A12 - 1782837dwg11of14.pdf PDF
ATTACHMENT A6 - 1782837dwg05of14.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Naval Building P-1334 - Child Development Center 60715453

MISC. REVISIONS

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

11/20, CHG 3: 08/23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map

Progress and Completion Pictures

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, SECTION 01 30 00 Page 1 July 9, 2025 during the entire period of performance under this contract. Provide other insurance coverage as required by State law.

1.6 SUPERVISION

1.6.1 Superintendent Qualifications

Provide project superintendent with a minimum of 10 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

1.6.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work. In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.6.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.6.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.7 PRECONSTRUCTION MEETING

Immediately after award, prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting. The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, SECTION 01 30 00 Page 2 submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.7.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NAVFAC Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:

1.8.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

1.8.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.

At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

1.9 PARTNERING

To most effectively accomplish this Contract, the Contractor and

SECTION 01 30 00 Page 3

Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

1.9.1 Facilitated (Formal) Partnering

a. Within 35 calendar days after award and prior to the start of work, host a Formal Partnering session with key personnel from the project team including both Contractor and Government personnel. All costs associated with the Partnering session including the third-party independent Facilitator Consultant, meeting room and other incidental items are the responsibility of the Contractor.

b. Before the Facilitated (Formal) Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note pads, pens/pencils, colored flash cards) and have these items available at the Partnering session. Provide copies of any documents required for distribution to all attendees. Participants will bear their own costs for meals, lodging and transportation associated with Partnering.

c. The Initial Partnering Session must be a duration of one day and be held at a location off base as agreed to by the Contracting Officer.

Partnering session may take place concurrently with the Pre-Construction Post-Award Kickoff Meeting.

d. Facilitator must be experienced in conducting corporate Partnering sessions and must be a third-party independent facilitating consultant

- not an employee of the Contractor. The Facilitator is responsible for leading all aspects of the Partnering session necessary to achieve the Partnering goal.

e. An outcome of the Partnering session must be an escalation matrix agreed upon by both the Government and Contractor, which identifies key Government and Contractor decision makers by name and anticipated decision durations.

f. Host follow-on Partnering Sessions at three- to six-month intervals or more frequently if needed and lasting generally a half day or less.

Attendees need only be those required to resolve current issues. The same Facilitator used in the Initial Partnering session must lead the follow-on sessions unless an alternative is permitted by the Contractor Officer. All costs associated with follow-on Partnering sessions are the responsibility of the Contractor.

1.10 MOBILIZATION

Contractor shall mobilize to the jobsite within 60 calendar days after contract award. Mobilize is defined as having equipment AND having a physical presence of at least one person from the contractor's team on the jobsite.

SECTION 01 30 00 Page 4 July 9, 2025 jodi.long Polygon

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

-- End of Section --

SECTION 01 30 00 Page 5

SECTION 01 30 02.00 22

DESIGN, PROCUREMENT, AND INSTALLATION OF AUDIOVISUAL EQUIPMENT

06/25

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AUDIOVISUAL AND INTEGRATED EXPERIENCE ASSOCIATION (AVIXA)

D401.01:2023 Documentation Requirements for Audiovisual Systems

F501.01:2015 Cable Labeling for Audiovisual Systems

202.01:2016 Display Image Size for 2D Content in Audiovisual Systems

A102.01:2022 Audio Coverage Uniformity in Listener Areas

F502.02:201X Rack Design for Audiovisual Systems

V201.01:2021 Image System Contrast Ratio

S601.01:2021 Energy Management for Audiovisual Systems

10:2013 Audiovisual Systems Performance Verification

RP-38-17 Recommended Practice for Lighting Performance for Small to Medium Sized Videoconferencing Rooms

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for Contractor Quality Control approval. The following shall be submitted in accordance with Section

01 33 00 SUBMITTAL PROCEDURES:

SD-02 Shop Drawings

AV Basis of Design; G, PDC44 NAVFAC MIDLANT Electrical Engineering

Pre-Final Best Value Determination (BVD) RFQ Package; G, PDC44 NAVFAC MIDLANT Electrical Engineering

Best Value Determination (BVD) Package; G, PDC44 NAVFAC MIDLANT Electrical Engineering

Naval Building P-1334 - Child Development Center 60715453

July 21, 2025

Pre-Final AV Package; G, PDC44 NAVFAC MIDLANT Electrical Engineering

Final AV Package; G, PDC44 NAVFAC MIDLANT Electrical Engineering

Touch Panel Submittal; G, PDC44 NAVFAC MIDLANT Electrical Engineering

SD-07 Certificates

Contractor's AV Designer's Qualifications; G, PDC44 NAVFAC MIDLANT Electrical Engineering

1.3 GENERAL REQUIREMENTS

This Specification Section outlines the minimum requirements and installation methods for the integrated audiovisual system, hardware, software, cables, accessories, and acceptance testing. System refers to the complete and functional assemblage of equipment required to achieve the specified functionality, performance, and design intent. Audiovisual (AV) system shall include, but is not limited to;

a. Audio equipment: Speakers, mixers, amplifiers, microphones, signal processing equipment, and source equipment.

b. Video equipment: Displays, signal routing and processing equipment, and source equipment.

c. Video projection screens

d. Remote control equipment including touch panels, control processors, software, and programming.

e. Equipment racks and associated hardware such as rack screws, power distribution products, cooling products, and blank panels.

f. Cables, snakes, connectors, plates, and wiring.

g. Other similar parts that may be required for normal operation such as projector bulbs and lenses.

h. Mounts, rigging, and required hardware such as all-thread, unistrut, chains, and cables.

i. Floor boxes

j. Display wall boxes

k. AV racks lecterns and credenzas

l. System commissioning

m. Training

n. Documentation

Naval Building P-1334 - Child Development Center 60715453

o. Communication and coordination with all team members and trades to fulfill the requirements of this Specification.

AV System shall be fully integrated with the building systems and finishes. AV system may also include specialty equipment for which the customer activity shall be responsible for specifying.

The design and documentation of the AV system shall be funded as the AV Design Services Option CLIN 0008A. The purchase and installation of the AV Package shall be funded separately as the AV Option CLIN 0008B. The Government AV budget on the Bid Schedule/Price Proposal Form for the AV Option is $76,715 and does NOT include the Contractor's Handling and Administration Rate (HAR). This Government AV estimate shall not be altered by Contractors during the bid process.

All AV items are subject to the Buy American Act/Trade Agreements Act.

1.4 AUDIOVISUAL DESIGN SERVICES OPTION

1.4.1 Qualifications and Affiliations

The AV Designer of Record, hereafter referred to as the Prime Contractor's AV Designer, shall be AVIXA Certified Technology Specialist - Design certified with at least five years of design experience utilizing D401.01:2023, F501.01:2015, 202.01:2016, A102.01:2022, F502.02:201X, V201.01:2021, S601.01:2021, 10:2013, and RP-38-17 on designs similarly sized and complex as this project. Provide documentation of the Prime Contractor's AV Designer's Qualifications and past project performance for at least three projects. The Government reserves the right to approve/disapprove the Prime Contractor's AV Designer.

1.4.2 Concept AV package

A Concept AV package, prepared by the A/E's AV Designer, indicating the salient characteristics of all required AV items and CADD drawings, will be provided to the Prime Contractor. As a separately priced option, different from the AV Option CLIN 0008B, the Prime Contractor shall provide the services of a Certified Technology Specialist - Design (CTS-D), other than the A/E's AV Designer, to function as Prime Contractor's AV Designer, to prepare and provide the Final, Best Valued AV Package and procurement data based on the Concept AV package. This separately priced option is CLIN 0008A on the Bid Schedule/Price Proposal Form.

All fixed and movable furnishings selections shall be closely coordinated with the final construction documents and interior finishes. The Prime Contractor's AV Designer shall validate, through Needs Analysis, all AV requirements with the Activity, and make any necessary changes to the AV System Design. The AV package includes the design, selection, specification, color coordination, and procurement documentation of the required items necessary to meet the functional, operational, sustainability, and security needs of the facility. The AV package shall be fully integrated with the design, construction, and schedule of all building systems (HVAC, Plumbing, Fire Protection, Communications, Electrical, Data, Architecture, etc. All outlets, switches, fire extinguishers, thermostats, etc. shall be fully accessible. All sprinkler heads, ADA, etc. clearances shall be accommodated.

The Prime Contractor's AV Designer shall attend walk-throughs, any and all

Naval Building P-1334 - Child Development Center 60715453 required meetings, and coordinate system requirements to accomplish this task. The Contractor's AV Designer and equipment specialists shall be responsible for designing and providing specifications for procurement of the AV System, to include delivery and installation, for the facilities built or renovated under this contract as directed by the NAVFAC Electrical Engineering Branch (PDC44). AV specifications shall be based on GSA Multiple Award Schedules, and other Federal contracts and complying with priorities found in FAR Part 8.404. The utilization of the current GSA MAS list is required for BVD Analysis Request for Pricing.

1.5 AUDIOVISUAL (AV) SUBMITTALS FOR THE AV DESIGN SERVICES OPTION

CLIN 0008A. Develop design as described and in accordance with the Activity requirements. Include in the design all AV equipment required to produce an optimum functional facility, consistent with quality commercial design.

This project also includes the preparation of specific detailed information for each selected item. Each submittal shall demonstrate thorough interaction with the Activity requirements and complete coordination with the facility design.

c. For all projects, including fast track projects, the Prime Contractor shall be responsible for sufficiently scheduling all AV and any revisions to submittals early enough to obtain the required government approvals, and meet all ordering and installation lead times to complete the project by the contract completion date.

These are minimum requirements and the Prime Contractor shall be prepared to provide any/all additional meetings and submittals that may be necessary to support the AV Design effort/ and coordination.

1.5.1 AV Requirements Meeting (Audiovisual Consultant Orientation)

This meeting shall occur atvia conference call prior to the AV "Over the Shoulder" Review Meeting and the development of the AV package. The NAVFAC Electrical Engineer/Audiovisual Consultant will review current template documents required for use in the AV BVD RFQ Package, mandatory sources to consider, GSA, review the BVD process, and discuss the number of BVDs required. Minutes of this meeting shall be submitted to the NAVFAC Project Manager within 7 business days. Submit the itemized AV Estimated Cost Summary within 21 days to the NAVFAC EE/AVC.

1.5.2 AV "Over the Shoulder" Review Meeting

Prior to the AV Basis of Design Meeting and Best Value Determination (BVD) Analysis, the Contractor's AV Designer shall meet with the NAVFAC Electrical Engineer/Audiovisual Consultant for an "over-the-shoulder" review to present preliminary AV options. These can be presented in a "loose" format for preliminary approval prior to the Activity presentation. The "over-the-shoulder" review meeting shall be held via conference call.

1.5.3 AV Basis of Design Meeting

The Prime Contractor's AV Designer shall present the NAVFAC approved AV Basis of Design to the Activity, located at NSA Hampton Roads, for

Naval Building P-1334 - Child Development Center 60715453 approval. This presentation shall include preliminary drawings and basis of design equipment. Attendees include the Contractor’s Project Manager and AV designer, Activity, AMB/ SMD (USMC projects), NAVFAC OICC/ Project Manager/ Electrical Engineer/Audiovisual Consultant and ID (if required).

E-mail files documenting the selections to the NAVFAC EE/AVC within 7 business days.

1.5.4 BVD RFQ Package(s) "Over the Shoulder Review" Meeting

Meet with the NAVFAC EE/AVC for an "over-the-shoulder" review of the Pre-Final Best Value Determination (BVD) RFQ Package and to review the GSA vendor lists. Send an electronic copy of the complete AV BVD RFQ Package(s) to the NAVFAC EE/AVC for review. The "over-the-shoulder" review meeting shall be held via conference call. Attendees include the Contractor’s Project Manager and AV Designer, Activity, AMB/ SMD (USMC projects), NAVFAC OICC/ Project Manager/ Electrical Engineer/Audiovisual Consultant and ID (if required).

BVD RFQ Package shall include the following;

a. Copy of the BVD Request for Pricing cover letter.

b. Copy of the BVD Request for Pricing Scope of Work.

c. BVD Request for Pricing Spreadsheet/Questionnaire with "basis of design" item product numbers, photos & descriptions.

d. Edited Copy of UFGS 27 41 00 AUDIO-VISUAL SYSTEMS.

e. Project Specific Room/Furniture/Rack Typicals.

f. Floor Plans with Legends coded to the BVD RFP (PDF format).

1.5.5 BVD Meeting

The Prime Contractor's AV Designer shall submit one (1) copy of the Best Value Determination (BVD) Package to the NAVFAC Electrical Engineer/Audiovisual Consultant. An electronic copy shall be sent to the NAVFAC Contracting Officer. The review meeting shall be held via conference call to review the results of the solicitation and determine a best value recommendation. The BVD Submittal shall be in a digital format and shall include the following items for review and approval:

a. Cover Title Page (project name, project #, location, submittal date, submittal title)

b. Table of Contents.

c. Point of Contact List.

d. Narrative of AV Designer Objectives.

e. BVD Analysis Request for Pricing Spreadsheet/Questionnaire completed by all bidders and completed Questionnaire.

f. Copy of all information sent to bidders and documentation that all

Naval Building P-1334 - Child Development Center 60715453 required sources were contacted.

g. Back-up Information submitted by each bidder (cut sheets/highlighted pricing sheets/technical specifications, pricing, dealer and manufacturer qualification for each product showing that products meets all requirements).

h. BVD Pricing Evaluation Spreadsheet comparing bidder quotes/responses.

i. Contractor's AV Designer recommendation for the Best Value vendor and justifications.

1.5.6 Pre-Final AV Meeting

The Pre-Final AV Package shall be presented to the Activity and NAVFAC digitally at a meeting to occur at the Activity, located at NSA Hampton Roads. Three (3) submittals will be required; (1) for the NAVFAC Project Manager, (1) for the FEAD, and (1) for the Activity.

Submit the following in a digital format for review and approval:

a. Cover Title Page (project name and number, submittal date and title).

b. Table of Contents.

c. Point of Contact List (includes contact info for recommended Best Value vendors and subcontractors).

d. Preliminary AV Cost Summary to include shipping, freight, handling, installation, design management, project management, HAR and applicable sales tax and bonding.

e. Procurement Data Sheets completed for each item (if required).

f. AV floor plans coded to the AV Cost Summary and Procurement Data Sheets/Bill of Materials.

g. UFGS Specification 27 41 00 AUDIO-VISUAL SYSTEMS used in bid request for the AV System.

h. Final Finish Selections and Samples (if required).

i. Copy of Quote(s)/Bill of Materials (BOM) on letterhead from the vendor(s) determined to be the best value. Code BOM line items to AV Cost Summary Item Codes.

1.5.7 Final AV Submittal

The Final AV Package shall be due 10 months prior to BOD following the receipt of review comments on the Pre-Final AV submittal and shall shall be in the format described below.

These are minimum requirements and the Contractor shall be prepared to provide any additional meetings and submittals that may be necessary to support the AV Design effort and coordination.

Naval Building P-1334 - Child Development Center 60715453

The Final AV Submittal shall be submitted digitally for review and approval. The number of final submittals required shall be;

Three (3) total; One each for the NAVFAC Project Manager, the FEAD/ROICC and the Activity.

The Final AV Submittal shall include the following;

a. Cover Title Page with project name, project #, submittal date, submittal title.

b. Table of Contents.

c. Point of Contact List which includes contact info for recommended Best Value vendors and subcontractors.

d. Final AV Cost Summary to include shipping, freight, handling, installation, design management, project management, HAR and applicable sales tax and bonding.

e. Procurement Data Sheets completed for each item (if required).

f. Final AV Plans coded to the AV Final Cost Summary and Procurement Data Sheets/Bill of Materials.

g. UFGS Specification 27 41 00 AUDIO-VISUAL SYSTEMS used in bid request for the AV System.

h. Copy of Final Quote(s)/Bill of Materials (BOM) on letterhead from the vendor(s) determined to be the Best Value. Code BOM line items to AV Cost Summary Item Codes.

i. Best Value Determination Guidelines sheets; completed and signed by the Prime Contactor's AV Designer.

j. Written guarantees from all vendors to hold pricing for a minimum of 120 days.

1.5.8 AV Pre-Programming and UX Meeting

Following review and approval of the Pre-Final AV Package, Contractor's AV designer and Vendor(s) Control System Programmer shall meet with the NAVFAC EE/AVC, Contracting Officer, and Activity to discuss details regarding the operation, layout and functionality of the system controls. The Vendor’s Control System Programmer shall bring relevant concept/sample touch panel layouts to this meeting. If applicable, the Vendor’s programmer shall view any existing AV touch panels and observe system operations. If the Activity has specific touch panel standards/requirements, they shall be discussed during this meeting. Hold Meeting at NAVFAC, Activity’s location or virtually, as deemed necessary by the NAVFAC EE/AVC.

The Touch Panel Submittal shall be submitted no later than 8 months prior to CCD. The Programming and User Experience (UX) Package shall be submitted as a live preview file when possible to convey the touch panel operational flow.

Naval Building P-1334 - Child Development Center 60715453

a. The Best Value Vendor’s Control System Programmer shall prepare touch panel submittals for review by the Contractor's AV designer, Construction Contractor, NAVFAC’s EE/AVC, and the activity.

b. When live preview/emulation file review is not possible or preferred by the activity, a PDF of screen shots with captions shall be provided.

Touch panel pages shall be arranged to convey touch panel operation flow.

c. The Best Value Vendor’s Control System Programmer shall submit up to

(3) CD copies including any generated preview files as well as preview software installation files (as applicable) for the reviewers.

d. Screenshots or preview files must be provided for each unique touch panel in the project with the applicable rooms/locations clearly identified for each.

1.5.9 Punch List:

See section 2.1.13 Punch List.

1.5.10 AV Construction Submittals

Submit any revisions or deviations caused by discontinued items or NAVFAC required changes to the Contracting Officer for approval by the NAVFAC Electrical Engineer. All submittal due dates for the AV shall be reflected in the Contractor's construction schedule. Changes to the AV schedule shall be submitted to the Contracting Officer or their Representative for approval.

1.6 BEST VALUE DETERMINATION

A Best Value Determination (BVD) is required by FAR 8.404 when placing orders against Federal Supply Schedules. Best Value is defined in FAR

2.101 as ensuring that the order to be placed under a Federal Supply Schedule results in the lowest overall cost alternative (considering price, special features, administrative costs and client's needs) to meet the government's needs.

a. A (BVD) shall be performed on a minimum of three manufacturers for orders with a total procurement greater than the Micro-Purchase Threshold (MPT) from an individual manufacturer. Multiple BVDs may be required in order to complete the final AV package.

b. The required quantity of BVD's to be performed will be determined by the NAVFAC Electrical Engineer during the design phase and is dependent on the specific project requirements.

c. Documentation shall be provided to the Government with the final AV package. Specific Documentation is indicated in the Preliminary BVD Submittal and "Over the Shoulder Review." The BVD Statement shall be completed and signed by the Contractor's AV Designer.

The Prime Contractor's AV Designer is responsible for the following written BVD justifications:

1.6.1 Total procurement greater than Micro-Purchase Threshold (MPT) and

Naval Building P-1334 - Child Development Center 60715453 less than Simplified Acquisition Threshold (SAT)

For any procurement in the AV package with a value greater than MPT and less than SAT, the Prime Contractor's AV Designer shall always review pricing from at least three vendors. In addition to the review of published list prices, the Contractor's AV Designer must confirm the pricing with the vendor. Manufacturer's quotes are NOT required. The BVD form must be completed and submitted for all AV procurements greater than MPT and less than SAT.

1.6.2 Evaluation Factors

The Best Value Determination shall address issues such as:

a. Special features of the supply or service required for effective program performance; Perceived appropriateness of offered product compared to Request for Pricing requirements.

b. Dealer/installation team must be located within 150 driving miles of Norfolk, Virginia to provide proximity for support and maintenance to the Base after delivery of the product.

c. Price (including freight)

d. Probable life of the item offered as compared with that of a comparable item; Perceived product durability and quality

e. Past performance.

f. Warranty considerations.

g. Maintenance availability; Dealer/manufacturer proximity for support.

h. Environmental and energy efficiency considerations (sustainability).

i. Comfort/suitability of the system and/or component.

j. Compatibility with existing furniture and/or products.

k. Product performance.

l. Delivery terms.

m. Other (Describe).

n. Emphasis shall be to create a fully integrated design solution by providing quality products to meet the functional needs of the customer. Customer preferences shall be considered. The focus shall be on the best overall value. Use the NAVFAC Best Value Determination forms provided by the NAVFAC Electrical Engineer.

PART 2 AV TURNKEY EFFORT

2.1 AV OPTION

CLIN 0008B AV Option: As an option, provide procurement and installation coordination of the complete and usable Final AV package. The AV Package

Naval Building P-1334 - Child Development Center 60715453 must include shipping, freight, handling, installation, applicable state sales tax, and the Prime Contractor's AV Handling and Administration Rate (HAR) percentage as applied to the final AV total cost (excluding taxes).

2.1.1 Authorization

The Government will provide separate funding for procurement and installation coordination of the AV package. Construction funds will not be used. Upon receipt of required funding, the Prime Contractor shall be authorized by the Contracting Officer, as an option to the construction contract, to procure and install all Final AV utilizing GSA Multiple Award Schedules, and other Federal contracts and complying with priorities found in FAR Part 8.404. The Prime Contractor will be expected to procure and coordinate the installation of the approved Final AV package exactly as specified. The amount of the modification will be the actual cost of these items from the Federal Government price schedules (GSA), including any freight and installation charges from the vendor as well as the Prime Contractor's HAR and any applicable state sales tax. The HAR includes all of the Prime Contractor's effort related to storage, coordination, handling, administration of subcontractors, and all other associated costs and profit for the procurement of AV Equipment.

The Government will indicate the AV estimate based on the Concept Design in the contract solicitation Price Proposal Form (Bid Schedule). This Government estimate shall not be altered by Prime Contractors during the bid process.

Prime Contractors shall propose a Handling and Administration Rate (HAR) only. The Prime Contractor will propose the AV HAR in the contract solicitation. The Prime Contractor's proposed HAR may not exceed 5 percent of the total AV costs, as noted on the bid schedule. The HAR shall not include costs associated with the AV Design Services required in the AV Design Services Option.

AV items are subject to the Buy American Act/Trade Agreements Act.

2.1.2 Procurement and Installation

The Prime Contractor shall coordinate the building completion date with the installation dealer(s) specified in the AV Package. The Prime Contractor shall anticipate possible manufacturer price increases if order placement is delayed. It is recommended to order the AV product once the option is awarded and funds are received to avoid incurring additional costs.

Delayed production and delivery dates can be noted at the time of order placement to coincide with the contract completion date. Any costs incurred due to manufacturer price increases will be the burden of the Prime Contractor.

2.1.3 Deposits

The Prime Contractor should anticipate providing a deposit of between 30 percent and 50 percent of the AV costs when placing the orders with the manufacturer's dealerships.

2.1.4 Davis Bacon Wages

Naval Building P-1334 - Child Development Center 60715453

Davis Bacon wages do not apply to the AV installer from the Government supply sources. The workforce for the AV installation and delivery shall be separate and distinct from the labor workforce performing under the construction contract.

2.1.5 Sales Tax

The Prime Contractor shall take maximum advantage of all exemptions from State and Local taxation authorities whether available to it directly or available to the Prime Contractor based on an exemption afforded the Government. The responsibility for paying applicable taxes rests with the Prime Contractor. Any state and local taxes applicable to the AV shall be included within the AV Dealer's quote.

2.1.6 Bonds

AV items are not considered construction and the prime contractor shall not be required to secure any additional bond for the award of the AV line item unless otherwise indicated in the contract. If any additional bond is required for the AV line item it is to be included in the prime contractor's AV HAR.

2.1.7 Unique Item Identification (IUID) and Valuation

Unique item identification and valuation is a system of marking and valuing items delivered to DoD that enhances logistics, contracting, and financial business transactions. The IUID policy is mandatory for all DoD contracts that require the delivery of items. An item is a single article or a single unit formed by a grouping of subassemblies, components, or constituent parts. The Prime Contractor shall provide DoD Unique item identification, valuation and delivery of data for all required AV items for which the government's unit acquisition cost is $5,000 or more.

PART 3 EXECUTION

3.1 Installation

The AV package includes the installation of all AV Equipment as specified in the AV package. The installation dealer(s) specified in the AV package shall receive, store as required, transport to the project site, off load, inside deliver, unpack, assemble, place/install, clean, and dispose of all the trash for all AV Equipment. It is the Prime Contractor's responsibility to coordinate the building completion, occupancy, and AV System installation dates with the installation dealer(s) specified in the AV package. Any costs associated with or delaying AV Equipment shipments is the responsibility of the Prime Contractor.

The Prime Contractor shall provide and coordinate all Building Systems (HVAC, Plumbing, Fire Protection, Communications, Electrical, Data, Architectural, etc. with the AV plans and AV installation. All outlets, switches, thermostats, etc. shall be fully accessible. All sprinkler heads, fire extinguishers, ADA, etc., clearances shall be accommodated.

3.2 Installation Warranty

All AV Equipment shall be installed in accordance with the manufacturer's instructions and warranty requirements. All Racks shall be level and

Naval Building P-1334 - Child Development Center 60715453 aligned. All doors, drawers and accessories shall be level and aligned to open, close and otherwise operate smoothly and securely.

All AV Equipment shall be installed by the furniture manufacturer's dealer of record and not the Prime Contractor. The Government reserves the right to approve/disapprove the Prime Contractor's AV installers. In addition, installation dealer(s) must be located within a 150 mile radius of the project site unless approved by the Government Electrical Engineer. The Prime Contractor shall repair, to the Government's satisfaction, any/all damage to any facility finish that is a result of the AV installation and correct all punch list items.

3.3 Ordering Documentation

After award of the AV package, two CD copies and one binder copy of all ordering documentation, including Factory Order number (FO) and warranty information for all products, shall be provided to the Contracting Officer at the final AV walk-thru.

3.4 Post Award Changes

After award of the AV Option, any request to change the AV items must be submitted to the Contracting Officer. The AV Option will have been accepted, priced, and negotiated as detailed in the final package. Those items will have been agreed to considering color, specific type and quality of material, price, sustainability, life cycle, and dealership service.

The Government will require the Prime Contractor to provide exactly those items. Should changes become necessary, careful consideration shall be essential to assure that equivalent quality, price and other aspects of the item are maintained. Otherwise, price adjustments must be negotiated.

Coordination with building services and other AV items is required for all proposed and approved substitutions. The Prime Contractor shall obtain approval from the Contracting Officer and NAVFAC Electrical Engineer for any changes to the AV Package.

Post award AV manufacturer's price increases, beyond the pricing guarantee date, are the responsibility of the Prime Contractor and shall not be transferred to the Government.

3.5 Punch List

The Contractor and their AV Designer shall attend at least one punch list site visit with the installation dealer(s), NAVFAC Electrical Engineer and the Base Representative/Activity Contact. The site visit shall identify all punch list items (at installation dealer's 98 percent completion) and a follow up (at 100 percent completion) will confirm that all punch list items have been resolved(if required by the Contracting Officer's Representative.

3.6 Best Value Determination

A best value determination has been performed on the final AV package. A best value determination is required by FAR 8.404 when placing orders against Federal Supply Schedules for the selection of furniture and furnishings. Best Value is defined in FAR 2.101 as ensuring that the order to be placed under a Federal Supply Schedule results in the lowest overall cost alternative (considering price, special features, administrative costs and client's needs) to meet the government's needs.

Naval Building P-1334 - Child Development Center 60715453

-- End of Section --

Naval Building P-1334 - Child Development Center 60715453

SECTION 01 35 26

GOVERNMENTAL SAFETY REQUIREMENTS

11/20, CHG 4: 08/23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN SOCIETY OF HEATING, REFRIGERATING AND AIR-CONDITIONING

ENGINEERS (ASHRAE)

ASHRAE 52.2 (2012) Method of Testing General Ventilation Air-Cleaning Devices for Removal Efficiency by Particle Size

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

ASME B30.3 (2020) Tower Cranes

ASME B30.5 (2021) Mobile and Locomotive Cranes

ASME B30.7 (2021) Winches

ASME B30.8 (2020) Floating Cranes and Floating Derricks

ASME B30.9 (2018) Slings

ASME B30.20 (2018) Below-the-Hook Lifting Devices

ASME B30.22 (2023) Articulating Boom Cranes

ASME B30.23 (2022) Personnel Lifting Systems Safety Standard for Cableways, Cranes, Derricks, Hoists, Hooks, Jacks, and Slings

ASME B30.26 (2015; R 2020) Rigging Hardware

AMERICAN SOCIETY OF SAFETY PROFESSIONALS (ASSP)

ASSP A10.22 (2007; R 2017) Safety Requirements for Rope-Guided and Non-Guided Workers’ Hoists

ASSP A10.34 (2021) Protection of the Public on or Adjacent to Construction Sites

ASSP A10.44 (2020) Control of Energy Sources (Lockout/Tagout) for Construction and Demolition Operations

ASSP Z244.1 (2016) The Control of Hazardous Energy Lockout, Tagout and Alternative Methods

SECTION 01 35 26 Page 1 July 18, 2025

ASSP Z359.0 (2018) Definitions and Nomenclature Used for Fall Protection and Fall Arrest

ASSP Z359.1 (2020) The Fall Protection Code

ASSP Z359.2 (2017) Minimum Requirements for a Comprehensive Managed Fall Protection Program

ASSP Z359.3 (2019) Safety Requirements for Lanyards and Positioning Lanyards

ASSP Z359.4 (2013) Safety Requirements for Assisted-Rescue and Self-Rescue Systems, Subsystems and Components

ASSP Z359.6 (2016) Specifications and Design Requirements for Active Fall Protection Systems

ASSP Z359.7 (2019) Qualification and Verification Testing of Fall Protection Products

ASSP Z359.11 (2014) Safety Requirements for Full Body Harnesses

ASSP Z359.12 (2019) Connecting Components for Personal Fall Arrest Systems

ASSP Z359.13 (2013) Personal Energy Absorbers and Energy Absorbing Lanyards

ASSP Z359.14 (2014) Safety Requirements for Self-Retracting Devices for Personal Fall Arrest and Rescue Systems

ASSP Z359.15 (2014) Safety Requirements for Single Anchor Lifelines and Fall Arresters for Personal Fall Arrest Systems

ASSP Z359.16 (2016) Safety Requirements for Climbing Ladder Fall Arrest Systems

ASSP Z359.18 (2017) Safety Requirements for Anchorage Connectors for Active Fall Protection Systems

ASSP Z490.1 (2016) Criteria for Accepted Practices in Safety, Health, and Environmental Training

ASTM INTERNATIONAL (ASTM)

ASTM D6245 (2012) Using Indoor Carbon Dioxide Concentrations to Evaluate Indoor Air Quality and Ventilation

ASTM D6345 (2010) Standard Guide for Selection of Methods for Active, Integrative Sampling of Volatile Organic Compounds in Air

SECTION 01 35 26 Page 2

ASTM F855 (2019) Standard Specifications for Temporary Protective Grounds to Be Used on De-energized Electric Power Lines and Equipment

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

IEEE 1048 (2016) Guide for Protective Grounding of Power Lines

IEEE C2 (2023) National Electrical Safety Code

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

NEMA Z535.2 (2011; R 2017) Environmental and Facility Safety Signs

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 10 (2022; ERTA 1 2021) Standard for Portable Fire Extinguishers

NFPA 51B (2024) Standard for Fire Prevention During Welding, Cutting, and Other Hot Work

NFPA 70 (2023; ERTA 7 2023; TIA 23-15) National Electrical Code

NFPA 70E (2024) Standard for Electrical Safety in the Workplace

NFPA 241 (2022) Standard for Safeguarding Construction, Alteration, and Demolition Operations

SHEET METAL AND AIR CONDITIONING CONTRACTORS' NATIONAL ASSOCIATION

(SMACNA)

ANSI/SMACNA 008 (2007) IAQ Guidelines for Occupied Buildings Under Construction, 2nd Edition

TELECOMMUNICATIONS INDUSTRY ASSOCIATION (TIA)

TIA-222 (2018H; Add 1 2019) Structural Standard for Antenna Supporting Structures and Antennas and Small Wind Turbine Support Structures

TIA-1019 (2012; R 2016) Standard for Installation, Alteration and Maintenance of Antenna Supporting Structures and Antennas

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual

SECTION 01 35 26 Page 3

U.S. NATIONAL ARCHIVES AND RECORDS ADMINISTRATION (NARA)

29 CFR 1910 Occupational Safety and Health Standards

29 CFR 1910.146 Permit-required Confined Spaces

29 CFR 1910.147 The Control of Hazardous Energy (Lock Out/Tag Out)

29 CFR 1910.333 Selection and Use of Work Practices

29 CFR 1915 Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment

29 CFR 1915.89 Control of Hazardous Energy (Lockout/Tags-Plus)

29 CFR 1926 Safety and Health Regulations for Construction

29 CFR 1926.16 Rules of Construction

29 CFR 1926.450 Scaffolds

29 CFR 1926.500 Fall Protection

29 CFR 1926.552 Material Hoists, Personal Hoists, and Elevators

29 CFR 1926.553 Base-Mounted Drum Hoists

29 CFR 1926.1400 Cranes and Derricks in Construction

CPL 02-01-056 (2014) Inspection Procedures for Accessing Communication Towers by Hoist

CPL 2.100 (1995) Application of the Permit-Required Confined Spaces (PRCS) Standards, 29 CFR 1910.146

1.2 DEFINITIONS

1.2.1 Competent Person (CP)

The CP is a person designated in writing, who, through training, knowledge and experience, is capable of identifying, evaluating, and addressing existing and predictable hazards in the working environment or working conditions that are dangerous to personnel, and who has authorization to take prompt corrective measures with regards to such hazards.

1.2.2 Competent Person, Confined Space

The CP, Confined Space, is a person meeting the competent person requirements as defined EM 385-1-1 Appendix Q, with thorough knowledge of OSHA’s Confined Space Standard, 29 CFR 1910.146, and designated in writing to be responsible for the immediate supervision, implementation and monitoring of the confined space program, who through training, knowledge and experience in confined space entry is capable of identifying, SECTION 01 35 26 Page 4 evaluating and addressing existing and potential confined space hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.3 Competent Person, Cranes and Rigging

The CP, Cranes and Rigging, as defined in EM 385-1-1 Appendix Q, is a person meeting the competent person requirements, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the Crane and Rigging Program, who through training, knowledge and experience in crane and rigging is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.4 Competent Person, Excavation/Trenching

A CP, Excavation/Trenching, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and 29 CFR 1926, who has been designated in writing to be responsible for the immediate supervision, implementation and monitoring of the excavation/trenching program, who through training, knowledge and experience in excavation/trenching is capable of identifying, evaluating and addressing existing and potential hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.5 Competent Person, Fall Protection

The CP, Fall Protection, is a person meeting the competent person requirements as defined in EM 385-1-1 Appendix Q and in accordance with ASSP Z359.0, who has been designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the fall protection program, who through training, knowledge and experience in fall protection and rescue systems and equipment, is capable of identifying, evaluating and addressing existing and potential fall hazards and, who has the authority to take prompt corrective measures with regard to such hazards.

1.2.6 Competent Person, Scaffolding

The CP, Scaffolding is a person meeting the competent person requirements in EM 385-1-1 Appendix Q, and designated in writing by the employer to be responsible for immediate supervising, implementing and monitoring of the scaffolding program. The CP for Scaffolding has enough training, knowledge and experience in scaffolding to correctly identify, evaluate and address existing and potential hazards and also has the authority to take prompt corrective measures with regard to these hazards. CP qualifications must be documented including experience on the specific scaffolding systems/types being used, assessment of the base material that the scaffold will be erected upon, load calculations for materials and personnel, and erection and dismantling. The CP for scaffolding must have a documented minimum of 8-hours of scaffold training to include training on the specific type of scaffold being used (e.g. mast-climbing, adjustable, tubular frame), in accordance with EM 385-1-1 Section 22.B.02.

1.2.7 Competent Person (CP) Trainer

A competent person trainer as defined in EM 385-1-1 Appendix Q, who is qualified in the training material presented, and who possesses a working knowledge of applicable technical regulations, standards, equipment and

SECTION 01 35 26 Page 5 systems related to the subject matter on which they are training Competent Persons. A competent person trainer must be familiar with the typical hazards and the equipment used in the industry they are instructing. The training provided by the competent person trainer must be appropriate to that specific industry.