Amendment 0001.pdf
PDF 255 KB Posted
- Attached to
- LP-21/33/34 Renovate Annex - 705 Compliance
- Solicitation number
- N4008525R0147
About this file
This document is a Standard Form 30 (SF-30) Amendment to a Navy solicitation for renovation work at Naval Station Norfolk, Virginia. Amendment 0001 extends the proposal due date to September 25, 2025 at 12:00 PM EDT and provides several key updates: updated general requirements (Revision 1), a site visit log, a hazardous materials survey report, a redacted justification and approval document, and responses to 23 pre-proposal inquiries (PPIs). The amendment covers renovation of Annex 705 for compliance purposes, with contract identifier N4008525R0147. The pre-proposal inquiries address technical details across multiple specification sections, including telecommunications infrastructure, fiber optic cabling, security systems, electrical components, and audiovisual equipment, with responses clarifying technical specifications, equipment requirements, and installation details.
View the file
Other files
Show all 21
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE PAGE OF PAGES
J 1 9
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. PROJECT NO. (If applicable) 0001 09/17/2025
6. ISSUED BY Code N40085 7. ADMINISTERED BY (If other than item 6.) Code
NAVFACSYSCOM MID-ATLANTIC
PWD NORFOLK
FACILITIES ENGINEERING & ACQ DIV
9324 VIRGINIA AVENUE
NORFOLK, VA 23511
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.
N40085-25-R-0147
9B. DATED (SEE ITEM 11)
09/04/2025
10A. MODIFICATION OF CONTRACT/ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER: (specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N4008525R0147, NSN, LP-21, 33, 34 Renovate Annex 705-Compliance, NAVAL STATION NORFOLK, NORFOLK, VIRGINIA
SEE SF 30 BLOCK 14 CONTINUATION PAGE
Contact POC: Natalya Kuti (757) 341-0563; natalya.kuti.civ@us.navy.mil
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR (Same as Item 8)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY
(Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)
PREVIOUS EDITION UNUSABLE Prescribed by GSA
SECTION SF30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
AMENDMENT 0001
The purpose of this amendment is to:
1. Provide Updated General Requirements REV1
2. Provide Site Visit Log (attachment M)
3. Extend Proposal Due Date: The proposal due date has been extended to Thursday, September 25, 2025 at 12:00PM EDT
(noon).
4. Provide Hazardous Materials Survey Report (attachment L)
5. Provide Redacted Justification and Approval (attachment N)
6. Provide Responses to Pre-Proposal Inquiries (PPIs) # 1-23.
All other terms and conditions remain unchanged.
1. Provide Updated General Requirements
See Attachement General_Requirements LP-21,33,34 REV1. Updates are in red font.
2. Provide Site Visit Log
See Attachment M – Site Visit Log
3. Extend Proposal Due Date
The proposal Due Date is extended from Monday, 22 September 2025, to Thursday, 25 September 2025 at 1200 EDT (Noon).
4. Provide Hazardous Materials Survey Report
See Attachment L – Hazardous Materials Survey Report
5. Provide Redacted Justification and Approval
See Attachment N – Reacted Justification and Approval
6. Provide Responses to PPIs #1
Pre-Proposal Inquiry Submission Form
N4008525R0147 LP-21,33,34 Renovate Annex 705 Compliance
Project Location: NAVAL STATION NORFOLK, NORFOLK, VIRGINIA
PPI# Date
Submitte d
LEAV
E
BLAN
K
Reference Question Responses
Page Section Paragraph
1 09/10/25 28 31 70 1.3.2(a) This section states that shop drawings must bear a PE seal and prepared by, or under the immediate supervision of, the FPQC. While this is per the unedited guide specification, it is also somewhat contradictory to paragraph 1.5.5, which only calls for FPQC review of the submittal.
Please advise if the 2nd and 3rd sentences of
1.3.2(a) may be deleted. Note that we have routinely deleted these sentences on projects where we are the designer of record, without objection from
NAVFAC ML
FPEs.
Delete the 2nd and 3rd sentences of 28 31 70 ¶1.3.2.a
("Construction (shop) drawings and calculations must be prepared by, or prepared under the immediate supervision of, the FPQC. The
FPQC must affix their professional engineering stamp with signature to the shop drawings, calculations, and material data sheets, indicating approval prior to submitting the shop drawings to the DFPE.").
This change provides consistency between Sections
01 45 00, 21 13 13, and 28 31
76.
2 09/10/25 E-401 What is the
NEMA rating for the 20A 125V
Twist Lock
Receptacles
The NEMA rating is L5-20R.
3 09/10/25 E-401 What is the
NEMA rating for the 20A 250V
Twist Lock
Receptacles
The NEMA rating is L5-20R.
4 09/10/25 T-504 On Sheet T-504, a floor box detail is shown but there is no symbol refeclting placement of the floor boxes on the telecom or electrical drawings.
Verification of placement and counts is needed for accurate pricing.
Floor boxes for telecom were removed from project requirements. Details will be removed from telecom drawings.
5 09/10/25 E-401 Detail B3 for the
LP-21 Electrical
Room 2121 shows the requirement of a SPD, what is the size of the
SPD
See Spec 262000, Para. 2.25 for rating and other electrical characteristics. If referring to physical dimensions, I would consider a 12"H x 12"W x
6.5"D NEMA 1 enclosure as my basis.
6 09/10/25 NA NA NA Reference RFP
General
Requirements.
The Proposal Due
Date is currently scheduled for
Monday, September 22nd.
According to leading industry organizations and in our own experience, scheduling the bid due date on a
Monday, Friday or immediately following a holiday generally lead to reduced engagement and higher risk of incomplete submissions.
Please consider rescheduling the
Proposal Due
Date to a
Tuesday, Wednesday or
Thursday.
Eproposal due date is extended until Septemebr 25, 2025 at 12:00 EDT (noon).
7 09/12/25 AD101 NA Remove Paint on
Underside of
Existing Roof
Deck Around
Perimeter of
Building. See
Demo RCP Plan for Each Building
The hazmat report does not indicate any lead containing materials sampling. Please advise if this paint should be considered lead contaminated?
Sampling of the roof deck paint was not included in the scope of the HazMat survey.
Buildings constructed after
1980 are at low-risk for having lead containing paint.
Characterize waste stream and follow appropriate disposal regulations.
8 09/12/25 TY001 NA NA Responsibility
Matrix states that the Owner is responsible for the Network
Switches and the
Network Video
Recorders. Please confirm that the
Owner will supply ONVIF
Compliant
ESS active devices are funded
OPN, outside of this contract
Network Video
Recorders.
9 09/12/25 TY001 NA NA Responsibility
Matrix states that the Door
Contacts are the responsibility of the General
Contractor.
Drawing TY501 shows the High
Security Level 2
Balanced
Magnetic
Contacts are flush mounted.
Please confirm that they are flush mounted.
ESS active devices are funded
OPN, outside of this contract
10 09/12/25 TY001 NA NA Responsibility
Matrix states that the Security Low
Voltage Power
Supplies are by the Security
Integrator.
Drawing TY501, Detail A3, Note 9 has the Lock
Power Supply
Provided by the
Lock Contractor.
Please confirm that the Lock
Power Supplies are provided by the Lock
Hardware
Contractor.
ESS active devices are funded
OPN, outside of this contract
11 09/12/25 TY001 NA NA Responsibility
Matrix states that the Conduit and
Back Boxes are by the Electrical
Trade. Drawing
TY501, Detail A3, Notes 10-15 & 20 state raceway by the Security
Contractor.
Please confirm that all of the raceway covered by notes 10-15 &
20 are the responsibility of
Confirm the Electrical
Contractor.
12 09/12/25 TY501 NA NA Drawing TY501, Detail A1 has the
Power Supply mounted in the secure side ceiling. Detail A3 has the Power
Supply, Note 9
Centrally mounted. Please confirm that there is a Lock
Power Supply mounted above each Security
Door with an
Electrically
Activated or
Deactivated
Lock.
ESS active devices are funded
OPN, outside of this contract
13 09/12/25 TY101 NA NA Drawing TY101 for LP-21 shows one Request to
Exit on one of two exterior perimeter doors.
Drawing TY102 for LP-33 shows two Request to
Exit devices for three exterior perimeter doors.
Drawing TY103 for LP-34 shows two Request to
Exit devices for three exterior perimeter doors.
Please confirm that there is one exterior perimeter door without a
Request to Exit device.
Confirm
14 09/12/25 TY101,
TY102,
TY103
NA NA Drawing TY101, TY102 and
TY102 have interior doors without Request to Exit devices shown. Please confirm that the
Confirm/Refer to Door
Hardware Schedule for details.
Request to Exit signals will come from the Door
Hardware Exit
Devices.
15 09/12/25 NA NA NA Please provide an update on when the
Environmental
Inspection
Survey will be made available.
See attachment L
16 09/12/25 NA NA NA Reference AE601
- Door Schedule -
Door 2119A is designated as door Type B on the door schedule but is also designated to receive RF
Shielding. On
AE602 - Door
Schedule and
Elevations - it appears that door
Type B is not designated with
RF Shielding but door Types C &
D are designated with RF
Shielding. Please provide the correct door type for Door 2119A.
The correct type for door
2119A is "C".
17 09/12/25 T501 A4 detail
On Drawing
T501, the M outlet detail is shown with one
“M” symbol and an open triangle.
On the corresponding floor plans, outlets are labeled as “MM.”
Please clarify:
Do the outlets labeled “MM” follow the same detail as the “M” outlet, or Does the “MM” designation indicate twice the amount of outlets/cabling as the “M” outlet detail?
The outlet identifiers mean the same. The "M" identifier shown on the outlet detail will be revised to "MM" to match all designations shown in the buildings.
18 09/12/25 TA
Drawing s
27 41 00 Will
Audio/Visual cabling and equipment be provided by the end user? Will this be provided by NIWC?
AV Contractor will Provide.
19 09/12/25 27 10 00 Power
Distribution
Units (PDUs)
PDUs are not mentioned in
Specification
Section 27 10 00.
Please confirm whether the telecommunicatio ns racks/cabinets will require
PDUs, and if so, provide the basis of design.
PDUs wil be provided for all telecommunications racks/cabinets. This requirement will be provided in the Spec Section 27 10 00 and the Basis of Design.
20 09/12/25 T
Drawin gs
Cabinet Material
Requirements
Patch panel elevations are not shown for cabinets in given drawings. Are cabinet elevations availble?
A typical cabinet elevation will be provided for better defination of what will be provided by contractor.
21 09/12/25 T505 Detail
C3
27.018 New 24-strand
single-mode OSP
Backbone fiber cabling connecting the
Telecomm rooms distance not made clear on drawings or specifications.
What are the approximate distances between buildings depicted on detail
C3?
Requirements for adding the
24 fiber OSP cabling will be better defined. Approximate distances will be provided between buildings on detail C3 for pricing/cost estimates.
22 09/12/25 T
Drawing s
Is the 24-strand single mode fiber the only fiber backbone between the buildings telecomm rooms?
There appears to be no ISP fiber backbone cabling on the provided drawings.
Requirements for ISP cabling backbones and horizontal cabling will be provided in an
ISP riser diagram.
23 09/12/25 33 82 00 Will Maxcell outdoor innerduct be required for the new 24-strand single mode fiber? Spec section 33 82 00 does not specify.
We were not sure if innerducts were in place in the existing duct banks but can add a keynote requiring them to be added if not.
All other terms and conditions remain unchanged.
(End of Summary of Changes)