- REPLACE GENERATOR AND AUTOMATIC TRANSFER SWITCH, BLDG 292, NAS OCEANA, VIRGINIA BEACH, VIRGINIA
- Solicitation number
- N4008525R0052
About this file
This document is an Addendum 0002 for a federal contract to replace a generator and transfer switch at Building 292 at NAS Oceana in Virginia Beach, VA, dated 21 Jul 2025. The addendum details comprehensive replacement requirements for an existing natural gas generator, including demolishing the current generator, disconnect switch, and automatic transfer switch, and installing a new 100kW, 3-phase, 480/277V, 60Hz diesel generator with specific technical specifications.
Key replacement requirements include installing a new generator with a sub-base fuel tank, Level 1 sound-attenuated aluminum weatherproof enclosure, and a new 150A automatic transfer switch with maintenance bypass. The fuel tank must be an above-ground, double-walled, stainless-steel, factory-fabricated diesel fuel storage sub-base tank conforming to UL 2085 standards, with electronic overfill and leak detection systems. The generator and enclosure must have a factory-applied coating system suitable for the severe corrosive environment, and all work must be coordinated with the Contracting Officer, NAVFAC UEM, and the resident activity.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
BUILDING 292 – REPLACE GENERATOR AND TRANSFER SWITCH
NAS Oceana, Virginia Beach VA
Addendum 0002
21 JUL 2025
1) In Part 3, Paragraph D5090 OTHER ELECTRICAL SERVICES, on Pages 34 and 35 of 223:
DELETE:
All paragraphs.
REPLACE WITH:
“Demolish existing natural gas generator, disconnect switch, and automatic transfer switch.
Demolish existing generator grounding system.
Demolish existing power conductors from generator to disconnect switch and from disconnect switch to automatic transfer switch.
Reuse existing conduit from generator to building. Modify conduit at new equipment pad and building as required.
Reuse conduit and conductors from automatic transfer switch to wireway. Modify as required.
Reuse conduit and conductors from automatic transfer switch to Main Switchboard.
Modify as required for connection to new disconnect switch.
Demolish existing control conductors from generator to automatic transfer switch.
Demolish existing Generator Remote and Alarm Control Panel in Room 131.
Demolish conduit and conductors back to source.
Provide and install new 100kW, 3 phase, 480/277V, 60Hz, diesel generator on new concrete equipment pad. Provide and install required grounding system and ground generator and equipment pad.
The generator shall be provided with, but not limited to, a sub-base fuel tank, Level 1 sound attenuated, aluminum weatherproof enclosure and local/remote alarm annunciator.
Addendum 0002
21 JUL 2025
The generator and enclosure shall have factory applied coating system for the severe corrosive environment present at the building location. Field applied coatings will not be acceptable.
Provide and install new open transition, 3 phase, 600V, 60Hz, 150A, automatic transfer switch with maintenance bypass in same room the existing switch is removed from.
Provide and install new power and control conductors from new generator to new automatic transfer switch.
Provide and install new disconnect switch. Provide and install new conductors from load side of new disconnect switch to automatic transfer switch and from line side of disconnect switch to Main Switchboard.
Provide and install new remote alarm annunciator, including conduit and conductors, in Room 155.
Provide and install power circuits for battery charger and engine heater for generator.
The fuel tank for the generator shall be an above-ground, double-walled, stainless-steel, factory-fabricated diesel fuel storage sub-base tank. The secondary containment reservoir shall be a factory-fabricated stainless steel-type that fully encloses the primary storage tank. The entire tank assembly shall conform to UL 2085 and bear the UL label for a protected tank. The tank shall be inspected in accordance with STI/SPFA SP001. The tank shall be strength tested before being placed in use in accordance with the applicable code or standard under which it was built per 9VAC25-91-140(B). All tank attachments and connected components shall meet applicable NFPA material requirements and fire ratings. The tank shall be sized for a continuous run time of 24 hours, under full load.
The tank shall be provided with a manual direct reading fuel level gauge. The tank shall be provided with an electronic overfill and leak detection system with audible alarms.
All work performed under this contract shall be coordinated with the Contracting Officer who will coordinate all required outages with the NAVFAC UEM and the resident activity.”
Addendum 0002
21 JUL 2025
**End of Addendum 0002**
File details come from the government source that posted it. Updated .