This document is Amendment 0001 for a renovation project at NAS Oceana, Dam Neck Annex in Virginia Beach, VA, dated 10 July 2025. The amendment modifies multiple sections of the original solicitation for Building 355, specifically focusing on Rooms 216-218. Key changes include:

  1. Flooring specifications: Replacing slip-resistant epoxy floor coating requirements with standard epoxy paint matching existing corridor colors, reducing the wall base from 12 to 8 inches. 2. Interior door specifications: Upgrading from "maximum duty" to "Level 4" hollow metal interior doors with a 40 STC (Sound Transmission Class) requirement. 3. Demolition and concept plans: Deleting the existing document in Part 6 and replacing it with a new version. These modifications suggest refinements to the original renovation plan for the SOCOM Compound, maintaining slip resistance and sound insulation standards while adjusting specific material and finish details.

View the file

Other files

File Type Posted
AMEND 0006 PPI SPREADSHEET.pdf PDF
25R0019 AMENDMENT 0006.pdf PDF
AMEND 0005 IMG_6901_Fire Alarm Panel 5.JPG JPG image
AMEND 0005 Dam Neck B-355 Existing FACP MNS Locations.pdf PDF
25R0019 AMENDMENT 0005.pdf PDF
AMEND 0005 IMG_6909_Panel Schedule 3.JPG JPG image
AMEND 0005 IMG_6900 Fire Alarm Panel 4.JPG JPG image
AMEND 0005 IMG_6898_Fire Alarm Panel 2.JPG JPG image
AMEND 0005 MASTER PPI SPREADSHEET.pdf PDF
AMEND 0005 IMG_6918_Panel Schedule 9.JPG JPG image
AMEND 0005 IMG_6895_Fire Alarm Panel.JPG JPG image
AMEND 0005 IMG_6897_Fire Alarm Panel 1.JPG JPG image
AMEND 0005 IMG_6924_Corridor Wall 1.JPG JPG image
AMEND 0005 IMG_6921_Corridor Wall.JPG JPG image
AMEND 0005 IMG_6902_Panel Schedule.JPG JPG image
AMEND 0005 IMG_6914_Comms 2.JPG JPG image
AMEND 0005 IMG_6915_Panel Schedule 6.JPG JPG image
AMEND 0005 IMG_6920_Panel Schedule 11.JPG JPG image
AMEND 0005 IMG_6913_Panel Schedule 5.JPG JPG image
AMEND 0005 IMG_6911_Comms.JPG JPG image
AMEND 0005 IMG_6917_Panel Schedule 8.JPG JPG image
AMEND 0005 IMG_6916_Panel Schedule 7.JPG JPG image
AMEND 0005 IMG_6922_Corridor.JPG JPG image
AMEND 0005 IMG_6907_Panel Schedule 1.JPG JPG image
AMEND 0005 IMG_6899_Fire Alarm Panel 3.JPG JPG image
AMEND 0005 IMG_6919_Panel Schedule 10.JPG JPG image
AMEND 0005 A101_Second Deck Concept Plan 250710.pdf PDF
AMEND 0005 IMG_6908 Panel Schedule 2.JPG JPG image
AMEND 0005 IMG_6910_Panel Schedule 4.JPG JPG image
AMENDMENT 0004 PPI SPREADSHEET.pdf PDF
AMEND 0004 B355_Operations Building_1989 (2).pdf PDF
25R0019 AMENDMENT 0004.pdf PDF
AMEND 0004 B355_FINAL SUBMISSION_DRAWINGS.pdf PDF
25R0019 AMENDMENT 0003.pdf PDF
ATTACHMENT H PRICE SCHEDULE FORM.pdf PDF
General Requirements 25R0019 .pdf PDF
25R0019 AMENDMENT 0002.pdf PDF
25R0019 AMENDMENT 0001.pdf PDF
ATTACHMENT J PROVISION 52.204-24.pdf PDF
ATTACHMENT E BLANK SPONSOR VERIFICATION SPREADSHEET.xls XLS spreadsheet
ATTACHMENT C BASE ACCESS INSTRUCTION.pdf PDF
ATTACHMENT B WD VA20250167.pdf PDF
ATTACHMENT H PRICE SCHEDULE FORM.docx DOCX document
ATTACHMENT G PPI Spreasheet.xlsx XLSX spreadsheet
ATTACHMENT F BLANK DEVGRU SPREADSHEET.xlsx XLSX spreadsheet
ATTACHMENT D SECNAV 5512 (1).pdf PDF
General Requirements 25R0019 .pdf PDF
ATTACHMENT K Oceana IDIQ Front End SPECS - 20220602.pdf PDF
ATTACHMENT A Scope of Work and Drawings.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BUILDING 355 – RENOVATE ROOMS 216-218

NAS Oceana, Dam Neck Annex, Virginia Beach VA

Amendment 0001

10 JULY 2025

1) In PART 3, 5.0 Room Requirements, Existing Corridor, Page 6:

Remove the following:

o Paint existing corridor floors with a slip resistant epoxy floor coating o Paint existing 12 inch ceramic tile base on existing CMU wall with a slip resistant epoxy floor coating

Replace with:

o Paint existing corridor floors with an epoxy paint, match existing epoxy paint in color o Paint existing 8 inch CMU base on existing CMU wall with an epoxy paint, match existing corridor floor epoxy paint in color

2) In PART 3, 6.0 Engineering Systems Requirements (ESR), C30 Interior Finishes, C3020 Floor Finishes, b. Resinous Flooring Systems, Page 9:

b. Resinous Flooring System: Provide a resinous epoxy floor coating system 3/16” thick with a slip-resistant, seamless finish in the existing corridor to include the existing 12 inch CMU wall base. Provide flooring systems smooth enough to meet the minimum requirements of this RFP or the manufacturer’s smoothness requirements, whichever is most restrictive. Maintain slip resistance with a dynamic coefficient of friction of 0.42, according to ANSI 137.1-2012.

b. Resinous Flooring System: Provide an epoxy paint floor coating system with a slip-resistant, seamless finish in the existing corridor to include the existing 8 inch CMU wall base. Epoxy paint to match existing epoxy paint in corridor. Provide flooring systems smooth enough to meet the minimum requirements of this RFP or the manufacturer’s smoothness requirements, whichever is most restrictive. Maintain slip resistance with a dynamic coefficient of friction of 0.42, according to ANSI 137.1-2012.

BUILDING 355 – RENOVATE ROOMS 216-218

NAS Oceana, Dam Neck Annex, Virginia Beach VA

Amendment 0001

10 JULY 2025

3) In PART 3, C1020 INTERIOR DOORS, Paragraph 1:

Provide flush hollow metal interior doors (maximum duty).

Provide flush hollow metal interior doors (Level 4). Doors must meet 40 STC requirements.

4) In PART 6, 2ND FLOOR DEMOLITION AND CONCEPT PLANS (A-101):

Delete the following:

The document in its entirety.

The new document in its entirety.

**End of Amendment 0001**