This is a Bid Form for FY25 Audit Repairs at Portsmouth Naval Shipyard in Kittery, Maine. The document outlines multiple Contract Line Item Numbers (CLINs) for various repair and maintenance tasks, including wall, deck, balcony, concrete, and drainage repairs across different sections (DD1, DD2, DD3). The bid form is structured with base bid (CLIN 0001) and four additional option quantities (CLIN 0002 through CLIN 0005), each covering specific repair work such as pumpwell wall repairs, tunnel spall repairs, floor delamination repairs, and drainage installation. Each CLIN includes spaces for material, labor, and equipment costs, with provisions for sub-contractor performance value, project management costs, overhead, profit, and bonding percentages. The document is a template for contractors to complete their pricing details for the proposed repair work at the naval shipyard.

View the file

Other files

File Type Posted
OF_1419 and 1419(A).pdf PDF
Solicitation Amendment N4008525B00010001_.pdf PDF
Solicitation Amendment N4008525B00010002.pdf PDF
Site Visit Sign In.pdf PDF
Solicitation Amendment N4008525B00010001.pdf PDF
Amd 1 RFIs.pdf PDF
Specifications - FY25 Audit Repairs.pdf PDF
Drawings_1859635_ FY25 Audit Repairs.pdf PDF
Pass Office Virtual Line Guidance.pdf PDF
Solicitation - N4008525B0001.pdf PDF
SECNAV 5512.pdf PDF
Site Visit Instructions.pdf PDF
DBIDS 5500.docx DOCX document
Bundle Submittal Reg.xlsx XLSX spreadsheet
PIEE Solicitation Module Instructions.pdf PDF
Local Visitor Request Form.pdf PDF
Show all 16

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BID FORM

FY25 Audit Repairs

PROJECT LOCATION

Portsmouth Naval Shipyard Kittery, Maine

CONTRACTOR:

DATE:

MATERIAL LABOR EQUIPMENT LINE ITEM

ITEM DESCRIPTION NUMBER UNIT COST COST COST TOTAL

0001AA DD2 West Wall Spall Repair 1 LS

0001AB DD2 East Side Deck Drainage Repairs 1 LS

0001AC DD2 Head End Capstan Repairs 1 LS

0001AD DD2 West Balcony Repairs 1 LS

0001AE DD3 Pumpwell Beam Repairs 1 LS

0001AF DD3 Pumpwell Concrete Repairs 1 LS

0001AG DD3 Pressure Plate repairs 1 LS

0001AH DD2 East Column Base Repairs 1 LS

Sub-KTR Performance Value (1) $ -

Prime KTR Div 01 & Project Management Costs (2) $ -

Subtotal (3) $ -

General Home Office Overhead (G&A) (%) $ -

Profit (%) $ -

Bond (%) $ -

CLIN 0001 FIRM FIXED PRICE PROPOSAL AMOUNT (4) $ -

NOTE:

Refer to Contract Docs and Repair Bid Schedule

CLIN 0001 - BASE BID

QUANTITY

PROJECT LOCATION

Portsmouth Naval Shipyard Kittery, Maine

CONTRACTOR:

DATE:

NOTE:

Refer to Contract Docs and Repair Bid Schedule

MATERIAL LABOR EQUIPMENT LINE ITEM

ITEM DESCRIPTION NUMBER UNIT COST COST COST TOTAL

0002AA DD2 Pumpwell Wall Repairs 1 LS

Sub-KTR Performance Value (1) $ -

Prime KTR Div 01 & Project Management Costs (2) $ -

Subtotal (3) $ -

General Home Office Overhead (G&A) (%) $ -

Profit (%) $ -

Bond (%) $ -

CLIN 0002 FIRM FIXED PRICE PROPOSAL AMOUNT (4) $ -

MATERIAL LABOR EQUIPMENT LINE ITEM

ITEM DESCRIPTION NUMBER UNIT COST COST COST TOTAL

0003AA DD1 Tunnel Spall Repairs 1 LS

Sub-KTR Performance Value (1) $ -

Prime KTR Div 01 & Project Management Costs (2) $ -

Subtotal (3) $ -

General Home Office Overhead (G&A) (%) $ -

Profit (%) $ -

Bond (%) $ -

CLIN 0003 FIRM FIXED PRICE PROPOSAL AMOUNT (4) $ -

CLIN 0003 - OPTION 02

QUANTITY

CLIN 0002 - OPTION 01

PROJECT LOCATION

Portsmouth Naval Shipyard Kittery, Maine

CONTRACTOR:

DATE:

NOTE:

Refer to Contract Docs and Repair Bid Schedule

MATERIAL LABOR EQUIPMENT LINE ITEM

ITEM DESCRIPTION NUMBER UNIT COST COST COST TOTAL

0004AA DD3 Floor Delam repairs 1 LS

Sub-KTR Performance Value (1) $ -

Prime KTR Div 01 & Project Management Costs (2) $ -

Subtotal (3) $ -

General Home Office Overhead (G&A) (%) $ -

Profit (%) $ -

Bond (%) $ -

CLIN 0004 FIRM FIXED PRICE PROPOSAL AMOUNT (4) $ -

MATERIAL LABOR EQUIPMENT LINE ITEM

ITEM DESCRIPTION NUMBER UNIT COST COST COST TOTAL

0005AA DD3 N Drainage install 1 LS

Sub-KTR Performance Value (1) $ -

Prime KTR Div 01 & Project Management Costs (2) $ -

Subtotal (3) $ -

General Home Office Overhead (G&A) (%) $ -

Profit (%) $ -

Bond (%) $ -

CLIN 0005 FIRM FIXED PRICE PROPOSAL AMOUNT (4) $ -

CLIN 0004 - OPTION 03

QUANTITY

CLIN 0005 - OPTION 04